- Avation Medical, Inc. v. Emkinetics, Inc.All claims unpatentablePTAB · Mar 16, 2026 · IPR2024-01375 · APJ John G New · IPR · Final written decision
Claims 1–13 are unpatentable as obvious under § 103 over Svihra, Mann, and Ponsford, and independently over Amarenco, Mann, and Ponsford.
RulingsFinal written decision- Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed board ownOther
“Ex. 1001, claim 1. In other words, to effectuate “direct” stimulation of the PTN nerve branch, a practitioner of the ’742 patent must: (1) non-invasively position an electrical stimulator relative to a portion of a patient’s body, such that a branch of a posterior tibial nerve within the first portion of the body is directly targeted by the electrical stimulator; (2) passing a current through the electrical stimulator; and (3) delivering an electrical stimulus from the electrical stimulator to the branch of the posterior tibial nerve such that the branch directly receives the electrical stimulation. Merely “placing electrodes over branches of the PTN” cannot be said, in and of itself, to “directly” target and stimulate the branches, as Petitioner argues.” slip op. at 12
- Skill levelSkill level petitioner adoptedDecided for petitioner
“of filing “would have had an undergraduate degree in the field of biomedical engineering or a related discipline, such as electrical engineering, and at least two years of experience in the design and/or analysis of biomedical devices” and that “[a]dditional work experience could substitute for a formal degree and vice versa.” Pet. 21 (citing Ex. 1003 ¶¶ 20–21). Patent Owner does not dispute Petitioner’s proposal. See generally Resp. Because Petitioner’s proposed level of ordinary skill in the art appears to be consistent with the challenged patent and prior art, we adopt this definition, and also use the term “skilled artisan” to refer to persons with such skill at the time the invention was filed.” slip op. at 13
- Expert testimonyPetitioner expert creditedOther
- Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundReasonable expectation foundUnpatentable
“the evidence of record, that a person of ordinary skill in the art would have found it obvious to modify the teachings of Svihra by non-invasively stimulating a nerve branch of the PTN, e.g., the medial or lateral plantar nerves, as taught by Ponsford, to treat OAB/urinary incontinence. A skilled artisan would have understood that the fibers of a given branch of the PTN necessarily constitute a subset of the PTN fibers, stimulation of which is known to be effective in the treatment of OAB/urinary incontinence. See Ex. 1004, 480–481. Just as it was known in the art that stimulation of the much larger sacral nerve, of which the fibers of the PTN form a part, could have beneficial effects in the treatment of incontinence, and that stimulation of the PTN itself could have a similar effect (see Ex. 1084, col. 12, ll. 33–52), so, a skilled artisan could reason, might electrical stimulation of a branch of the PTN exert a similar effect. We also agree that a person of ordinary skill in the art would have been motivated to stimulate a smaller nerve branch of the PTN, rather than the entire PTN itself, so as to minimize undesirable side effects of stimulating the entire PTN, i.e., the recruitment of downstream muscular contraction, as taught by Mann. With respect as to whether a person of ordinary skill in the art would have had a reasonable expectation of success in the treatment of OAB/incontinence via stimulation of a branch of the PTN, rather than the entire PTN itself, we agree with Petitioner that a person of ordinary skill in the art, would understand from Mann that electrical stimulation of the larger, more central sacral nerve could be employed to treat OAB/urinary incontinence, and that a subset of those PTN fibers could be electrically stimulated to achieve a similar effect. See Ex. 1084, col. 12, ll. 33–52. Such a skilled artisan could similarly reason that a subset of those PTN fibers, i.e., a branch of the PTN, particularly major branches such as the plantar nerves, could also be similarly electrically stimulated to treat OAB/urinary incontinence. Although success in such an experiment would not be guaranteed, “only a reasonable expectation of success, not absolute predictability, is necessary for a conclusion of obviousness.” In re Longi, 759 F.2d 887, 897 (Fed. Cir. 1985).” slip op. at 46
Patent outcomesUS 11,224,742 unpatentableClaim construction§ 102 anticipation§ 103 obviousnesscites Phillips · GrahamPatents in suitUS 11,224,742 - PTAB · Jan 15, 2026 · IPR2025-01231 · APJ Mary C Hoffman · IPR · Institution
The Board instituted IPR on claims 1–13 on all asserted grounds, finding a reasonable likelihood that at least one challenged claim is unpatentable.
