  • PTAB · Oct 14, 2026 · IPR2025-00712 · APJ Kevin W Cherry · IPR · Final written decision

    Claims 1, 3–9, 13, 17, 18, 23, 25, 26, 28, and 29 were not shown unpatentable because Walker was not prior art and Kelly did not teach limitations 1[d.i] and 1[d.ii].

    RulingsFinal written decision
    • Novelty / Anticipation (§102) › Priority / effective filing date / continuation supportReference not prior artPriority date awardedDecided for patent owner

      “b) Walker Priority Date Under Dynamic Drinkware, the Petitioner is required to show that “the provisional application provides support for the claims of the patent or published application.” In re Riggs, 131 F.4th 1377, 1384 (Fed. Cir. 2025). Thus, Petitioner must show that (1) at least one claim of Walker is supported by its provisional (U.S. Provisional Application No. 60/378,289 (the “’289PROV”) and (2) the specific subject matter relied upon as prior art is supported by the ’289PROV. Id. Petitioner does provide a detailed explanation about how the ’289PROV supports claim 1 of Walker. See Reply 5–10. However, as Patent Owner argues, Petitioner fails to show that the ’298PROV provides support for the specific subject matter relied on in Walker. See Sur-Reply 3–9. Petitioner only explains how the ’298PROV discloses “predetermined criteria” but does not provide any other explanation for how the other subject matter relied on in Walker is supported by the ’298PROV. Thus, we find that Petitioner has failed to show that Walker is entitled a priority date before May 1, 2003. See Riggs, 131 F.3d at 1384 (noting while “a prior art patent or published application cannot be accorded the benefit of its provisional application’s filing date absent a showing that the provisional application provides support for the claims of the patent or published application,” the challenger must also show that “the specific portions of the patent specification identified and relied on” to demonstrate purported invalidity have written description support).” slip op. at 25

    • Obviousness (§103) › Graham factors (scope of art, differences, level of skill)Not shown unpatentableNot shown unpatentable

      “evidence that Kelly teaches limitations 1[d.i] and 1[d.ii]. As Patent Owner persuasively argues, “the recorded information regarding particular game play events” of limitations 1[d.i] and 1[d.ii] refers to “memory to . . . record game play information regarding particular game play events” in limitation 1[b.ii], but Petitioner does not map “the game play events” identified in limitation 1[b.ii] to limitations 1[d.i] and 1[d.ii]. In its Reply, Petitioner does not dispute Patent Owner’s assertion, but largely reiterates its arguments from the Petition. However, none of these arguments or evidence demonstrates that the “game play events” in limitations 1[d.i] and 1[d.ii] are same the “game play events” that are allegedly stored in limitation 1[b.ii]. Even if we accept Petitioner’s contention that it was not identifying button presses or the “game identifier,” but rather includes “game states and game events in the game process,” Petitioner provides no evidence or even arguments that what it has identified here relates to what it has identified for limitations 1[d.i] and 1[d.ii]. See Pet. 29–33 (citing Ex. 1005, 25:23–24, 26:59–27:1, 32:27–33, 37:1–10, 38:66–39:7 40:33–45, 56:49–51, 57:27–33). For these reasons, Petitioner has failed to show by a preponderance of the evidence that Kelly teaches or suggests limitations 1[d.i] and 1[d.ii]. Accordingly, we find that Petitioner has failed to show that claim 1 would have been obvious over Kelly. 2. Claims 3–9, 13, 17, 18, 23, 25, 26, 28, and 29 Claims 3–9, 13, 17, 18, 23, 25, 26, 28, and 29 all depend (either directly or indirectly) from claim 1. See PO Resp. 16 (explaining that the arguments for independent claim 1 also apply to the dependent claims inherent the deficiencies asserted with respect to the independent claims). We find Patent Owner’s arguments availing, as explained above. Accordingly, we find that Petitioner has failed to show by a preponderance of the evidence that claims 3–9, 13, 17, 18, 23, 25, 26, 28, and 29 would have been obvious over Kelly.” slip op. at 44

