  • PTAB · Jun 9, 2026 · IPR2025-00321 · APJ Christopher M Kaiser · IPR · Final written decision

    The Board held claims 1, 2, 5–7, 9, 16, and 17 not unpatentable because the asserted combinations did not establish the required purge-tower teachings or prior-art status.

    RulingsFinal written decision
    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Petitioner contends that one of ordinary skill in the art “would have had (1) at least a bachelor’s degree in Mechanical Engineering, Computer Engineering, Chemical Engineering, Materials Science, or a related field, and (2) at least two years of research or industry experience in 3D printing or materials used for 3D printing.” Pet. 5 (citing Ex. 1003 ¶¶ 14–16). Petitioner also argues that “[a]dditional experience could substitute for a formal degree or formal training (and vice versa).” Id. Patent Owner proposes a slightly different level of skill, arguing that a person of ordinary skill in the art “would have had a bachelor’s degree in Mechanical Engineering, Computer Engineering, Chemical Engineering, Materials Science, or a comparable field and at least two years of experience related to 3D printing, with additional experience potentially being a substitute for a formal degree or training (and vice versa).” Prelim. Resp. 24. Neither party explains why the outcome of this case would be affected by the adoption of any of the proffered definitions of a person of ordinary skill in the art. We adopt Petitioner’s assessment of the level of ordinary skill in the art, as it appears consistent with the ’324 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001).” slip op. at 8

    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed board ownOther

      “According to the ’713 patent, “[p]urge tower 24 itself may be . . . recycled or otherwise discarded as desired.” Ex. 1001, 8:27–28. This description provides some support for Patent Owner’s view, because a purge tower too intimately integrated with the part would be difficult or impossible to recycle or discard. This is further supported by the ’713 patent’s statement that “purge tower 24 may be printed at any suitable location on build substrate 44 (i.e., at any location in the x-y build plane not occupied by 3D part 20 or support structure 22).” Id. at 8:30–34. It also is supported by Dr. Hickner’s testimony that the ’713 patent “clearly shows . . . the 24 purge tower separated from the part” and that “the purge tower is a separate physical object.” Ex. 2016, 28:8–10, 64:1–9. On the other hand, there is evidence supporting Petitioner’s view that, as long as the purge tower is generally separate from the part and the support structure, it may still make contact with those portions of the print. As noted above, “purge tower 24 may be printed at any suitable location on build substrate 44 (i.e., at any location in the x-y build plane not occupied by 3D part 20 or support structure 22).” Ex. 1001, 8:30–34. This language does not exclude locations adjacent to or in contact with the part or the support structure. Thus, determine that a “purge tower,” as that term is used in the context of the ’713 patent, may not be an integrated portion of a printed part or support structure but need not be free of all contact with the printed part or support structure.” slip op. at 9

    • BurdenNot shown unpatentable

      “There is evidence of record to support both Petitioner’s view and Patent Owner’s view. On the record developed at trial, however, we cannot say that the preponderance of the evidence favors Petitioner, who bears the burden of proof. See 35 U.S.C. § 316(e). Accordingly, Petitioner has not shown by a preponderance of the evidence that KISSlicer teaches printing a layer of a purge tower each time the printer switches one extruder to the operating mode. Because proving the obviousness of claims 1 and 16 requires such a showing, Petitioner has not shown by a preponderance of the evidence that claims 1 and 16 would have been obvious over the combination of Priedeman and KISSlicer. 5. Analysis of Remaining Claims Claims 2, 6, 7, 9, and 17 all depend, directly or indirectly, from claim 1 or claim 16. Accordingly, they all include the limitations of either claim 1 or claim 16. Because, as discussed above, Petitioner has not shown that the combination of Priedeman and KISSlicer teaches or suggests all the limitations of claims 1 and 16, Petitioner also has not proven by a preponderance of the evidence that claims 2, 6, 7, 9, and 17 would have been obvious over that combination of references.” slip op. at 21

