  • PTAB · May 31, 2024 · IPR2024-00255 · APJ Patrick R Scanlon · IPR · Institution

    The Board instituted IPR of claims 1–4 and 6–11 on both asserted obviousness grounds, finding a reasonable likelihood that Petitioner would prevail on at least one challenged claim.

    RulingsInstitution decision
    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Decided for petitioner

      “that, because judgments have been entered in the district court actions, there is finality as that relates to Fintiv issues. In a similar instance, where a district court’s § 101 determination was appealed to the Federal Circuit, the Director determined that the Board had the authority to institute an inter partes review and a Fintiv analysis should be performed. See Volvo Penta of the Americas, LLC v. Brunswick Corp., IPR2022-01366, Paper 15 at 1–8 (PTAB May 2, 2023). The Director has additionally distinguished a Fintiv analysis under similar circumstances to those here, where “the district court’s judgment of invalidity under 35 U.S.C. § 101, i.e., a statutory ground that could not have been raised before the Board, does not raise concerns of inefficient duplication of efforts or potentially inconsistent results between the Board and the district court.” AviaGames, Inc., Paper 14 at 3. Further, the Director determined that, “the challenged claims have not yet been cancelled and remain in force until the opportunity to appeal has been exhausted,” noting that “[b]y the time an appeal will have concluded, Petitioner will be barred under 35 U.S.C. § 315(b) from bringing a new challenge in an IPR petition.” Id. at 3–4. Fintiv states that “a district court stay of the litigation pending resolution of the PTAB trial allays concerns about inefficiency and discern that the § 101 issues addressed in the Federal Circuit appeal would duplicate the anticipation and obviousness issues addressed here. Accordingly, given the limited § 101 issues on appeal, we do not discern there are any concerns about duplication of efforts. Moreover, because of the uncertainty of the timing of any remand from the Federal Circuit to the district court to address any anticipation or obviousness issues, the present circumstances with a pending appeal effectively act as a stay on the assessment of invalidity issues.9” slip op. at 12

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “review. See 35 U.S.C. § 314 (2018); 37 C.F.R. § 42.4(a) (2022). To institute an inter partes review, we must determine that the information presented in the Petition shows “a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). For the reasons set forth below, we determine that Petitioner has demonstrated a reasonable likelihood that it would prevail with respect to at least one challenged claim. Accordingly, we institute an inter partes review of the challenged claims on the grounds set forth in the Petition.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “of ordinary skill in the art. Pet. 7 n.2 (citing Ex. 1003 ¶¶ 8, 10, 26). Dr. Sundaresan testifies that a person having ordinary skill in the art “had at least a Bachelor’s degree in electrical engineering, computer science, or a similar discipline, and at least two years of experience in the field working with . . . navigation and/or geolocation systems,” and “[s]uperior education could compensate for a deficiency in work experience, and vice-versa.” Ex. 1003 ¶ 8. For the purposes of its Preliminary Response, Patent Owner does not dispute Petitioner’s definition of the level of ordinary skill in the art. Prelim. Resp. 32. For purposes of this Decision, we adopt Petitioner’s proposal as reasonable and consistent with the ’104 patent and the prior art. See” slip op. at 7

    • Prior constructionPrior construction adoptedDecided for petitioner

      “For purposes of this Decision, we adopt the district court’s construction of “grid point” as “a point associated with representative calibration data for an area.” See Ex. 1054, 18–20. This construction is consistent with the claim language and the specification of the ’104 patent and is further supported by the reasoning provided by the district court’s claim construction order. See id. We do not discern a need to construe explicitly any other claim language at this juncture because doing so would have no effect on our analyses below of Petitioner’s asserted grounds and will not assist in resolving the present controversy between the parties. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’”) (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)).” slip op. at 9

    Claim construction§ 103 obviousnessDiscretionary denialcites Graham
    Patents in suitUS 7,561,104
  • PTAB · May 10, 2024 · IPR2024-00259 · APJ Sheila F Mcshane · IPR · Institution

    The Board instituted inter partes review of claims 1, 7, 9, 32, 38, and 40 on the asserted obviousness ground over Bhattacharya and Yost.