RulingsInstitution decision- PTAB / AIA Trials › Real party in interest / privityRpi dispute resolved for petitionerDecided for petitioner
“petition identifies all real parties in interest. 35 U.S.C. § 312(a)(2). Whether an unnamed party is a real party in interest “is a highly fact-dependent question.” See Applications in Internet Time, LLC v. RPX Corp., 897 F.3d 1336, 1351, 1360 (Fed. Cir. 2018) (“AIT”); Ventex Co., Ltd. v. Columbia Sportswear N. Am., Inc., IPR2017-00651, Paper 152 at 4–5 (PTAB Jan. 24, 2019) (precedential) (citing Worlds Inc. v. Bungie, Inc., 903 F.3d 1237, 1242 (Fed. Cir. 2018)); Consolidated Trial Practice Guide, 13 (2019), https://www.uspto.gov/sites/default/files/documents/tpgnov.pdf (CTPG). “A common consideration is whether the non-party exercised or could have exercised control over a party’s participation in a proceeding.” CTPG at 16. Other considerations include whether the non-party is funding or directing the proceeding; the non-party’s relationship with the petitioner; the non-party’s relationship to the petition itself, including the nature and/or degree of involvement in the filing; and the nature of the entity filing the petition. Id. at 17–18.” slip op. at 8
- Skill levelSkill level board ownOther
“person of ordinary skill in the art (“POSITA”) “would have at least a bachelor’s degree in electrical engineering or a related field and at least two years of experience with lighting technology.” Pet. 2 (citing Ex. 1017 ¶ 35). Petitioner makes additional contentions about what a POSITA would have understood. Id. (“A POSITA would understand that all types of cameras (e.g., analog and digital, photo and video) generally involve the same lighting considerations . . . . [and] that it is important to provide light that evenly illuminates the target subject or object to minimize reflected glare and shadows.”). Patent Owner contends that a POSITA would have at least: (a) a bachelor’s degree in electrical engineering, optical engineering, or a related field; (b) two years of practical experience in designing and developing lighting systems, particularly those integrated with electronic devices such as webcams or computer monitors; and (c) knowledge of user-interface considerations for consumer electronics . . . . Additional experience can substitute for education and vice versa. Prelim. Resp. 12 (citing Ex. 2036 ¶ 48). Patent Owner disputes Petitioner’s contentions regarding what a POSITA would have understood. Prelim. Resp. 12–13 (“[O]ne of ordinary skill in the art would have understood that analog and digital cameras have different operating principles and lighting requirements [and] Petitioner’s lack of appreciation for the suitability and unsuitability of different lights for different applications infects and dooms its invalidity analysis.” (citing Ex. 2036 ¶¶ 36–47)). and years of experience required for a POSITA. Pet. 2; Prelim. Resp. 12. For purposes of this Decision, we consider a person of ordinary skill in the art to have a bachelor’s degree in electrical engineering or related field and two years of practical experience in lighting technology, and that additional experience may substitute for education and vice versa, which is consistent with the level of skill reflected in the ’729 patent and prior art of record. See Exs. 1001, 1005–1010, 1012–1015; see also Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001) (explaining that specific findings regarding ordinary skill level are not required “where the prior art itself reflects an appropriate level and need for testimony is not shown” (quoting Litton Indus. Prods., Inc. v. Solid State Sys. Corp., 755 F.2d 158, 163 (Fed. Cir. 1985))).” slip op. at 12
- Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther
“Patent Owner agrees that the Board need not formally construe any claim terms in order to adjudicate the merits of the Petition and argues Petitioner fails to show unpatentability of any claim under any reasonable construction of the claims. Prelim. Resp. 13 (citing Ex. 2036 ¶ 51). We determine that no express claim construction is necessary to determine whether institution is warranted in this proceeding. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (holding that only terms in controversy must be construed “and only to the extent necessary to resolve the controversy”) (citing Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)).” slip op. at 14
- PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted
“claimed subject matter and the prior art are “such that the subject matter as a whole would have been obvious at the time the invention was made to a person having ordinary skill in the art to which said subject matter pertains.” KSR Int’l Co. v. Teleflex Inc., 550 U.S. 398, 406 (2007). When a ground in a petition is based on a combination of references, we consider “whether there was an apparent reason to combine the known elements in the fashion claimed by the patent at issue.” Id. at 418 (citing In re Kahn, 441 F.3d 977, 988 (Fed. Cir. 2006)). We base our obviousness inquiry on factual considerations including (1) the scope and content of the prior art, (2) any differences between the claimed subject matter and the prior art, (3) the level of skill in the art, and (4) any objective indicia of obviousness or non-obviousness that may be in evidence.14 See Graham, 383 U.S. at 17–18.” slip op. at 24
Claim construction§ 103 obviousnesscites Phillips · KSR · GrahamPatents in suitUS 7,841,729 - Exotec Product France SAS / Exotec North America Inc. et al. v. Opex CorporationAll claims unpatentablePTAB · Oct 28, 2025 · IPR2024-00850 · APJ Arthur M Peslak · IPR · Final written decision
Claims 1, 3–12, 14, and 23–27 are unpatentable as obvious over Raizer and Hangzhou.
RulingsFinal written decision- Skill levelOther
“B. Level of Ordinary Skill in the Art We consider the asserted grounds of unpatentability in view of the” slip op. at 9
- Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther
“C. Claim Construction Neither Petitioner nor Patent Owner proposes an express construction” slip op. at 10
- Obviousness (§103) › Motivation to combine / reasonable expectation of successUnpatentableMotivation foundUnpatentable
“that it would improve similar devices in the same way, using the technique is obvious unless its actual application is beyond his or her skill.” KSR, 550 U.S. at 417. In this case, we must determine whether one of ordinary skill in the art would recognize that Hangzhou’s disclosure of driving its auto-guided trolleys 200 under shelves 100 would improve the operation of Raizer’s system in the same way. For us to resolve this question in Petitioner’s favor, Petitioner must provide “some articulated reasoning with some rational underpinning to support the legal conclusion of obviousness.” Id. at 418 (citing In re Kahn, 441 F.3d 977, 988 (Fed. Cir. 2006)). However, bodily incorporation, i.e., “an actual physical substitution of” Hangzhou’s auto-guided trolleys or operating software into Raizer’s system, is not required. See In re Mouttet, 686 F.3d 1322, 1332 (Fed. Cir. 2012) (“It is well-established that a determination of obviousness based on teachings from multiple references does not require an actual, physical substitution of elements.”); In re Nievelt, 482 F.2d 965, 968 (CCPA 1973) (“Combining the teachings of references does not involve an ability to combine their specific structures.”).” slip op. at 23
Patent outcomesUS 11,472,632 unpatentableClaim construction§ 103 obviousnesscites KSR · GrahamPatents in suitUS 11,472,632 - PTAB · Oct 16, 2025 · IPR2025-00776 · APJ John G New · IPR · Institution
Instituted review of claims 9, 11, 32–58, 60–62, and 64–67 on all remaining petition grounds, after finding a reasonable likelihood that claim 9 is unpatentable over Thomas and Faucette.