    • Expert testimonyPetitioner expert creditedDecided for patent owner

      “programmable variable parameter sets to achieve the mandated parameters,” we find that Patent Owner sufficiently explained “the notes from the 12/4/02 meeting reflect that the inventors proposed that their invention could raise the global payout percentage ‘to 75%’ – a mandated parameter – by ‘increas[ing] % of wins by the level 2,’ i.e., a secondary game level – a variable parameter.” See PO Resp. 28–32, 37, 38; Ex. 2016; Ex. 2017 ¶¶ 23–24, 41–42; Ex. 2012 ¶ 90, 63–64. Indeed, Mr. Crevelt confirmed that that a POSITA would unequivocally regard disclosure of “win rate[s]” and “global payout percentage[s]” as disclosing the claimed “mandated parameters” that are achieved by utilizing variable parameters. See Ex. 2020, 15:7–18:4, 19:14–21:16, 24:25–25:15 (global payout percentages), 21:18– 24:24 (win rates).” slip op. at 33

    Patent outcomesUS 11,393,279 not shown unpatentable
    § 102 anticipation§ 103 obviousnesscites Phillips · Graham
    Patents in suitUS 11,393,279
  • PTAB · Oct 14, 2026 · IPR2025-00708 · APJ Kevin W Cherry · IPR · Final written decision

    Claims 1, 3–5, 12, 13, 18–20, 22, 24–26, 29, 42, 44–47, and 50 were not shown unpatentable over Kelly or Walker and Schneier.

    RulingsFinal written decision
    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “understanding of a person of ordinary skill in the art (“POSITA”). In assessing the level of ordinary skill in the art, various factors may be considered, including the “type of problems encountered in the art; prior art solutions to those problems; rapidity with which innovations are made; sophistication of the technology; and educational level of active workers in the field.” In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995) (quoting Custom Accessories, Inc. v. Jeffrey-Allan Indus., Inc., 807 F.2d 955, 962 (Fed. Cir. 1986)). “[O]ne or more factors may predominate.” Id. Based on the testimony of Mr. Crevelt, we determine that a person of ordinary skill in the art would have had at least a bachelor’s degree in computer science or computer engineering, with at least three years of experience in game development. Pet. 14 (citing Ex. 1003 ¶¶ 62–65). Additional experience could substitute for less education, and additional education could likewise substitute for less experience. Id. We determine that the level of ordinary skill in the art adopted above is consistent with the level of technical understanding and competence reflected in the ’336 patent Specification and the asserted prior art references, based on our review of the record. Patent Owner states that “[f]or the purposes of this response, Patent Owner does not dispute Petitioners’ proposed level of skill, and under any level of skill a POSITA would not understand the asserted Grounds to raise any unpatentability issue,” and “this POR and supporting declarations apply Petitioner’s proposed level of skill.” PO Resp. 8. Thus, we adopt Petitioner’s articulation of the level of ordinary skill in the art, which is consistent with the ’336 patent and the asserted prior art, and we apply it in our obviousness analysis below.” slip op. at 11

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededDecided for patent owner

      “The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’” Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)). We determine that no terms require express construction to resolve the parties’ disputes in this case. See id. slip op. at 13

    • Novelty / Anticipation (§102) › Priority / effective filing date / continuation supportPriority date awardedDecided for patent owner

      “b) Walker Priority Date Under Dynamic Drinkware, the Petitioner is required to show that “the provisional application provides support for the claims of the patent or published application.” In re Riggs, 131 F.4th 1377, 1384 (Fed. Cir. 2025). Thus, Petitioner must show that (1) at least one claim of Walker is supported by its provisional (U.S. Provisional Application No. 60/378,289 (the “’289PROV”) and (2) the specific subject matter relied upon as prior art is supported by the ’289PROV. Id. Petitioner does provide a detailed explanation about how the ’289PROV supports claim 1 of Walker. See Reply 6–12. However, as Patent Owner argues, Petitioner fails to show that the ’298PROV provides support for the specific subject matter relied on in Walker. See Sur-Reply 3–8. Petitioner only explains how the ’298PROV discloses “predetermined criteria” but does not provide any other explanation for how the other subject matter relied on in Walker is supported by the ’298PROV. Thus, we find that Petitioner has failed to show that Walker is entitled a priority date before May 1, 2003. See Riggs, 131 F.3d at 1384 (noting while “a prior art patent or published application cannot be accorded the benefit of its provisional application’s filing date absent a showing that the provisional application provides support for the claims of the patent or published application,” the challenger must also show that “the specific portions of the patent specification identified and relied on” to demonstrate purported invalidity have written description support).” slip op. at 24