    RulingsInstitution decision
    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “that because judgements have been entered in the district court actions, this suggests finality. In a similar instance in Volvo, where a district court’s § 101 determination was appealed to the Federal Circuit, the Director determined that the Board had the authority to institute an inter partes review and a Fintiv analysis should be performed. See Volvo Penta of the Americas, LLC v. Brunswick Corp., IPR2022-01366, Paper 15 at 1–8 (PTAB May 2, 2023). The Director has additionally distinguished the Fintiv analysis in AviaGames under similar circumstances to those here, where “the district court’s judgment of invalidity under 35 U.S.C. § 101, i.e., a statutory ground that could not have been raised before the Board, does not raise concerns of inefficient duplication of efforts or potentially inconsistent results between the Board and the district court.” AviaGames, IPR2022- 00530, Paper 14 at 3 (PTAB Mar. 2, 2023) (Decision on Director Review). Further, the Director determined that “the challenged claims have not yet been cancelled and remain in force until the opportunity to appeal has been exhausted,” noting that “[b]y the time an appeal will have concluded, Petitioner will be barred under 35 U.S.C. § 315(b) from bringing a new challenge in an IPR petition.” Id. at 3–4. Fintiv states that “a district court stay of the litigation pending resolution of the PTAB trial allays concerns about inefficiency and duplication of efforts.” Fintiv at 6. In view of the circumstances, we do not discern that the § 101 issues addressed in the Federal Circuit appeal duplicate the obviousness issues addressed here. The timing of the progress of the appeal and any potential remand to the district court is uncertain. Accordingly, given the limited § 101 issues on appeal, we do not discern there are any concerns about duplication of efforts. Moreover, because of the uncertainty of the timing of any remand from the Federal Circuit to the district court to address any obviousness issues, the present circumstances with a pending appeal effectively act as a stay on the assessment of invalidity issues.” slip op. at 10

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “viii. Conclusion Accordingly, we are persuaded that Petitioner has demonstrated a reasonable likelihood that it would prevail in showing that claim 1 is rendered obvious by Bhattacharya and Yost.” slip op. at 32

    • Skill levelSkill level petitioner adoptedOther

      “IV. ANALYSIS A. Level of Ordinary Skill in the Art Petitioner asserts that a person of ordinary skill in the art: would have had at least a Bachelor’s degree in electrical engineering, computer science, or a similar discipline, and at least two years of experience in the field working with working with navigation and/or geolocation systems. Pet. 6–7 (citing Ex. 1003 ¶ 8). Petitioner also contends that additional education could compensate for less work experience and vice versa. Id. at 7. For the purposes of the Preliminary Response, Patent Owner adopts Petitioner’s asserted level of ordinary skill in the art. Prelim. Resp. 26. For the purposes of this Decision, we adopt the assessment offered by Petitioner, except for the inclusion of “at least,” as it is consistent with the ’753 patent and the prior art before us. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001).” slip op. at 16

    • Prior constructionPrior construction adoptedOther

      “patent and district court issued claim constructions for some terms that were disputed. Ex. 1020; Ex. 1025. Petitioner uses the district court’s construction or the agreed-upon construction for the terms “calibration data,” “calibration points,” “grid point,” “network measurement report,” and the order of the “providing,” “generating,” “evaluating,” and “selecting” steps of claim 1. Pet. 7–9 (citing Ex. 1020; Ex. 1025). Petitioner proposes that all terms should be interpreted consistent with the Phillips standard. Id. at 7. Patent Owner “does not dispute Petitioner’s statement on claim construction for the purposes of this Preliminary Response” and “reserves the right to present arguments on the constructions should the Petition be instituted.” Prelim. Resp. 26. For the purposes of this Decision, we will use the district court’s claim constructions and those agreed-upon by the parties in the litigations, where the adoption of those constructions have been agreed to by the parties at this juncture in this proceeding. We determine that we need not expressly construe any other claim terms at this juncture. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))).” slip op. at 17

    Claim construction§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 8,406,753
  • PTAB · May 10, 2024 · IPR2024-00032 · APJ Brian D Range · IPR · Institution

    The Board instituted IPR on claims 1–5, 9, 11, 12, 14–16, 18–22, 25, 27, 29, 31, 32, and 35 on all asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “unless the information presented in the petition “shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” The following findings of fact and conclusions of law are not final, but are made for the sole purpose of determining whether Petitioner meets the threshold for initiating review. Any final decision shall be based on the full trial record, including any response timely filed by Patent Owner. Any arguments not raised by Patent Owner in a timely-filed response may be deemed waived. For the reasons stated below, we determine that Petitioner has established a reasonable likelihood that it would prevail with respect to at least one claim. We hereby institute an inter partes review as to claims 1–5, 9, 11, 12, 14–16, 18–22, 25, 27, 29, 31, 32, and 35 of the ’494 patent based upon Petitioner’s asserted grounds of unpatentability.” slip op. at 2

    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “resolution of the PTAB trial allays concerns about inefficiency and duplication of efforts.” Fintiv at 6. In view of the circumstances, we do not discern that the § 101 issues addressed in the Federal Circuit appeal would duplicate the anticipation and obviousness issues addressed here. Accordingly, given the limited § 101 issues on appeal, we do not discern there are any concerns about duplication of efforts. Moreover, because of the uncertainty of the timing of any remand to the district court to address any anticipation or obviousness issues, the present circumstances with a pending appeal effectively act as a stay on the assessment of invalidity issues.” slip op. at 15