RulingsInstitution decision- PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted
“For the reasons set forth below, we determine that Petitioner has demonstrated that there is a reasonable likelihood that at least one of claims 9, 11, 32–58, 60–62, and 64–67 of the ’802 patent is unpatentable, and we on the Grounds set forth in the Petition.” slip op. at 2
- Settled expectationsOther
“Patent Owner also filed a Request with the Acting Director of the USPTO seeking discretionary denial of institution of inter partes review (Paper 6, the “Request”). Petitioner subsequently filed a brief opposing Patent Owner’s Request (Paper 8). On September 3, 2025, the Acting Director denied Patent Owner’s Request for discretionary denial of institution of inter partes review and referred the case to the panel for an institution decision on the merits (Paper 11).” slip op. at 2
- Skill levelSkill level petitioner adoptedDecided for petitioner
“Petitioner asserts that a person of ordinary skill would have an M.D. or a Ph.D. degree in virology, immunology, and vaccinology, and at least 3 years of experience in one or more of the research, design, development, and testing of antiviral vaccines. Pet. 17. Petitioner asserts that a person of ordinary skill may be part of a multidisciplinary team having such experience. Id. (citing Ex. 1002 ¶ 81). Patent Owner does not dispute the level of skill asserted by Petitioner.” slip op. at 9
- Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther
“Neither party requests construction of any claim terms. Petitioner asserts that all claim terms should be given their ordinary and customary meaning, and Patent Owner does not disagree. See Pet. 17. Accordingly, we find, for the purposes of this Decision, that no terms of the challenged claims requires construction beyond the ordinary and customary meaning of the terms, as understood by a person of ordinary skill in the art at the time of the invention. Phillips, 415 F.3d at 1312–13; see also Vivid Techs., Inc. v. construes claims only to the extent necessary to resolve a dispute).” slip op. at 10
Claim construction§ 103 obviousnessDiscretionary denialcites Phillips · GrahamPatents in suitUS 11,730,802 - PTAB · Oct 14, 2025 · IPR2025-00685 · APJ John G New · IPR · Institution
The Board instituted IPR on claims 1–23 and all petitioned grounds, finding a reasonable likelihood that the claims are obvious over Wei and Liu.
RulingsInstitution decision- PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted
“Summary Based upon the record as presently developed, we conclude that Petitioner has met its burden of showing a reasonable likelihood of showing at trial that at least claim 1 of the ’370 patent is obvious over the cited prior art. Because we determine that Petitioner has demonstrated a reasonable likelihood of success at trial in showing that at least one claim is unpatentable on at least one of the stated Grounds, we institute inter partes review of all challenged claims of the ’370 patent, based on all of the remaining grounds identified in the Petition. See 37 C.F.R. § 42.208(a); SAS Inst., Inc. v. Iancu, 584 U.S. 357, 371 (2018); PGS Geophysical AS v. Iancu, 891 F.3d 1354, 1360 (Fed. Cir. 2018) (interpreting the statute to require “a simple yes-or-no institution choice respecting a petition, embracing all challenges included in the petition”).” slip op. at 44
- Skill levelSkill level board ownOther
“appears to be generally consistent with the level of skill presented in the cited prior art. See generally, e.g., Exs. 1005–1008; see also Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001) (the prior art itself may reflect an appropriate level of skill in the art). However, at this point we reject the portion of Petitioner’s proposed definition that includes having “access to other individuals with that knowledge and experience,” as not reflecting the individual level of skill of a given skilled artisan. See, e.g., Custom Accessories, Inc. v. Jeffrey-Allan Indus., Inc., 807 F.2d 955, 962 (Fed. Cir. 1986) (holding that “[t]he person of ordinary skill is a hypothetical person who is presumed to be aware of all the pertinent prior art. The actual inventor’s skill is not determinative”) (emphasis added, footnotes omitted). Consequently, and for the purposes of this Decision, we adopt Petitioner’s proposed definition as defining a person of ordinary skill in the art as a person who would have had “a Ph.D. in immunology, molecular biology, cellular biology, or a similar field, or an M.D. with similar experience, and would further have had at least five years of experience with antibodies and antibody engineering.”” slip op. at 6
- Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)Plain and ordinary meaningOther