    • Obviousness (§103) › Graham factors (scope of art, differences, level of skill)Not shown unpatentableNot shown unpatentable

      “We find that Petitioner has failed to show by a preponderance of the evidence that Kelly teaches limitation 1[f]. As Patent Owner persuasively argues, “the game play events” of limitation 1[f] refers to “game play events” in limitation 1[d], but Petitioner does not map “the game play events” identified in limitation 1[d] to limitation 1[f]. In its Reply, Petitioner does not dispute Patent Owner’s assertion, but merely reiterates its arguments from the Petition. See Reply 23–24, 26. However, none of these arguments or evidence demonstrates that the “game play events” in limitation 1[f] are same the “game play events” that are allegedly stored in limitation 1[d]. Even if we accept Petitioner’s contention that it was not identifying button presses, but rather includes “game states and game events in the game process,” Petitioner provides no evidence or even arguments that what it has identified here relates to what it has identified for limitation 1[f]. See Pet. 25–26 (citing Ex. 1005, 25:23–24, 32:27–33, 40:33–45, 56:49–51). For these reasons, Petitioner has failed to show by a preponderance of the evidence that Kelly teaches or suggests limitation 1[f]. Accordingly, we find that Petitioner has failed to show that claim 1 would have been obvious over Kelly. 2. Claims 3–5, 12, 13, 18–20, 22, 24–26, 29, 42, 44–47, and 50 Claims 3–5, 12, 13, 18–20, 22, 24–26, 29, 42, 44–47, and 50 all depend from claim 1. See PO Resp. 16 (explaining that the arguments for independent claim 1 also apply to the dependent claims inherent the deficiencies asserted with respect to the independent claims). We find Patent Owner’s arguments availing, as explained above. Accordingly, we find that Petitioner has failed to show by a preponderance of the evidence that claims 3–5, 12, 13, 18–20, 22, 24–26, 29, 42, 44–47, and 50 would have been obvious over Kelly.” slip op. at 40

    Patent outcomesUS 8,529,336 not shown unpatentable
    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · Graham
    Patents in suitUS 8,529,336
  • PTAB · Oct 6, 2026 · IPR2025-00530 · APJ Scott C Moore · IPR · Final written decision

    Original claims 1–9 were canceled; the non-contingent motion to add substitute claims 10–18 was denied for lack of written-description support, and claim 18 was also indefinite.

    RulingsFinal written decision
    • 112 supportMotion to amend, deniedDenied

      “that either the ’303 application or the ’838 provisional contain adequate written description support for the disputed feature of limitation [10.d]. Though the disclosures cited by Patent Owner indicate that a secondary identifier can be used to aid in verification of a UAV, these disclosures also make clear that both first and second identifiers are transmitted by and received from the UAV. See, e.g., Ex. 2002, 4:15–17, 30:24–31:6; Ex. 2003 ¶¶ 14, 66. Patent Owner’s reliance on disclosure characterized as transmitting an identifier from a remote computing system “through the UAV” (Reply 2) is not persuasive. The cited disclosures from the ’303 application and ’838 provisional generally disclose that the identifiers transmitted by a UAV can be “generated remotely,” such as by a “remote computing system.” Ex. 2002, 14:23–15:2; Ex. 2003 ¶ 45. But Patent Owner has not identified disclosure indicating that a remote computing system may transmit an identifier to the identification receiver. In the ’303 application and ’838 provisional, only the UAV (which is part of the discrimination system, and thus not “remote”) actually transmits identifiers to the identification receiver. Patent Owner is correct in its assertion that an “aerial system identifier can be generated on-board the aerial system” or “generated remotely . . . at a remote computing system.” Mot. 7 (citing Ex. 2002, 14:23–15:2; Ex. 2003 ¶ 45). But even if a UAV’s identifier was at some time in the past generated by a remote computing system, the subsequent transmission of that identifier from the UAV to the identification receiver would not satisfy the plain language of limitation [10.d]. The claim language “receive … a second identifier from a computing system that is remote to the discrimination system” requires the receipt of a transmission of the second identifier from a remote computing system. This claim language limits the source of the received transmission (i.e., where the particular transmission is “receive[d] … from”). Thus, the relevant issue is from where was the recited second identifier received. The relevant is not where the second identifier was originally generated.” slip op. at 12