    • Obviousness (§103) › Analogous artAnalogous artOther

      “On the record developed at trial, we agree with Petitioner. According to several industry forum posts, people interested in three-dimensional printing located the website where KISSlicer was posted between February 2012 and April 2012. Ex. 1028, 1 (post discussing and directing others to KISSlicer on April 11, 2012); Ex. 1031, 1 (two posts discussing KISSlicer on March 16, 2012, and March 21, 2012); Ex. 1032, 1 (two posts discussing KISSlicer on February 11, 2012, and February 14, 2012). Thus, not only was it possible for people of ordinary skill in the art to locate KISSlicer; people of ordinary skill in the art actually did locate it. Accordingly, Petitioner has shown by a preponderance of the evidence that KISSlicer was publicly accessible.” slip op. at 19

    Patent outcomesUS 9,421,713 not shown unpatentable
    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 9,421,713
  • PTAB · Dec 19, 2025 · IPR2025-00434 · APJ Mitchell G Weatherly · IPR · Rehearing

    The Board denied Petitioner’s rehearing request, leaving institution denied because Shen and Soldano did not establish a reasonable likelihood of anticipating claims 1–7.

    RulingsRehearing decision
    • RehearingRehearing, deniedDenied

      “When rehearing a decision on petition, the Board will review the decision for an abuse of discretion. See 37 C.F.R. § 42.71(c). An abuse of discretion may be determined if a decision is based on an erroneous interpretation of law, if a factual finding is not supported by substantial evidence, or if the decision represents an unreasonable judgment in weighing relevant factors. See Arnold P’ship v. Dudas, 362 F.3d 1338, 1340 (Fed. Cir. 2004). The party challenging the decision has the burden of showing the decision should be modified, and the request for rehearing “must specifically identify all matters the party believes the Board misapprehended or overlooked, and the place where each matter was previously addressed” in its papers. 37 C.F.R. § 42.71(d).” slip op. at 2

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “II. ANALYSIS In our Decision, we concluded that Petitioner had failed to carry its burden of demonstrating a reasonable likelihood of prevailing that either Shen or Soldano anticipated claims 1–7. Dec. 18, 26. Petitioner argues that we should institute review for three reasons. First, Petitioner argues that we abused our discretion by (a) “refusing” to interpret the scope of the claimed” slip op. at 2

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededNot reached

      “Owner’s interpretation of “carrier” as meaning “one or more components for supporting ROSA components such as an AWG.” Dec. 9 (quoting Pet. 11). For our analysis of Petitioner’s challenges, we referred to this interpretation of “carrier” as Petitioner’s second alternative construction. Id. We also noted that Petitioner appeared to dispute Patent Owner’s interpretation when it argued that “carrier” should mean “a ceramic or silicon substrate.” Id. (quoting Pet. 10). We referred to this interpretation of “carrier” as the first alternative construction. Id. Rather than resolve this apparent dispute about the meaning of “carrier,” we found that both of Petitioner’s anticipation challenges failed under both interpretations of “carrier.” Id. at 10–26. Because we found that Petitioner had failed to carry its burden regardless of which interpretation of “carrier” applied, we found it unnecessary to resolve the dispute over that interpretation. Id. at 9–10. For the reasons expressed in Parts II.B–C below, we maintain our conclusion that Petitioner has failed to demonstrate a reasonable likelihood of proving that either Shen or Soldano anticipates any claim under either interpretation of “carrier.” Accordingly, Petitioner fails to demonstrate an abuse of discretion in our alleged “refusal” to interpret “carrier.”” slip op. at 3

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “Reh’g Req. 14. We cannot weigh Petitioner’s arguments based on its assertions about “caselaw” because Petitioner cited no cases to support its arguments. See id. Nevertheless, we infer that Petitioner intends its statements of “caselaw” to refer to the requirements to make out a case for anticipation. If so, Petitioner demonstrably miscasts what appear to be the legal principles for proving anticipation. As stated in our Decision: “A claim is anticipated only if each and every element as set forth in the claim is found, either expressly or inherently described, in a single prior art reference.” Verdegaal Bros., Inc. v. Union Oil Co. of California, 814 F.2d 628, 631 (Fed. Cir. 1987).” Dec. 7. Making a showing that a prior art reference anticipates a patent claim thus necessarily requires proof that a single reference “expressly or inherently” describes every element of that claim and with all elements being arranged in the reference as they are in the” slip op. at 7

    Claim construction§ 102 anticipation
    Patents in suitUS 10,379,301
  • PTAB · Dec 1, 2025 · IPR2025-01010 · APJ Michael T Cygan · IPR · Institution