“Petitioner states that no term of the challenged claims requires construction to resolve the challenges in this Petition. Pet. 32. Patent Owner does not contest Petitioner’s assertion. See generally Prelim. Resp. We find, for the purposes of this Decision, that no terms of the challenged claims require construction beyond the ordinary and customary meaning of the terms, as understood by a person of ordinary skill in the art at the time of the invention. Phillips, 415 F.3d at 1312–13.” slip op. at 7
- Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundInstituted
“We find, based upon the present record and for the purposes of this Decision, that Petitioner has sufficiently established that a person of ordinary skill in the art would have been motivated to combine the teachings of Wei and Liu to determine the activity and suitability of Liu’s humanized anti- EGFR antibodies in an ADC. We acknowledge that Liu is silent regarding the pH selectivity or tissue preference of its binding affinity, but Patent Owner points to no prior art reference that would have informed a skilled artisan upon this point or that would have discouraged a person of ordinary skill in the art from combining the references. See fn.7, supra. And, even if a skilled artisan might have recognized that Liu’s humanized cetuximab might have been potentially problematic if it failed to show pH-selective activity like Wei’s Y104D, the mere fact that some disadvantage may come with an advantage when combining prior art does not foreclose their combination under § 103. Medichem, S.A. v. Rolabo S.L., 437 F.3d 1157, 1165 (Fed. Cir. 2006). In the instance of Liu’s humanized anti-EGFR antibody, a person of ordinary skill in the art would have recognized that its advantages (enhanced activity against tumor cells compared to chimeric cetuximab, thus requiring smaller dosages) could balance or outweigh its possible disadvantages (e.g., possible activity against non-tumor cells). Furthermore, it is in the nature of scientific research to continue to try new substitutions in drug therapy, even if a promising candidate has been discovered. As the Supreme Court stated in KSR: When there is a design need or market pressure to solve a problem and there are a finite number of identified, predictable solutions, a person of ordinary skill has good reason to pursue the known options within his or her technical grasp. If this leads to the anticipated success, it is likely the product not of innovation but of ordinary skill and common sense. In that instance the fact that a combination was obvious to try might show that it was obvious under § 103. 550 U.S. at 421.” slip op. at 39
Claim construction§ 103 obviousnesscites Phillips · KSRPatents in suitUS 10,792,370 - Tanklogix, LLC v. Sitepro, Inc.Institution deniedPTAB · Oct 10, 2025 · IPR2025-00653 · APJ Bart A Gerstenblith · IPR · Institution
The Board denied institution on all claims because the Petition did not show a reasonable likelihood that any challenged claim was unpatentable over the asserted grounds.
RulingsInstitution decision- PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied
“An inter partes review may be instituted only if “the information presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2
- Skill levelSkill level patent owner adoptedDecided for patent owner
“The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’504 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 12
- Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther
“Additionally, only terms that are in controversy need to be construed, and these need be construed only to the extent necessary to resolve the controversy. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’”) (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)). The parties assert that each claim term should be construed in accordance with its plain and ordinary meaning. Pet. 9; Prelim. Resp. 4 (citing Ex. 2009 ¶ 72); see Ex. 1002 ¶ 22 (opining the same). And, in the respective claim construction sections of their briefs, the parties do not propose any claim terms for express construction. We agree with the parties that no claim terms require express construction to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 13
- Expert testimonyPetitioner expert discountedDecided for patent owner
“Ex. 1002 ¶ 47. As reflected above, Dr. Wooley’s testimony as to element [1.2] does not even assert that Cardamone discloses a tank, let alone one or more sensors disposed at a tank as recited in element [1.2]. Thus, Dr. Wooley’s testimony does not support Petitioner’s argument on this issue.” slip op. at 18
Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · GrahamPatents in suitUS 11,726,504 - Tanklogix, LLC v. Sitepro, Inc.Institution deniedPTAB · Oct 10, 2025 · IPR2025-00652 · APJ Bart A Gerstenblith · IPR · Institution
The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–23 and 25–30 were unpatentable over the asserted grounds.