    • Disclosure Requirements (§112) › Definiteness (Nautilus)DefiniteIndefiniteMixed

      “We determine that the disputed language in limitation [10.d] is not indefinite. There is no recitation in proposed substitute claim 10 that the second identifier is transmitted solely from the identifier transmission system. Thus, the alleged irreconcilable contradiction cited by Petitioner is not recited in the claims. Petitioner’s position appears to rest on the fact that the ’303 application and ’838 provisional do not disclose receiving the second identifier from a remote computing system. See Sur-reply 6 (“To manufacture written description support, [Patent Owner] argues the claim encompasses identifiers routed ‘through the UAV.’”). Though we agree that limitation [10.d] lacks adequate written description support, this defect does not render the claim indefinite because the scope of limitation [10.d] is otherwise reasonably certain based on its plain language. See supra § III.C.4.” slip op. at 18

    • Novelty / Anticipation (§102) › Priority / effective filing date / continuation supportReference not prior artPriority date, deniedDecided for patent owner

      “In contrast, the ’393 provisional never discloses that the described drone defense system may use the identity of a detected drone to develop a particular countermeasure. The disclosed RTSS certainly uses identity information to determine whether a drone is a threat. And if a threat is identified, the RTSS immediately starts “a series of processes … to determine what rule of engagement will be applied on the intruding drone.” Ex. 1006 ¶ 10. The ’393 provisional discloses that the system may select a particular countermeasure based on (i) the particular zone within a protected area within which a drone is located, (ii) “the behavior of the hostile drone,” or (iii) “other instructions.” Id. ¶¶ 9, 10. But the ’393 provisional never discloses that these “other instructions” may include the identity of the drone. The system disclosed in the ’393 provisional uses the identity of a drone to determine whether to activate the countermeasure system. See id. ¶¶ 16–18. But there is no disclosure in the ’393 provisional that the countermeasure system, once activated, uses the identity of the drone to develop the particular countermeasure to be employed. See generally Ex. 1006. Thus, though the Whitmarsh reference itself contains ample written description support for limitation [19e], the earlier-filed ’393 provisional does not. On this record, and having reviewed the ’393 provisional in its entirety, we determine that the ’393 provisional does not “reasonably convey[] to those skilled in the art that the inventor had possession of” the subject matter of limitation [19e] of Whitmarsh’s claim 19 “as of the filing date” of the ’393 provisional. See Ariad, 598 F.3d at 1351.” slip op. at 27

    § 102 anticipation§ 112 disclosurecites Nautilus
    Patents in suitUS 10,249,199
  • PTAB · Nov 13, 2025 · IPR2025-00805 · APJ Eric C Jeschke · IPR · Institution

    The Board instituted IPR on claims 1–24 and all asserted grounds, finding a reasonable likelihood that Petitioner would prevail on at least one challenged claim.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “review. See 35 U.S.C. § 314; 37 C.F.R. § 42.4(a) (2024) (“The Board institutes the trial on behalf of the Director.”). Inter partes review may not be instituted “unless . . . the information presented in the petition . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314. Upon consideration of the evidence and arguments in the record, for the reasons below, we determine that the information presented shows a reasonable likelihood that Petitioner would prevail with respect to at least one of the challenged claims. We thus institute inter partes review on all challenged claims on all asserted grounds. See SAS Inst. Inc. v. Iancu, 584 U.S. 357, 362–63, 369–70 (2018); 37 C.F.R. § 42.108(a) (“When instituting inter partes review, the Board will authorize the review to proceed on all of the challenged claims and on all grounds of unpatentability asserted for each claim.”).” slip op. at 2