    The Board instituted IPR on claims 1–15 and all asserted grounds, finding a reasonable likelihood that Petitioner would prevail on at least one challenged claim.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “review. See 35 U.S.C. § 314 (2018); 37 C.F.R. § 42.4(a) (2023). The standard for instituting an inter partes review is set forth in 35 U.S.C. § 314(a), which provides that an inter partes review may not be instituted “unless . . . there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” For the reasons given below, on this record, Petitioner has established a reasonable likelihood that it would prevail in showing the unpatentability of at least one of challenged claims 1–15 of the ’322 patent. Accordingly, we institute an inter partes review of the ’322 patent.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “B. Level of Ordinary Skill in the Art Petitioner asserts that a person of ordinary skill in the art (“POSITA”) at the critical time “would have had at least a bachelor’s degree in computer 3 Neither party presents evidence or arguments regarding objective evidence of non-obviousness. work or research experience in the field of content delivery management or networks,” and that “[w]ork experience can substitute for formal education and additional formal education can substitute for work experience.” Pet. 10 (citing Ex. 1003 ¶¶ 61–63). Patent Owner does not provide any such assessment in its Preliminary Response. Prelim. Resp. 11. For purposes of this Decision, we adopt Petitioner’s proposed level of ordinary skill, as it appears to be consistent with the specification of the ’322 patent and the prior art of record.” slip op. at 6

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)Term construed board ownDecided for petitioner

      “On the current record, we determine that the “modified embedded resource” may be a “link.” Both Petitioner and Patent Owner point to claim 13, which explicitly states that a modified embedded resource is a link. Because claim 13 depends from claim 1, claim 1 must be broad enough to encompass a modified embedded resource that is a link. Patent Owner also points to a statement in the ’322 patent that “[t]he embedded resource is a link.” Prelim. Resp. 18 (citing Ex. 1001, 4:26–31). Patent Owner argues that every embodiment of the ’322 patent “involves embedding the ‘modified embedded resource’ in another resource when it is returned to the client.” Paper 16, 2–3. Patent Owner cites to description in the ’322 patent of a “document” or a “page” returned to the requesting client. Id. (citing Ex. 1001, 4:42–48, 7:48–55). However, claim 15 does not return the modified embedded resource to the client, only the origin system. Claim 1 recites only that the “modified embedded resource” is returned to the client device with the content resource. Neither claim 1 nor claim 15 recite returning a document or a page containing the modified embedded resource, only the modified embedded resource itself. We acknowledge some tension with the adjective “embedded,” which Patent Owner argues requires that the embedded resource be embedded in something. Paper 16, 1–3. However, the clear description of an embedded patent, more strongly guides our preliminary construction.” slip op. at 9

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Instituted

      “We are persuaded by Petitioner’s assertions for limitations [15pre]– [15a]. Dr. Mowry attests that Verna’s client browser sends a URL 28 to a content provider 22, which is then forwarded to broker 25, which selects the appropriate cache server to serve the content and returns a re-written URL to the content server that received the client request. Ex. 1003 ¶ 67 (citing Ex. 1005 ¶¶ 12, 26, 27, 37). On the current record, this function of Verna’s broker fulfills Dr. Russ’s characterization of an API as acting as bridge establishing a connection between client and server. Ex. 2010 ¶ 50. Verma also meets Dr. Russ’s characterization of an API as “an interface that allows the client to communicate with an application executing on the server.” Ex. 2010 ¶ 50. Dr. Russ describers Verma’s broker as sending availability inquiries from the content provider (client) to servers 23 and 24 to “find out whether they currently store the requested movie file,” and provide that information back to the content provider (client). Id. ¶ 53. On the current record, this function of Verna’s broker fulfills Dr. Russ’s characterization of an API acting as an interface that allows the client to provides availability information to the broker). Consequently, we determine that Petitioner has shown Verma to disclose limitation [15a] for purposes of institution on the current record.” slip op. at 13

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 10,057,322
  • PTAB · Nov 25, 2025 · IPR2025-00860 · APJ Sheila F Mcshane · IPR · Institution