RulingsInstitution decision- PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied
“presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2
- Skill levelSkill level patent owner adoptedDecided for patent owner
“The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’403 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 12
- Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther
“The parties assert that each claim term should be construed in accordance with its plain and ordinary meaning. Pet. 10; Prelim. Resp. 4 (citing Ex. 2009 ¶ 73); see Ex. 1002 ¶ 22 (opining the same). And, in the respective claim construction sections of their briefs, the parties do not propose any claim terms for express construction. We agree with the parties that no claim terms require express construction to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 13
- Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable
“We agree with Patent Owner that the Petition fails to demonstrate that Kahn discloses element [1.2] because the evidence cited does not disclose a “first computer system being configured to provide remote control of the first pump or first valve” (i.e., a fluid-handling device). Kahn is directed to providing access to fluid sensing data and analyzing and providing visual information on that data, but Petitioner has not identified any disclosure of the capability to remotely control fluid-handling devices. See, e.g., Ex. 1005, code (54), 1:27–36, 2:50–3:2. More specifically, Kahn’s disclosures that Petitioner relies on for allegedly teaching remote control are deficient. We discuss each. First, Petitioner points to the following, “[f]or instance, as illustrated in FIG. 1C, a fluid control device such as a valve 15A is located on the input side of a sen[s]or unit 110.” Ex. 1005, 8:19–21, cited in Pet. 13. This portion of Kahn, however, does not disclose remote control. Second, Petitioner cites to the following: Finally, or in addition to, the communication unit 112B can include on-site alerts such as optical (indicator lights), audible alerts (e.g., alarm sounds), tactile (e.g., vibration of the unit) or can be interfaced to an appropriate control valve for simply shutting off the supply of fluid upon the detection of emergency events, for instance. Pet. 13 (citing Ex. 1005, 10:62–67). We agree with Patent Owner that this portion of Kahn teaches on-site alerts and local control of the fluid-handling device. See Prelim. Resp. 7. This portion of Kahn does not disclose remote control.” slip op. at 18
Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · GrahamPatents in suitUS 11,294,403 - Tanklogix, LLC v. Sitepro, Inc.Institution deniedPTAB · Oct 10, 2025 · IPR2025-00651 · APJ Bart A Gerstenblith · IPR · Institution
The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–3, 6, 7, and 9–20 were unpatentable over any asserted ground.
RulingsInstitution decision- PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied
“presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2
- Skill levelSkill level patent owner adoptedDecided for patent owner
“The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’680 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 11
- Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed patent owner constructionDecided for patent owner
“target value” is part of a command that is sent from a computing device to a server and then to a controller. The controller then receives a measurement of the fluid by a sensor and determines whether the measurement satisfies the “target value.” If the measurement does not satisfy the “target value,” further operations are undertaken. The recited operation sequence makes clear that the plain and ordinary meaning of “target value” is not as Dr. Wooley opines because the particular operating condition that a device is in at a particular time is represented by the measurement taken by the sensor, 11 Some claim language less relevant to construing “target value” was omitted for ease of reference. which the controller then uses to determine whether the measurement satisfies the “target value.” Additionally, claim 1 recites that the “target value” is sent as part of a command to the controller. The “target value” is not sent to the controller from the sensor, as might be expected if the plain and ordinary meaning of “target value” were as Dr. Wooley opines. Petitioner and Dr. Wooley’s construction would also result in “target value” meaning effectively the same thing as the measurement of the fluid by the sensor, a concept that is separately recited in claim 1 and to which the “target value” is compared. The Specification of the ’680 patent does not support Petitioner’s understanding of the plain and ordinary meaning of “target value.” Although the Specification does not recite “target value,” it recites “target state,” and describes “target state” sufficiently to understand