    • PTAB / AIA Trials › Discretionary denial › §325(d) same art / argumentsDenied

      “an IDS in the ’494 patent, we agree with Patent Owner that the record shows that Bhattacharya and Spain10 were listed on an IDS during prosecution of the parent ’358 patent, which the ’494 patent Examiner was required to consider. Prelim. Resp. 5 (citing MPEP 609.02). As such, we determine that Bhattacharya and Spain were presented previously to the Office. See Prelim. Resp. 9; Advanced Bionics at 7–8. We also agree with Patent Owner that the addition of Meunier does not substantially impact our § 325(d) analysis because of the Petition’s limited reliance on this reference. For these reasons, we determine that the first prong of Advanced Bionics is met and turn to the second prong.” slip op. at 23

    • Skill levelSkill level petitioner adoptedOther

      “would have at least a Bachelor’s degree in electrical engineering, computer science, or a similar discipline, and at least two years of experience in the field working with working with navigation and/or geolocation systems. 1003 ¶ 8; Pet. 6, n.2. According to Petitioner, “[s]uperior education could compensate for a deficiency in work experience, and vice-versa.” Ex. 1003 ¶ 8. Patent Owner does not dispute the level of ordinary skill in the art. Prelim Resp. 43. For purposes of this Decision, we adopt Petitioner’s proposal as reasonable and consistent with the ’494 patent specification and the prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001) (the prior art may reflect an appropriate level of skill in the art).” slip op. at 8

    Claim construction§ 102 anticipation§ 103 obviousnessDiscretionary denialcites KSR · Graham
    Patents in suitUS 8,786,494
  • PTAB · May 10, 2024 · IPR2024-00031 · APJ Patrick R Scanlon · IPR · Institution

    The Board instituted IPR of claims 15–20, 24, 26, and 27 on all asserted grounds, finding a reasonable likelihood of success on anticipation and obviousness.

    RulingsInstitution decision
    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “time it was made, 35 U.S.C. § 103 requires us to resolve the level of ordinary skill in the pertinent art at the time of the invention. Graham v. John Deere Co., 383 U.S. 1, 17 (1966). The person of ordinary skill in the art is a hypothetical person who is presumed to have known the relevant art at the time of the invention. In re GPAC, Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995). Factors that may be considered in determining the level of ordinary skill in the art include, but are not limited to, the types of problems encountered in the art, the sophistication of the technology, and educational level of active workers in the field. Id. In a given case, one or more factors may predominate. Id.” slip op. at 6

    • Prior constructionPrior construction adoptedDecided for petitioner

      “district-court-type standard, as described in Phillips v. AWH Corp., 415 F.3d 1303 (Fed. Cir. 2005) (en banc). See 37 C.F.R. § 42.100(b). Under that standard, we generally give claim terms their ordinary and customary meaning, as would be understood by a person of ordinary skill in the art at the time of the invention, in light of the language of the claims, the specification, and the prosecution history. See Phillips, 415 F.3d at 1313–14. Although extrinsic evidence, when available, may also be useful when construing claim terms under this standard, extrinsic evidence should be considered in the context of the intrinsic evidence. See id. at 1317–19.” slip op. at 7

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction needed

      “district-court-type standard, as described in Phillips v. AWH Corp., 415 F.3d 1303 (Fed. Cir. 2005) (en banc). See 37 C.F.R. § 42.100(b). Under that standard, we generally give claim terms their ordinary and customary meaning, as would be understood by a person of ordinary skill in the art at the time of the invention, in light of the language of the claims, the specification, and the prosecution history. See Phillips, 415 F.3d at 1313–14. Although extrinsic evidence, when available, may also be useful when construing claim terms under this standard, extrinsic evidence should be considered in the context of the intrinsic evidence. See id. at 1317–19.” slip op. at 7

    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Decided for petitioner

      “Fintiv states that “a district court stay of the litigation pending resolution of the PTAB trial allays concerns about inefficiency and duplication of efforts.” Fintiv at 6. In view of the circumstances, we do not discern that the § 101 issues addressed in the Federal Circuit appeal would duplicate the anticipation and obviousness issues addressed here. Accordingly, given the limited § 101 issues on appeal, we do not discern there are any concerns about duplication of efforts. Moreover, because of the uncertainty of the timing of any remand from the Federal Circuit to the district court to address any anticipation or obviousness issues, the present circumstances with a pending appeal effectively act as a stay on the assessment of invalidity issues.7” slip op. at 12

    Claim construction§ 102 anticipation§ 103 obviousnessDiscretionary denialcites Graham
    Patents in suitUS 8,400,358
  • PTAB · May 9, 2024 · IPR2024-00084 · APJ Donna M Praiss · IPR · Institution