    • PTAB / AIA Trials › Discretionary denial › §325(d) same art / argumentsNot reached

      “C. Patent Owner’s Arguments Under 35 U.S.C. § 325(d) In the Preliminary Response, Patent Owner contends that Petitioner’s unpatentability arguments presented in this proceeding were previously considered by the USPTO. See Prelim. Resp. 31–33. In her decision referring this matter to the Board, then-Acting Director Stewart rejected that argument. See Paper 20 at 2–3 (discussing why “Petitioner provides persuasive reasoning, supported by evidence, that discretionary denial under 35 U.S.C. § 325(d) is not appropriate”); see also Prelim. Resp. 31–33 (referring to and citing Patent Owner’s Discretionary Denial Brief (Paper 8)). We need not and do not address this issue further.” slip op. at 15

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “For purposes of this Decision, we adopt the definition of the level of ordinary skill in the art proposed by Petitioner. As to the inclusion of physics in Petitioner’s definition, Dr. Singhose (a professor of mechanical engineering) testifies as to why undergraduate mechanical engineering degree holders would have the requisite knowledge here, but does not testify that undergraduate physics degree holders would not. See Singhose Decl. ¶¶ 2, 27, 28. In addition, Patent Owner and Dr. Singhose require “a four-year degree in mechanical engineering or a closely related field,” but fail to identify what fields are “closely related.” See Prelim. Resp. 11; Singhose Decl. ¶ 27. Based on the Morse Declaration, we are persuaded at this stage that a hypothetical undergraduate physics degree holder would have adequate knowledge for one of ordinary skill in the art of the invention here. See Morse Decl. ¶ 31. As to the requisite years of experience proposed in the definitions— three for Petitioner versus “at least one” for Patent Owner—we note that Patent Owner’s definition is broader than, but includes, Petitioner’s definition. Moreover, for both the inclusion of physics and the years of experience issues, Patent Owner acknowledges that the arguments in the Preliminary Response “are not impacted based on which definition is applied.” Prelim. Resp. 12 (citing Singhose Decl. ¶¶ 30–34). Further, Patent Owner does not argue at this stage that Petitioner’s proposal for the level of ordinary skill leads to an improper understanding of how a skilled artisan would understand either the challenged patent or the prior art.” slip op. at 11

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “B. Claim Construction In inter partes reviews, the Board interprets claim language using the same claim construction standard that would be used in a civil action under 35 U.S.C. § 282(b), as described in Phillips v. AWH Corp., 415 F.3d 1303 (Fed. Cir. 2005) (en banc). See 37 C.F.R. § 42.100(b). Under that standard, we generally give claim terms their ordinary and customary meaning, as would be understood by a person of ordinary skill in the art at the time of the invention, in light of the language of the claims, the specification, and the prosecution history. See Phillips, 415 F.3d at 1313–14. Although extrinsic evidence, when available, may also be useful when construing claim terms under this standard, extrinsic evidence should be considered in the context of the intrinsic evidence. See id. at 1317–19. Petitioner does not propose express constructions for any claim terms. Pet. 12. Patent Owner also does not propose any express constructions. See Prelim. Resp. 12. On the current record, we need not construe explicitly any claim terms. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)). As discussed below, however, the parties dispute the meaning of “gaseous fuel.” We address this issue below in the analysis of the challenge to claims 1–3, 5–9, and 18 based on Nakafushi and Olmr.” slip op. at 12

    Claim construction§ 102 anticipation§ 103 obviousnessDiscretionary denialcites Phillips
    Patents in suitUS 10,393,034
  • PTAB · Oct 16, 2025 · IPR2025-00711 · APJ Linda E Horner · IPR · Institution