the plain and ordinary meaning of “target” as used in “target value” and “target state.” In particular, the ’680 patent explains that “[i]n some embodiments, the process 104 includes receiving, via a network interface, from a remote user device, (e.g., via a command-center server) a command to change a state of a fluid-handling device to a target state.” Ex. 1001, 11:48–51. This portion reflects that the command is seeking to change a state of a fluid-handling device to a target state. In other words, the “target value” or “target state” is not generally “the particular operating condition that a device is in at a particular time”; rather, it is a value or state that the fluid-handling device is desired to be in, as Patent Owner and Dr. Durham explain. Additionally, just as claim 1 recites a directional component for the “target value” to be sent to the controller in a command, so too does the Specification describe a “target state” as being sent in a command from a remote user device. Thus, the Specification clearly supports the plain and ordinary meaning proposed by Patent Owner and Dr. Durham and not the plain and ordinary meaning proposed by Petitioner and Dr. Wooley. slip op. at 14
- Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable
“time-stamped process data, report exception therein to the remote host, and extract and transmit time-stamped process data to the remote host.” Ex. 1005, Abst. (emphases added). Almadi explains that its remote field systems must include a plurality of controller units “to issue commands to, and gather and process data from a plurality of field devices, including remote systems and instruments, . . . [and] a database server for the storage of process data retrieved from the remote subsystems and instruments.” Id. at 2:22–30 (emphases added). Based on these disclosures, we agree with Patent Owner that Petitioner has not established that Almadi discloses element [1.4]. Specifically, the teachings from Almadi identified by Petitioner refer to process data, which is data retrieved from the remote subsystems/field devices. Thus, we understand that Almadi’s teaching—of using an Ethernet switch to transmit “process data”—describes transmitting data from the remote subsystems/field devices. See Ex. 1005, 3:13–17, cited in Pet. 15. But claim 1 and particularly element [1.4], recites “sending, with the server, the target value to the network address [which identifies a controller of the fluid-handling device13] via the network,” which is different than sending process data from the field devices to the remote host or database server for storage.” slip op. at 19
Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · GrahamPatents in suitUS 11,175,680 - Tanklogix, LLC v. SiteproInstitution deniedPTAB · Oct 10, 2025 · IPR2025-00650 · APJ Sheila F Mcshane · IPR · Institution
The Board denied institution because Petitioner did not show a reasonable likelihood that claims 18–32 and 34 were unpatentable over Kahn or Kahn and Gutierrez.
RulingsInstitution decision- PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied
“information presented in the petition . . . and any response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). Upon consideration of the Petition, the Preliminary Response, and the evidence of record, we determine that Petitioner has not established a reasonable likelihood of prevailing with respect to the unpatentability of at least one claim of the ’871 patent. Accordingly, for the reasons that follow, we decline to institute an inter partes review of claims 18–32 and 34 of the ’871 patent.” slip op. at 2
- Skill levelSkill level patent owner adoptedDecided for patent owner
“The respective proposed levels of qualifications for a person of ordinary skill in the art are similar, with Patent Owner proposing two years of experience compared to Petitioner proposing significant experience with remotely controlling fluid-handling devices, like SCADA systems. Patent Owner also proposes more extensive experience in lieu of educational experience. While we find Petitioner’s proposed qualifications to be acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of skill necessary to understand and implement the teachings of the ’871 patent and the asserted prior art. Our analysis and findings herein, however, do not turn on any differences in the qualifications adopted.” slip op. at 8
- Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther
“We determine that we need not expressly construe any claim terms to resolve the parties’ disputes on the current record. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“[W]e need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))).” slip op. at 10
- Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable
“actuators and the remote control of fluid handling devices, including the receipt with the user-interface module of “a user command to actuate an actuator via a presented control interface” (limitation [18.7]) and “account authorized to send commands to remotely control fluid handling devices” (limitation [18.11]). We agree with Patent Owner that the Petition fails to demonstrate that Kahn discloses or teaches these limitations because the evidence does not provide support that there is remote control of fluid handling devices or the use of a user command on a control interface to send a command to a fluid handling device, for instance. Kahn is directed to providing access to fluid sensing data and analyzing and providing visual information on that data, but we do not discern that it teaches or discloses the capability to remotely control fluid handling devices. See, e.g., Ex. 1005, code (54), 1:27–36, 2:50–3:2. More specifically, the Kahn disclosures that Petitioner repeatedly relies upon for allegedly teaching this control are deficient. See Ex. 1005, 10:62–67, 14:35– 15:2, 15:62–16:32; see also Pet. 12–14, 16–18. Kahn discloses that “the communication unit 112B can include on-site alerts such as optical (indicator lights), audible alerts (e.g., alarm sounds), tactile (e.g., vibration of the unit) or can be interfaced to an appropriate control valve for simply shutting off the supply of fluid upon the detection of emergency events, for instance.” Ex. 1005, 10:62–67. Communication unit 112B is part of the local “sensor unit,” wherein the detection conditions determined by the sensor are communicated to remote devices by communication unit 112B. See id. at 3:31–33, 5:62–6:2, 6:27–35, 7:33–37, 13:7–12, Figs. 1A–1C. Kahn discloses that the sensor units, which include communication units 112B, can be located near shut-off valves and can communicate with distant locations. See id. at 11:1–13. There are no disclosures, however, in the above passages that there is remote control of fluid handling devices, that there is a user command on a control interface that actuates an actuator, or that there is a command sent to the facility actuators via a network connection, as required in limitations [18.5]–[18.7] and [18.9]–[18.12], respectively. Rather, the disclosure indicates that the communication unit 112B includes on-site alerts and that the local (non-remote) communication unit 112B can be interfaced with the control valve.” slip op. at 18
Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · GrahamPatents in suitUS 10,488,871 - Solus Advanced Materials Co., Ltd. v. SK Nexilis Co., Ltd.Rehearing deniedPTAB · Oct 7, 2025 · IPR2024-01462 · APJ Jo-Anne M Kokoski · IPR · Rehearing
The Board denied Solus’s rehearing request, leaving institution denied for claims 1–8 because the petition did not adequately show motivation to combine Hanafusa and Dobashi.
RulingsRehearing decision- RehearingRehearing, deniedDenied
“of the decision de novo, but instead review the decision for an abuse of discretion. 37 C.F.R. § 42.71(c). An abuse of discretion may be determined “if a decision is based on an erroneous interpretation of law, if a factual finding is not supported by substantial evidence, or if the decision represents” slip op. at 2
- Obviousness (§103) › Motivation to combine / reasonable expectation of successNot shown unpatentableMotivation not foundNot shown unpatentable
“In particular, neither Petitioner nor Dr. Josefowicz adequately explain why a POSITA looking for ways to make Hanafusa’s surface roughness low-profile would look to methods to achieve Dobashi’s RSm values. Dobashi teaches that because RSm “can be adopted as the period of waviness, RSm can also be used as an indicator for judgment of the surface.” Ex. 1005, 2:66–3:1, 6:23–26. Dobashi explains that waviness is “an indicator for determining whether the fine pattern forming performance is good or bad,” and “[t]he surface has small waviness and is smooth when RSm is large, and the surface has large waviness Dobashi also teaches that surface roughness Rzjis is used as a low-profile indicator. Ex. 1005, 2:66–3:1. Dobashi, therefore, teaches that RSm is an indicator of surface waviness, which Dobashi explains is different than surface roughness. Id. at 2:66– 3:3, 6:23–29. Given these teachings in Dobashi, neither Petitioner nor Dr. Josefowicz sufficiently explains how or why a POSITA would have been motivated to implement Dobashi’s RSm values to make Hanafusa’s surface roughness low-profile. See Pet. 10–12; Ex. 1003 ¶¶ 46–52.” slip op. at 4
§ 103 obviousnessPatents in suitUS 11,346,014
Holdings, summaries, rulings, issues, outcomes, winners and claim constructions shown for a decision were generated by a large language model reading the opinion. They are a guide to the decision, not the decision. Confirm every one against the court's own text before relying on it. Outcomes read from the patent owner’s side. Party names are extracted from the decision and are missing on about 900 short Director denials and scans, which carry the trial number instead.