    The Board instituted review of claims 1–20 on all asserted grounds, finding a reasonable likelihood that the Dilley, Pai, and Wang combination renders the claims obvious.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “partes review. See 35 U.S.C. § 314; 37 C.F.R. § 42.4(a). Under 35 U.S.C. § 314(a), we may not authorize an inter partes review unless the information in the petition and the preliminary response “shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” For the reasons stated below, we determine that Petitioner has established a reasonable likelihood that it would prevail with respect to at least one claim. We therefore institute inter partes review as to all of the challenged claims of the ’573 patent and all of the asserted grounds of unpatentability in the Petition.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “III. ANALYSIS A. Level of Ordinary Skill in the Art Petitioner asserts that a person of ordinary skill in the art: would have had at least a bachelor’s degree in computer science, electrical engineering, or a related field, and at least two years of work or research experience in the field of content delivery management or networks. Work experience can substitute for formal education and additional formal education can substitute for work experience. Pet. 12 (citing Ex. 1006 ¶ 70). Patent Owner asserts that “the Board does not need to resolve the appropriate level of skill for a POSA [person of ordinary skill in the art] for purposes of deciding institution because the Petition fails under any articulation of a POSA.” Prelim Resp. 10. For the purposes of this Decision, we adopt the assessment offered by Petitioner as it is consistent with the ’573 patent and the prior art before us. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001).” slip op. at 8

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “Petitioner asserts that no claim terms need to be expressly construed by the Board and all terms should be given their ordinary meaning. Pet. 12. Patent Owner agrees that the Phillips standard applies. Prelim. Resp. 10. We determine that we need not expressly construe any claim terms at this juncture. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))).” slip op. at 9

    • Disclosure Requirements (§112) › Written description (Ariad)Written description adequateEntitled to earlier dateDecided for patent owner

      “We consider the disclosures of the Provisional Application, which refer to cases 1 and 2, in which requests are redirected to an origin server for lower popularity content and to a parent server for medium popularity content at steps 522 and 524 as shown in Figure 5, respectively, wherein the edge server receives a redirect from the popularity service without a “followme” flag. See Ex. 1011 ¶¶ 43, 44. The Provisional Application also discloses that, by comparison, if there is a “follow-me” redirect sent to the edge server, it obtains and caches a resource as shown at step 528 for higher popularity content. Id. ¶ 44. On this record, as Patent Owner asserts, these disclosures are consistent with technical reasons provided in the Provisional Application for instructing the edge server not to cache unpopular resources. See Ex. 1011 ¶¶ 68–69. In light of these disclosures, we preliminarily find support for Dr. Shenoy’s testimony that, even with the words “instruction to not cache” are not literally recited in the Provisional Application, caching and not caching are alternative options that indicate the instruction to the edge server that will be implemented for each option. See Ex. 2014 ¶ 56. Further, these disclosures provide support for Dr. Shenoy’s testimony that the disclosures “reasonably convey to those skilled in the art that Patent Owner had possession of the edge server receiving an instruction to not cache the resource (and instead simply forward the redirect).” Id. In re Johnson states that “it is not true that the factual context out of which the question under § 112 arises is immaterial. Quite the contrary. Here, . . . the ‘written description’ in the [] specification supported the claims in the absence of the limitation, and that specification, having described the whole, necessarily described the part remaining.” See Johnson, 558 F.2d at 1019. This is consistent with M.P.E.P. § 2173.05(i) which states, “[i]f alternative elements are positively recited in the specification, they may be explicitly excluded in the claims.” M.P.E.P. § 2173.05(i). Further, “the failure of the specification to specifically mention a limitation that later appears in the claims is not a fatal one when one skilled in the art would recognize upon reading the specification that the new language reflects what the specification shows has been invented.” All Dental Prodx, LLC v. Advantage Dental Prod., Inc., 309 F.3d 774, 779 (Fed. Cir. 2002). Even though we do not discern that the Provisional Application explicitly discloses an “instruction to not cache,” at least on this preliminary record, and for the purposes of this Decision, there is positive recital of instructions to cache in the Provisional Application and Petitioner has provided sufficient supporting evidence that caching and not caching are alternative options. Further, there is sufficient evidence, in the context of the disclosures of written description support in the Provisional Application, providing support for Dr. Shenoy’s testimony that Patent Owner had possession of an edge server receiving an instruction to not cache the resource. Nonetheless, we invite additional briefing on these issues, including issues relating to alternative options of caching and not caching. On this preliminary record, we find that the ’573 patent has a priority date of April 2, 2008, which predates the earliest possible date on which Newton-471 could be effective as prior art, September 30, 2014 (the date on which the earliest application in the priority chain of Newton-471 was filed). Accordingly, we preliminarily find that Newton-471 is not prior art to the challenged claims. Thus, on the present record, Petitioner has not demonstrated a reasonable likelihood that it would prevail in showing that claims 1–20 are anticipated by Newton-471.” slip op. at 13