    The Board instituted IPR on claims 1, 2, 4–7, 9, 11–13, 15, 19, 23, 24, and 29 based on a reasonable likelihood of success on the § 103 challenges.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “Under 35 U.S.C. § 314(a), an inter partes review may not be instituted unless the information presented in the petition and the preliminary response shows “there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” Upon consideration of the Petition and the Preliminary Response, and for the reasons explained below, we determine that Petitioner has shown a reasonable likelihood that it would prevail with respect to at least one of the challenged claims. Thus, we grant the Petition and institute an inter partes review of claims 1, 2, 4–7, 9, 11‒13, 15, 19, 23, 24, and 29 of the ’164 patent.” slip op. at 2

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “Cir. 2012). “The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’” Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (alteration in original) (quoting Vivid Techs., Inc. v. Am. Sci. Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)). Petitioner argues that it is not necessary for us to provide an express construction for any claim term because the Petition “establishes the prior art meets each claim limitation under any reasonable construction.” Pet. 13. Patent Owner similarly submits that we “need not construe any terms at this stage, because under any reasonable construction of the claim terms, the prior art fails to disclose or suggest the claimed features.” Prelim. Resp. 9. At this stage of the proceeding, we do not need to expressly construe any claim terms to determine whether Petitioner showed a reasonable likelihood of prevailing as to its challenge of at least one challenged claim.” slip op. at 14

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundInstituted

      “Kelly discloses that game processor 12 implements the functions of game unit 10 during a game process and includes several input and output functions (Ex. 1005, 9:15–18), including: The game processor controls the game apparatus by receiving inputs from a player, from other game apparatuses, from a server (described below), from a progressive bonus apparatus, and from other sources. The game processor also controls output signals to update the game process when appropriate. In addition, the game processor controls the redemption system of the present invention by calculating when prizes are awarded, calculating and updating prize lists and prize costs, and other functions, as described below. Ex. 1005, 9:18–27. As to the redemption system, Kelly discloses prize table 480 that is displayed to the operator. Ex. 1005, 34:64–65, Fig. 9a. In one embodiment, the operator can adjust prize characteristics for the game unit and any linked game units. Id. at 35:1–2. Kelly also discloses an alternative embodiment, however, in which selection of a specific prize from the table 480 can be based on random and/or statistical determination. Id. at 36:48–49. In this alternative embodiment, “random determination of whether a particular prize is to be awarded is also modified by statistical information to create a ‘best fit’ of prizes awarded according to the operator’s desired odds.” Id. at 36:63–66. awarded every 8,000 games, so if it is randomly determined that a third video console is to be awarded within, for example, the 3000th game, then a different prize, e.g., the next most valuable prize, can be awarded so that the desired odds are better met. Id. at 37:1–9. Thus, we find Petitioner has set forth sufficient evidence to show a reasonable likelihood that Kelly’s game processor can modify the variable parameters of the prizing structure to meet the mandated parameters of the desired odds, as called for in limitation [1.c.v].” slip op. at 23

    • Novelty / Anticipation (§102) › Priority / effective filing date / continuation supportReference is prior artOther

      “To remove Walker as prior art under §§ 102(a) and 102(e), Patent Owner must show either it reduced the invention to practice prior to Walker’s effective date, or that it invented prior to Walker’s effective date. In the case of the latter, Patent Owner must demonstrate conception prior to May 1, 2003, and reasonably continuous diligence throughout the entire critical period, which begins just prior to the Walker’s effective date and ends on the date of the invention’s actual or constructive reduction to practice. Patent Owner provides evidence purporting to show that it conceived of the invention prior to May 1, 2003. Patent Owner has not asserted that this evidence demonstrates actual reduction to practice, nor do we have sufficient evidence at this stage to make that determination. Further, Patent Owner’s earliest possible constructive reduction to practice (September 1, 2004) does not pre-date Walker’s effective date. Thus, at this stage, Patent Owner would need to show it invented prior to Walker’s effective date through evidence of conception and reasonable diligence to remove Walker as prior art. At this stage of the proceeding, without Patent Owner’s evidence of diligence, Patent Owner has not provided sufficient evidence to show that Petitioner fails to show a reasonable likelihood of prevailing in establishing that Walker is prior art. This issue of whether Walker is prior art to the ’164 patent will benefit from further development of the record during the trial proceeding.” slip op. at 31