    The Board instituted IPR on claims 1–3 and all asserted grounds, finding a reasonable likelihood that at least one challenged claim would have been shown obvious.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “To institute inter partes review, we must determine that the information presented in the Petition shows “there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). For the reasons discussed below, after considering the parties’ submissions and the evidence of record, we determine that Petitioner has demonstrated a reasonable likelihood of prevailing with respect to at least one claim of the ’484 patent, and we institute inter partes review of all claims and all grounds asserted in the Petition.1” slip op. at 2

    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “Sotera Wireless, Inc., the PTAB will not discretionarily deny institution in view of parallel district court litigation where a petitioner presents a stipulation not to pursue in a parallel proceeding the same grounds or any grounds that could have reasonably been raised before the PTAB.” Guidance Memo 3 (footnote omitted) (citing Sotera Wireless, Inc. v. Masimo Corp., IPR2020-01019, Paper 12 (PTAB Dec. 1, 2020) (precedential as to § II.A)). The Guidance Memo explains that such a Sotera stipulation “mitigates concerns of potentially conflicting decisions and duplicative efforts between the district court and the PTAB. . . . and allows the PTAB to review grounds that the parallel district court litigation will not resolve.” Id. at 7–8. Here, in an email to Patent Owner, Petitioner “stipulates that if the PTAB institutes IPR, Structural Wrap will not pursue in [the Florida Litigation] the same grounds asserted in the petition, or any grounds that could have reasonably been raised in the petition.” Ex. 1022, 1.” slip op. at 12

    • Adverse judgmentDecided for petitioner

      “Patent Owner’s argument is not persuasive because the cited discussion in the prosecution history does not relate to the challenged claims in this proceeding. Pages 25–26 of Exhibit 2008 correspond to the Declaration of Christopher Mouriz (“Mouriz Declaration”). The Mouriz Declaration relates to claim language that “recites attaching the construction material to a specific component of a roof, namely, the vertical, outward facing [fascias] of the eaves of the roof.” Ex. 2008, 25 ¶ 7. The Mouriz Declaration explains that “the roof component to which a waterproofing membrane is attached is not recognized as a particular parameter that can be experimented with, in order to increase or optimize the waterproofing process in a structural waterproofing system.” Id. at 26 ¶ 8. Thus, the claim language discussed in the Mouriz Declaration relates to attaching construction material specifically to “vertical, outward facing facias of the eaves of the roof.” Id. at 25 ¶ 7. There is no discussion of wrapping battens. Pages 40–41 of Exhibit 2008 correspond to a Response to Office Action wherein the applicant distinguishes the ’554 application claims over prior art references cited by the Examiner, namely, Lennox and Wiki. Ex. 2008, 40–41. The applicant argues that “neither Lennox nor Wiki discloses attaching the construction material that was rolled in the end of the strip to the vertical, outward-facing fascia of the eaves of the roof, as claimed by Applicant.” Ex. 2008, 41 (emphasis original). Again, the claim limitation at issue, which Patent Owner directs us to, relates to the location for attaching construction material, namely, vertical outward-facing fascia. We see no similar limitation in the challenged claims. We also note that Petitioner does not rely on Lennox and Wiki in this proceeding. Accordingly, we are not persuaded that Petitioner should be estopped from arguing that the challenged claims of the ’484 patent are obvious based on arguments presented to the Office concerning claims and references that are not involved in this proceeding.” slip op. at 10

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “We determine we need not explicitly construe any claim term at this stage of the proceeding. See Realtime Data, 912 F.3d at 1375. We encourage the parties to further discuss an express construction for “sheet” during trial if they choose.” slip op. at 7

    Claim construction§ 102 anticipation§ 103 obviousnessDiscretionary denialcites Phillips
    Patents in suitUS 11,168,484
  • PTAB · May 8, 2024 · IPR2024-00168 · APJ Brian D Range · IPR · Institution

    Instituted inter partes review of claims 1–6 and 8 on all petition grounds addressing those claims, based on a reasonable likelihood of prevailing on at least one challenged claim.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “unless the information presented in the petition “shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” The following findings of fact and conclusions of law are not final, but are made for the sole purpose of determining whether Petitioner meets the threshold for initiating review. Any final decision shall be based on the full trial record, including any response timely filed by Patent Owner. Any arguments not raised by Patent Owner in a timely-filed response may be deemed waived. For the reasons stated below, we determine that Petitioner has established a reasonable likelihood that it would prevail with respect to at least one claim. We hereby institute an inter partes review as to claims 1–6 and 8 of the ’245 patent based upon Petitioner’s asserted grounds of unpatentability.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Petitioner contends that a person of ordinary skill in the art “would have had a bachelor’s degree in a field relating to the semiconductor manufacturing process, such as materials science, physics, electrical engineering, and/or other related subjects, and at least two to three years of experience with fabrication of integrated circuits.” Pet. 4 (citing Ex. 1002 ¶ 20). Petitioner also contends “[m]ore education can supplement practical experience and vice versa.” Id. Patent Owner does not dispute the level of ordinary skill in the art. Prelim. Resp. 4–5. For purposes of this Decision, we adopt Petitioner’s proposal as reasonable and consistent with the ’245 patent specification and the prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001) (the prior art may reflect an appropriate level of skill in the art).” slip op. at 9