    Claim construction§ 102 anticipation§ 103 obviousness§ 112 disclosurecites Phillips · KSR · Graham
    Patents in suitUS 10,924,573
  • PTAB · Nov 21, 2025 · IPR2025-00930 · APJ Mitchell G Weatherly · IPR · Institution

    The Board instituted IPR of claims 1–20 on all asserted grounds, finding a reasonable likelihood that Murphy renders claim 1 obvious.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “Preliminary Response. Therefore, Petitioner’s arguments for unpatentability are currently unopposed. Institution of an inter partes review is authorized by statute when “the information presented in the petition filed under section 311 and any response filed under section 313 shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). Based on our review of the record, we conclude that Petitioner is reasonably likely to prevail with respect to at least one challenged claim.” slip op. at 2

    • Obviousness (§103) › Graham factors (scope of art, differences, level of skill)Instituted

      “Teleflex Inc., 550 U.S. 398 (2007), reaffirmed the framework for determining obviousness as set forth in Graham v. John Deere Co., 383 U.S. 1 (1966). The KSR Court summarized the four factual inquiries set forth in Graham that we apply in determining whether a claim is reasonably likely to be unpatentable as obvious under 35 U.S.C. § 103(a) as follows: (1) determining the scope and content of the prior art, (2) ascertaining the differences between the prior art and the claims at issue, (3) resolving the level of ordinary skill in the pertinent art, and (4) considering objective evidence indicating obviousness or nonobviousness. KSR, 550 U.S. at 406. With these standards in mind, we address each challenge below. C. Claims 1–6, 8–11, and 13–20: Obviousness in View of Murphy” slip op. at 6

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Instituted

      “A claim is anticipated only if each and every element as set forth in the claim is found, either expressly or inherently described, in a single prior art reference.” Verdegaal Bros., Inc. v. Union Oil Co. of Cal., 814 F.2d 628, 631 (Fed. Cir. 1987). The Supreme Court in KSR International Co. v. slip op. at 5

    § 102 anticipation§ 103 obviousnesscites Phillips · KSR
    Patents in suitUS 11,472,427
  • PTAB · Oct 10, 2025 · IPR2025-00653 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution on all claims because the Petition did not show a reasonable likelihood that any challenged claim was unpatentable over the asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “An inter partes review may be instituted only if “the information presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’504 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 12

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “Additionally, only terms that are in controversy need to be construed, and these need be construed only to the extent necessary to resolve the controversy. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’”) (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)). The parties assert that each claim term should be construed in accordance with its plain and ordinary meaning. Pet. 9; Prelim. Resp. 4 (citing Ex. 2009 ¶ 72); see Ex. 1002 ¶ 22 (opining the same). And, in the respective claim construction sections of their briefs, the parties do not propose any claim terms for express construction. We agree with the parties that no claim terms require express construction to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 13

    • Expert testimonyPetitioner expert discountedDecided for patent owner

      “Ex. 1002 ¶ 47. As reflected above, Dr. Wooley’s testimony as to element [1.2] does not even assert that Cardamone discloses a tank, let alone one or more sensors disposed at a tank as recited in element [1.2]. Thus, Dr. Wooley’s testimony does not support Petitioner’s argument on this issue.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,726,504
  • PTAB · Oct 10, 2025 · IPR2025-00652 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–23 and 25–30 were unpatentable over the asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’403 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 12

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “The parties assert that each claim term should be construed in accordance with its plain and ordinary meaning. Pet. 10; Prelim. Resp. 4 (citing Ex. 2009 ¶ 73); see Ex. 1002 ¶ 22 (opining the same). And, in the respective claim construction sections of their briefs, the parties do not propose any claim terms for express construction. We agree with the parties that no claim terms require express construction to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 13