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)Term construed board ownDecided for patent owner

      “Claim 1 affirmatively recites, for example, “a plurality of layers under the top layer.” Ex. 1001, 4:13. Claim 1 also affirmatively recites that the “plurality of layers compris[es] a bottom routing layer having signal traces thereon.” Id. at 4:14–15. So, claim 1 requires a bottom routing layer having signal traces. Claim 1 then recites “where[] none of the signal traces of the bottom routing layer are located over ball pads of the ball pad layer which are disposed in an area within two ball pad pitches of the corner of the die.” Id. at 4:17–20. This recitation serves to describe the “signal traces of the bottom routing layer.” The recitation does not affirmatively recite a required location of any ball pads. Likewise, the claim as a whole also does not state that the ball pad layer comprises ball pads disposed within two ball pad pitches of the corner of the die. Rather, the claim recites “said ball pad layer having a plurality of ball pads” without affirmatively indicating where those ball pads must be located within the ball pad layer. Thus, on the present record, we interpret claim 1’s recitation of “none of the signal traces . . . within two ball pad pitches of the corner of the die” as requiring that no signal traces of the bottom routing layer be located over ball pads of the ball pad layer disposed within two ball pad pitches of the corner of the die if any such ball pads exist in this location. We do not interpret claim 1 as affirmatively requiring ball pads disposed within two ball pad pitches of the corner of the die. To the extent Patent Owner maintains arguments regarding this recitation in a Patent Owner Response, we invite the parties to further address this claim construction issue at trial to the extent permitted by our rules.” slip op. at 22

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundInstituted

      “We have reviewed Petitioner’s contentions for all of the elements of independent claim 1, as well as the supporting evidence. Pet. 45–55. Based on the record before us, we are persuaded that Petitioner’s discussion of the particular structures and methods in Chung and Celeron establishes a reasonable likelihood of prevailing at trial on the issue of whether the combined teachings of Chung and Celeron teach or suggest all of the limitations of independent claim 1. Id. Also, based on the present record, we are persuaded that Petitioner adequately establishes that a person having ordinary skill in the art would have had reason to combine the teachings of Chung and Celeron.” slip op. at 24

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 7,345,245
  • PTAB · Apr 17, 2024 · IPR2024-00005 · APJ Julia Heaney · IPR · Institution

    The Board instituted IPR on claims 9 and 19 on all asserted grounds, finding a reasonable likelihood that Gowanlock 2 combined with Swivelpole renders at least one challenged claim unpatentable.

    RulingsInstitution decision
    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “District Court proceeding, and restate those positions here. See Pet. 20–21 (citing Ex. 1057, Ex. 1058); Prelim. Resp. 5. Both parties agree, however, that construction of “mounting pole” is not necessary in this proceeding. Pet. 21; Prelim. Resp. 5. Accordingly, we need not construe this term at this stage of the proceeding. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“we need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))).” slip op. at 8

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Petitioner argues a person of ordinary skill in the art at the time of the invention “would have had at least a bachelor’s degree in petroleum engineering, mechanical engineering, civil engineering, construction, architecture, or a similar degree with a year or more experience working on or around rigs, such as a drilling rig, where one or more lighting systems were used to illuminate the wellsite.” Pet. 18 (citing Ex. 1008 ¶¶ 39–40). Petitioner further argues that “[a]dditional practical experience would substitute for lack of a formal degree.” Id. (citing Ex. 1008 ¶ 41). Patent Owner does not dispute the level of ordinary skill in the art. See generally Prelim. Resp. For purposes of this decision, we adopt Petitioner’s definition of the level of ordinary skill in the art because it is consistent with the ’626 patent and the asserted prior art.” slip op. at 9

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundReasonable expectation foundInstituted

      “As to motivation to combine the references, we find that Petitioner sufficiently demonstrates a rational basis for a person of ordinary skill in the art to combine the teachings of Gowanlock 2 and Swivelpole. See Pet. 43– 51; Ex. 1008 ¶¶ 89–96. Patent Owner’s argument that the combination “goes against the fundamental teachings of both references, neither of which disclose a crown deck” (Prelim. Resp. 50) is not persuasive, because as discussed above, Petitioner has sufficiently shown that Gowanlock 2 discloses a crown deck. We do not agree that Swivelpole’s disclosure is limited to a lighting system for illuminating the area immediately beneath the light, and nothing beyond its adjacent walkway. See id. at 50–51. For example, Swivelpole’s description of its S3 system also states it is ideal for lighting roof tops. Ex. 1004, 9. Because Patent Owner’s argument does not reasonably credit the ability of a person of ordinary skill in the art to interpret Swivelpole’s disclosure as a whole, we do not find it persuasive.” slip op. at 23

    • PTAB / AIA Trials › Discretionary denial › §325(d) same art / argumentsInstitution denied 325dDecided for petitioner

      “We find that Petitioner has demonstrated a material error by the Office in failing to consider the teachings of the prior art of record. Under the second prong of Advanced Bionics, we consider “the extent to which the asserted art was evaluated during examination, including whether the prior art was the basis for rejection.” Becton, Dickinson, 17. Here, Petitioner has shown that during prosecution of the ’626 patent, the Examiner immediately allowed claims 21–33 and 35–39 of the application without rejection, in the first office action dated November 25, 2020. Ex. 1002, 34–35. The reasons for allowance set forth in the office action merely recite the limitations of claims 21 and 31, and state “the references of the Prior Art of record fail to teach or suggest the combination of the limitations as set forth in claim [21 and 31].” Id. Upon issuance, claims 21 and 31 became claims 9 and 19 of the ’626 patent, respectively. In view of the Examiner’s statement in the reasons for allowance of claims 9 and 19, we determine the Examiner erred by failing to consider the prior art of record. As discussed above with regard to the patentability challenges to claims 9 and 19 (see Section II.D.4), we find that Petitioner has sufficiently shown a reasonable likelihood that the combination of Gowanlock 2 and Swivelpole discloses the subject matter found allowable by the Examiner. Accordingly, we are persuaded that the Examiner erred in a manner material to patentability by overlooking the teachings of Gowanlock 2 and Swivelpole. Conclusion For the foregoing reasons, we decline to exercise discretion to deny institution under § 325(d). IV.” slip op. at 28

    Claim construction§ 103 obviousnessDiscretionary denialcites KSR · Graham
    Patents in suitUS 10,900,626
  • PTAB · Feb 23, 2024 · IPR2023-01350 · APJ Jon B Tornquist · IPR · Institution

    The Board instituted inter partes review of claims 5–14 on all four asserted obviousness grounds, finding a reasonable likelihood that Apple would prevail on at least one challenged claim.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “An inter partes review may not be instituted “unless . . . the information presented in the petition . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2018). Having considered the arguments and evidence presented by Petitioner and Patent Owner, we determine that the information presented in the Petition demonstrates a reasonable likelihood that Petitioner would prevail on at least one of the challenged claims of the ’641 patent. Accordingly, we institute an inter partes review as to all the challenged claims of the ’641 patent on all the grounds of unpatentability set forth in the Petition.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Petitioner contends a person of ordinary skill in the art, as of the earliest possible priority date for the ’641 patent, “would have held a Bachelor’s degree in chemistry or chemical engineering, with at least 4 years of experience in cell design, electrochemical techniques, and battery materials development.” Pet. 4. Petitioner further contends that a “Master’s Degree can substitute[] for some of the relevant experience,” and “[e]quivalent training with battery specific experience can accommodate other degreed fields.” Id. Patent Owner does not dispute Petitioner’s definition, “except noting that other majors may provide equivalent education and experience designing, testing, and building lithium-ion batteries.” Prelim. Resp. 14. Upon review of the prior art of record and the parties’ arguments, we adopt Petitioner’s unopposed definition of the person of ordinary skill in the art for purposes of this Decision. The parties may further address at trial whether “other majors” should be added to this definition, and whether such a modification would have any impact on the unpatentability analysis in this case.” slip op. at 6

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “Neither party contends any terms of the ’641 patent require express construction. Pet. 4–5; Prelim. Resp. 13–14. And, for purposes of this decision, we agree that no claim terms require express construction. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999) (“[O]nly those terms need be construed that are in controversy, and only to the extent necessary to resolve the controversy.”)).” slip op. at 7