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “We agree with Patent Owner that the Petition fails to demonstrate that Kahn discloses element [1.2] because the evidence cited does not disclose a “first computer system being configured to provide remote control of the first pump or first valve” (i.e., a fluid-handling device). Kahn is directed to providing access to fluid sensing data and analyzing and providing visual information on that data, but Petitioner has not identified any disclosure of the capability to remotely control fluid-handling devices. See, e.g., Ex. 1005, code (54), 1:27–36, 2:50–3:2. More specifically, Kahn’s disclosures that Petitioner relies on for allegedly teaching remote control are deficient. We discuss each. First, Petitioner points to the following, “[f]or instance, as illustrated in FIG. 1C, a fluid control device such as a valve 15A is located on the input side of a sen[s]or unit 110.” Ex. 1005, 8:19–21, cited in Pet. 13. This portion of Kahn, however, does not disclose remote control. Second, Petitioner cites to the following: Finally, or in addition to, the communication unit 112B can include on-site alerts such as optical (indicator lights), audible alerts (e.g., alarm sounds), tactile (e.g., vibration of the unit) or can be interfaced to an appropriate control valve for simply shutting off the supply of fluid upon the detection of emergency events, for instance. Pet. 13 (citing Ex. 1005, 10:62–67). We agree with Patent Owner that this portion of Kahn teaches on-site alerts and local control of the fluid-handling device. See Prelim. Resp. 7. This portion of Kahn does not disclose remote control.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,294,403
  • PTAB · Oct 10, 2025 · IPR2025-00651 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–3, 6, 7, and 9–20 were unpatentable over any asserted ground.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’680 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 11

    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed patent owner constructionDecided for patent owner

      “target value” is part of a command that is sent from a computing device to a server and then to a controller. The controller then receives a measurement of the fluid by a sensor and determines whether the measurement satisfies the “target value.” If the measurement does not satisfy the “target value,” further operations are undertaken. The recited operation sequence makes clear that the plain and ordinary meaning of “target value” is not as Dr. Wooley opines because the particular operating condition that a device is in at a particular time is represented by the measurement taken by the sensor, 11 Some claim language less relevant to construing “target value” was omitted for ease of reference. which the controller then uses to determine whether the measurement satisfies the “target value.” Additionally, claim 1 recites that the “target value” is sent as part of a command to the controller. The “target value” is not sent to the controller from the sensor, as might be expected if the plain and ordinary meaning of “target value” were as Dr. Wooley opines. Petitioner and Dr. Wooley’s construction would also result in “target value” meaning effectively the same thing as the measurement of the fluid by the sensor, a concept that is separately recited in claim 1 and to which the “target value” is compared. The Specification of the ’680 patent does not support Petitioner’s understanding of the plain and ordinary meaning of “target value.” Although the Specification does not recite “target value,” it recites “target state,” and describes “target state” sufficiently to understand the plain and ordinary meaning of “target” as used in “target value” and “target state.” In particular, the ’680 patent explains that “[i]n some embodiments, the process 104 includes receiving, via a network interface, from a remote user device, (e.g., via a command-center server) a command to change a state of a fluid-handling device to a target state.” Ex. 1001, 11:48–51. This portion reflects that the command is seeking to change a state of a fluid-handling device to a target state. In other words, the “target value” or “target state” is not generally “the particular operating condition that a device is in at a particular time”; rather, it is a value or state that the fluid-handling device is desired to be in, as Patent Owner and Dr. Durham explain. Additionally, just as claim 1 recites a directional component for the “target value” to be sent to the controller in a command, so too does the Specification describe a “target state” as being sent in a command from a remote user device. Thus, the Specification clearly supports the plain and ordinary meaning proposed by Patent Owner and Dr. Durham and not the plain and ordinary meaning proposed by Petitioner and Dr. Wooley. slip op. at 14

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “time-stamped process data, report exception therein to the remote host, and extract and transmit time-stamped process data to the remote host.” Ex. 1005, Abst. (emphases added). Almadi explains that its remote field systems must include a plurality of controller units “to issue commands to, and gather and process data from a plurality of field devices, including remote systems and instruments, . . . [and] a database server for the storage of process data retrieved from the remote subsystems and instruments.” Id. at 2:22–30 (emphases added). Based on these disclosures, we agree with Patent Owner that Petitioner has not established that Almadi discloses element [1.4]. Specifically, the teachings from Almadi identified by Petitioner refer to process data, which is data retrieved from the remote subsystems/field devices. Thus, we understand that Almadi’s teaching—of using an Ethernet switch to transmit “process data”—describes transmitting data from the remote subsystems/field devices. See Ex. 1005, 3:13–17, cited in Pet. 15. But claim 1 and particularly element [1.4], recites “sending, with the server, the target value to the network address [which identifies a controller of the fluid-handling device13] via the network,” which is different than sending process data from the field devices to the remote host or database server for storage.” slip op. at 19