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundInstituted

      “This argument is not persuasive. Contrary to Patent Owner’s arguments, the Federal Circuit has held that “generic” reasons to combine are not inherently suspect, and may reasonably include a desire to make a device “stronger, cheaper, cleaner, faster, lighter, smaller, more durable or more efficient.” See Intel Corp. v. Qualcomm Inc., 21 F.4th 784, 797 (Fed. Cir. 2021) (quoting DyStar Textilfarben GmbH v. C.H. Patrick Co., 464 F.3d 1356, 1368 (Fed. Cir. 2006)). Regardless, Petitioner’s asserted reasons to combine are specific (improved safety and less deterioration after repeated charging and discharging cycles), as is the proposed combination (implementing Sakamoto’s range of ratios for the positive and negative electrode materials in Yamaki’s lithium ion battery). Pet. 9–12. Identification of specific benefits that are tied to specific elements of specific prior art references is sufficient to support an obviousness ground. See Intel, 21 F.4th at 797.” slip op. at 11

    Claim construction§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 7,749,641
  • PTAB · Feb 20, 2024 · IPR2023-01210 · APJ Patrick R Scanlon · IPR · Institution

    The Board instituted IPR on claims 1, 15, 18, 41, and 52 on all asserted grounds, finding a reasonable likelihood of success on at least one challenged claim.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “We have authority to determine whether to institute an inter partes review. See 35 U.S.C. § 314 (2018); 37 C.F.R. § 42.4(a) (2022). To institute an inter partes review, we must determine that the information presented in the Petition shows “a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). For the reasons set forth below, we determine that Petitioner has demonstrated a reasonable likelihood that it would prevail with respect to at least one challenged claim. Accordingly, we institute an inter partes review of the challenged claims on the grounds set forth in the Petition. Our factual findings and conclusions at this stage of the proceeding are based on the evidentiary record developed thus far. This is not a final decision as to patentability of the challenged claims. Any final decision will be based on the full trial record, including any response to the Petition timely filed by Patent Owner.” slip op. at 2

    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Institution denied fintivDenied

      “7. Conclusion We have considered the circumstances and facts before us in view of the Fintiv factors. Because our analysis is fact-driven, no single factor is determinative of whether we exercise our discretion to deny institution under § 314(a). We take “a holistic view of whether efficiency and integrity of the system are best served by denying or instituting review” when evaluating these factors. Fintiv, Paper 11, 6. Evaluating all of the factors on this record, we determine that weight of factors 1, 2, and 4 outweigh the remaining factors. Thus, based on our assessment of the Fintiv factors, we decline to exercise our discretion under 35 U.S.C. § 314(a) to deny inter partes review.” slip op. at 21

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Petitioner contends that a person having ordinary skill in the art would have been someone knowledgeable in wireless networks, cellular radio systems, mobile communication devices and radio navigation systems, having at least a bachelor’s degree in electrical engineering, with a background in radio frequency communications and/or navigation system technology as well as approximately two years of industry experience working on radio communication and/or navigation systems. Pet. 13 (citing Ex. 1012 ¶ 30). Patent Owner does not dispute Petitioner’s definition for the level of ordinary skill in the art. Prelim. Resp. 30. For purposes of this Decision, we adopt Petitioner’s proposal as reasonable and consistent with the prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001) (the prior art may reflect an appropriate level of skill in the art).” slip op. at 8

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)Term construed petitioner constructionDecided for petitioner

      “The first four of Petitioner’s proposed constructions are consistent with the clam constructions issued by the district court in the Google Action—the only difference being that although the district court found the corresponding structure for “positioning determining equipment” indefinite, Petitioner applies the corresponding structure proposed by Patent Owner in the Google Action. Ex. 1028, 8, 10–16, 20; Pet. 16. Petitioner cites Exhibit 1024 as supporting its contention that the parties have stipulated as to the order of the “collecting,” “modifying,” and “comparing” steps in claim 1, but this Exhibit does not appear to support the stipulation. See Ex. 1024. Patent Owner “does not dispute Petitioner’s statement on claim construction for the purposes of [the] Preliminary Response” and “reserves the right to present arguments on the constructions should the Petition be instituted.”7 Prelim. Resp. 31. For purposes of this Decision, we adopt the undisputed claim constructions that Petitioner proposes. These constructions are consistent 7 In other sections of the Preliminary Response, Patent Owner appears to argue in favor of a modified construction of “grid point.” Prelim. Resp. 18– 25; see also id. at 32 (“As further explained above in Section III, the district court concluded that ‘grid point,’ as used in the ’358 Patent, specifically refers to ‘a point associated with representative calibration data for an area’ that is generated based on analysis of calibration data.”). We disagree with these arguments for the reasons discussed below. with the claim language and the specification of the ’358 patent and are further supported by the reasoning provided by the district court’s claim construction order. See Ex. 1028. We do not discern a need to construe explicitly any other claim language at this juncture because doing so would have no effect on our analyses below of Petitioner’s asserted grounds and will not assist in resolving the present controversy between the parties. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’”) (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)).” slip op. at 10

    Claim construction§ 102 anticipation§ 103 obviousnessDiscretionary denialcites Graham
    Patents in suitUS 8,400,358
  • PTAB · Feb 20, 2024 · IPR2023-01209 · APJ Patrick R Scanlon · IPR · Institution

    The Board instituted IPR of claims 1–3 and 11 on all asserted grounds, finding a reasonable likelihood that Google would prevail on at least one challenged claim.

    RulingsInstitution decision
    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “is finality as that relates to Fintiv issues. In a similar instance in Volvo, where a district court’s § 101 determination was appealed to the Federal Circuit, the Director determined that the Board had the authority to institute an inter partes review and a Fintiv analysis should be performed. See Volvo, Paper 15 at 1–8. The Director has additionally distinguished a Fintiv analysis under similar circumstances to those here, where “the district court’s judgment of invalidity under 35 U.S.C. § 101, i.e., a statutory ground that could not have been raised before the Board, does not raise concerns of inefficient duplication of efforts or potentially inconsistent results between the Board and the district court.” AviaGames, Inc., Paper 14 at 3. Further, the Director determined that, “the challenged claims have not yet been cancelled and remain in force until the opportunity to appeal has been exhausted,” noting that “[b]y the time an appeal will have concluded, Petitioner will be barred under 35 U.S.C. § 315(b) from bringing a new challenge in an IPR petition.” Id. at 3–4. Fintiv states that “a district court stay of the litigation pending resolution of the PTAB trial allays concerns about inefficiency and duplication of efforts.” Fintiv at 6. In view of the circumstances, we do not discern that the § 101 issues addressed in the Federal Circuit appeal would duplicate the anticipation and obviousness issues addressed here. We also agree with Petitioner that the timing of the progress of the appeal and any potential remand to the district court is uncertain. Accordingly, given the limited § 101 issues on appeal, we do not discern there are any concerns about duplication of efforts. Moreover, because of the uncertainty of the timing of any remand from the Federal Circuit to the district court to address any anticipation or obviousness issues, the present circumstances with a” slip op. at 14

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “review. See 35 U.S.C. § 314 (2018); 37 C.F.R. § 42.4(a) (2022). To institute an inter partes review, we must determine that the information presented in the Petition shows “a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). For the reasons set forth below, we determine that Petitioner has demonstrated a reasonable likelihood that it would prevail with respect to at least one challenged claim. Accordingly, we institute an inter partes review of the challenged claims on the grounds set forth in the Petition.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Petitioner contends that a person having ordinary skill in the art would have been someone knowledgeable in wireless networks, cellular radio systems, mobile communication devices and radio navigation systems, having at least a bachelor’s degree in electrical engineering, with a background in radio frequency communications and/or navigation system technology as well as approximately two years of industry experience working on radio communication and/or navigation systems. Pet. 13–14 (citing Ex. 1012 ¶ 31). Patent Owner does not dispute Petitioner’s definition for the level of ordinary skill in the art. Prelim. Resp. 31. For purposes of this Decision, we adopt Petitioner’s proposal as reasonable and consistent with the prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001) (the prior art may reflect an appropriate level of skill in the art).” slip op. at 8

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)Term construed petitioner constructionNo construction neededOther

      “The first four of Petitioner’s proposed constructions are consistent with the clam constructions issued by the district court in the Google Action (see Ex. 1028, 8, 10, 20) or a position taken by Patent Owner in the Google Action (see Ex. 1016 ¶¶ 108–109). Petitioner cites Exhibit 1024 as supporting its contention that the parties have stipulated as to the order of the “collecting,” “modifying,” and “comparing” steps in claim 1, but this Exhibit does not appear to support the stipulation. See Ex. 1024. Patent Owner “does not dispute Petitioner’s statement on claim construction for the purposes of [the] Preliminary Response” and “reserves the right to present arguments on the constructions should the Petition be instituted.”8 Prelim. Resp. 31. For purposes of this Decision, we adopt the undisputed claim constructions that Petitioner proposes. These constructions are consistent with the claim language and the specification of the ’104 patent and are further supported by the reasoning provided by the district court’s claim construction order. See Ex. 1028. We do not discern a need to construe explicitly any other claim language at this juncture because doing so would have no effect on our analyses below of Petitioner’s asserted grounds and will not assist in resolving the present controversy between the parties. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’”) (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)).” slip op. at 9

    Claim construction§ 102 anticipation§ 103 obviousnessDiscretionary denialcites Graham
    Patents in suitUS 7,561,104

Holdings, summaries, rulings, issues, outcomes, winners and claim constructions shown for a decision were generated by a large language model reading the opinion. They are a guide to the decision, not the decision. Confirm every one against the court's own text before relying on it. Outcomes read from the patent owner’s side. Party names are extracted from the decision and are missing on about 900 short Director denials and scans, which carry the trial number instead.