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,175,680
  • Tanklogix, LLC v. SiteproInstitution denied
    PTAB · Oct 10, 2025 · IPR2025-00650 · APJ Sheila F Mcshane · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 18–32 and 34 were unpatentable over Kahn or Kahn and Gutierrez.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “information presented in the petition . . . and any response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). Upon consideration of the Petition, the Preliminary Response, and the evidence of record, we determine that Petitioner has not established a reasonable likelihood of prevailing with respect to the unpatentability of at least one claim of the ’871 patent. Accordingly, for the reasons that follow, we decline to institute an inter partes review of claims 18–32 and 34 of the ’871 patent.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The respective proposed levels of qualifications for a person of ordinary skill in the art are similar, with Patent Owner proposing two years of experience compared to Petitioner proposing significant experience with remotely controlling fluid-handling devices, like SCADA systems. Patent Owner also proposes more extensive experience in lieu of educational experience. While we find Petitioner’s proposed qualifications to be acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of skill necessary to understand and implement the teachings of the ’871 patent and the asserted prior art. Our analysis and findings herein, however, do not turn on any differences in the qualifications adopted.” slip op. at 8

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “We determine that we need not expressly construe any claim terms to resolve the parties’ disputes on the current record. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“[W]e need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))).” slip op. at 10

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “actuators and the remote control of fluid handling devices, including the receipt with the user-interface module of “a user command to actuate an actuator via a presented control interface” (limitation [18.7]) and “account authorized to send commands to remotely control fluid handling devices” (limitation [18.11]). We agree with Patent Owner that the Petition fails to demonstrate that Kahn discloses or teaches these limitations because the evidence does not provide support that there is remote control of fluid handling devices or the use of a user command on a control interface to send a command to a fluid handling device, for instance. Kahn is directed to providing access to fluid sensing data and analyzing and providing visual information on that data, but we do not discern that it teaches or discloses the capability to remotely control fluid handling devices. See, e.g., Ex. 1005, code (54), 1:27–36, 2:50–3:2. More specifically, the Kahn disclosures that Petitioner repeatedly relies upon for allegedly teaching this control are deficient. See Ex. 1005, 10:62–67, 14:35– 15:2, 15:62–16:32; see also Pet. 12–14, 16–18. Kahn discloses that “the communication unit 112B can include on-site alerts such as optical (indicator lights), audible alerts (e.g., alarm sounds), tactile (e.g., vibration of the unit) or can be interfaced to an appropriate control valve for simply shutting off the supply of fluid upon the detection of emergency events, for instance.” Ex. 1005, 10:62–67. Communication unit 112B is part of the local “sensor unit,” wherein the detection conditions determined by the sensor are communicated to remote devices by communication unit 112B. See id. at 3:31–33, 5:62–6:2, 6:27–35, 7:33–37, 13:7–12, Figs. 1A–1C. Kahn discloses that the sensor units, which include communication units 112B, can be located near shut-off valves and can communicate with distant locations. See id. at 11:1–13. There are no disclosures, however, in the above passages that there is remote control of fluid handling devices, that there is a user command on a control interface that actuates an actuator, or that there is a command sent to the facility actuators via a network connection, as required in limitations [18.5]–[18.7] and [18.9]–[18.12], respectively. Rather, the disclosure indicates that the communication unit 112B includes on-site alerts and that the local (non-remote) communication unit 112B can be interfaced with the control valve.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 10,488,871
  • PTAB · Oct 8, 2025 · IPR2025-00706 · APJ Eric C Jeschke · IPR · Institution

    The Board instituted inter partes review of claims 1, 4, and 7–10 on all asserted grounds, finding a reasonable likelihood of prevailing on at least one challenged claim.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “review. See 35 U.S.C. § 314; 37 C.F.R. § 42.4(a) (2024) (“The Board institutes the trial on behalf of the Director.”). Inter partes review may not be instituted “unless . . . the information presented in the petition . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314. Upon consideration of the evidence and arguments in the record, for the reasons below, we determine that the information presented shows a reasonable likelihood that Petitioner would prevail with respect to at least one of the challenged claims. We thus institute inter partes review on all challenged claims on all asserted grounds. See SAS Inst. Inc. v. Iancu, 584 U.S. 357, 362–63, 369–70 (2018); 37 C.F.R. § 42.108(a) (“When instituting inter partes review, the Board will authorize the review to proceed on all of the challenged claims and on all grounds of unpatentability asserted for each claim.”).” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “we view the prior art and the claimed invention. Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001). The person of ordinary skill in the art is a hypothetical person presumed to have known the relevant prior art. In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995). In determining the level of ordinary skill in the art, we may consider certain factors, including the “type of problems encountered in the art; prior art solutions to those problems; rapidity with which innovations are made; sophistication of the technology; and educational level of active workers in the field.” Id. (internal quotation marks and citation omitted).” slip op. at 7

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “same claim construction standard that would be used in a civil action under 35 U.S.C. § 282(b), as described in Phillips v. AWH Corp., 415 F.3d 1303 (Fed. Cir. 2005) (en banc). See 37 C.F.R. § 42.100(b). Under that standard, we generally give claim terms their ordinary and customary meaning, as would be understood by a person of ordinary skill in the art at the time of the invention, in light of the language of the claims, the specification, and the prosecution history. See Phillips, 415 F.3d at 1313–14. Although extrinsic evidence, when available, may also be useful when construing claim terms under this standard, extrinsic evidence should be considered in the context of the intrinsic evidence. See id. at 1317–19. Neither Petitioner nor Patent Owner propose explicit constructions for any claim terms. Pet. 12–13; see generally Prelim. Resp. At this stage of the proceeding and based on the current record, we need not construe explicitly any claim terms because doing so would not change the outcome of the analysis below. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)).” slip op. at 8

    • Obviousness (§103) › Graham factors (scope of art, differences, level of skill)Motivation foundInstituted

      “On the current record, this argument does not identify a deficiency in Petitioner’s position as to clauses 1C and 1D. Patent Owner implies that the structures recited in clauses 1C and 1D require functionality recited elsewhere in the claim—namely, forming a “fluid dispersion” (Prelim. Resp. 4)—but Patent Owner does not adequately present evidence supporting this implied claim construction. See In re Self, 671 F.2d 1344, 1348 (CCPA 1982) (rejecting arguments “not based on limitations appearing in the claims”). Instead, Patent Owner cites to the entirety of claim 1 in support of these implied functional requirements. See Prelim. Resp. 4. Stated differently, Patent Owner has not adequately explained why any particular component (or collection of components) must perform the function of forming the “fluid dispersion” recited in clause 1G. Moreover, even assuming as correct Patent Owner’s assertion that Sevy “requires downstream separation,” Patent Owner has not explained why such a 8 In its Preliminary Response, Patent Owner appears to use different terms for the same concept: “downstream separation”; “post-formation correction”; and “post-atomization correction.” See, e.g., Prelim. Resp. 3 (“downstream separation”), 4 (“post-formation correction”), 5–6 (“post-atomization correction”). In any response, Patent Owner should clarify the scope of these terms. requirement would fall outside of the scope of claim 1. See Elbit Sys. of Am., LLC v. Thales Visionix, Inc., 881 F.3d 1354, 1359 (Fed. Cir. 2018) (“‘[A]ttorney argument is not evidence’ and cannot rebut other admitted evidence.” (quoting Icon Health & Fitness, Inc. v. Strava, Inc., 849 F.3d 1034, 1043 (Fed. Cir. 2017))). On the current record, we determine that Petitioner has made a sufficient showing that Sevy discloses or suggests the structures recited in clauses 1C and 1D.” slip op. at 14

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips
    Patents in suitUS 10,583,449
Page 1 of 22
← Previous12345…Next →

Holdings, summaries, rulings, issues, outcomes, winners and claim constructions shown for a decision were generated by a large language model reading the opinion. They are a guide to the decision, not the decision. Confirm every one against the court's own text before relying on it. Outcomes read from the patent owner’s side. Party names are extracted from the decision and are missing on about 900 short Director denials and scans, which carry the trial number instead.