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · Graham
    Patents in suitUS 11,335,164
  • PTAB · Oct 16, 2025 · IPR2025-00712 · APJ James A Tartal · IPR · Institution

    The Board instituted inter partes review of claims 1, 3–9, 13, 17, 18, 23, 25, 26, 28, and 29 on all asserted grounds, finding a reasonable likelihood of prevailing on claim 1 over Walker.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “review. 35 U.S.C. § 314(b) (2018); 37 C.F.R. § 42.4(a) (2025). An inter partes review may not be instituted “unless . . . the information presented in the petition . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). Upon institution of inter partes review, the review proceeds “on all of the challenged claims and on all grounds of unpatentability asserted for each claim.” 37 C.F.R. § 42.108(a). Based on our consideration of the Petition, the Preliminary Response, and the evidence of record, we conclude that the information demonstrates a reasonable likelihood that Petitioner would prevail in showing the unpatentability of at least one of the Challenged Claims. Accordingly, we institute an inter partes review as to the Challenged Claims of the ’279 patent on all grounds asserted in the Petition.” slip op. at 2

    • Novelty / Anticipation (§102) › Priority / effective filing date / continuation supportPriority date awardedOther

      “application filed November 12, 2021, that asserts the benefit of a series of applications, the earliest of which was filed September 2, 2003. Ex. 1001, codes (22), (45), (60). Petitioner asserts that the Challenged Claims of the ’279 patent “are entitled to an effective filing date of no earlier than September 2, 2003,” consistent with the date of the earliest application identified by the ’279 patent.9 See Pet. 6. For purposes of our analysis on the current record, in this Decision we apply September 2, 2003, as the priority date of the Challenged Claims.” slip op. at 18

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successInstituted

      “independent claim 1. Pet. 32–63. Petitioner relies on the testimony of Mr. Crevelt in support of its contentions with respect to claim 1. Ex. 1003 ¶¶ 234–286. Further, according to Petitioner, “[n]o findings regarding motivation to combine or reasonable expectation of success are necessary with a single reference ground,” but Walker “teaches that the features of the embodiments are options that can be combined.” Pet. 42 n.6 (citing Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1372–73 (Fed. Cir. 2019). At this stage, Patent Owner does not contest Petitioner’s proffered assertions about the” slip op. at 20

    § 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,393,279
  • PTAB · Oct 16, 2025 · IPR2025-00708 · APJ James A Tartal · IPR · Institution

    The Board instituted IPR on all challenged claims and grounds, finding a reasonable likelihood that claims 1, 3–5, 12, 13, 18–20, 22, 24–26, 29, 42, 44–47, and 50 are unpatentable over Walker and Schneier.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “We have authority to determine whether to institute an inter partes review. 35 U.S.C. § 314(b) (2018); 37 C.F.R. § 42.4(a) (2025). An inter partes review may not be instituted “unless . . . the information presented in the petition . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). Upon institution of inter partes review, the review proceeds “on all of the challenged claims and on all grounds of unpatentability asserted for each claim.” 37 C.F.R. § 42.108(a). Based on our consideration of the Petition, the Preliminary Response, and the evidence of record, we conclude that the information demonstrates a reasonable likelihood that Petitioner would prevail in showing the unpatentability of at least one of the Challenged Claims. Accordingly, we institute an inter partes review as to the Challenged Claims of the ’336 patent on all grounds asserted in the Petition.” slip op. at 2

    • Skill levelSkill level board ownOther

      “B. Level of Ordinary Skill in the Art At this stage of the proceeding, there is no evidentiary dispute about the level of ordinary skill in the art.8 Based on the testimony of Mr. Crevelt, we determine that a person of ordinary skill in the art would have had at least a bachelor’s degree in computer science or computer engineering, with at least three years of experience in game development. Pet. 14 (citing Ex. 1003 ¶¶ 62–65). Additional experience could substitute for less education, and additional education could likewise substitute for less experience. Id. We determine that the level of ordinary skill in the art 7 Petitioner states that it is not aware of secondary considerations that affect the obviousness arguments it presents. Pet. 66. Patent Owner has not offered objective evidence of nonobviousness at this stage of the proceeding. 8 Patent Owner “disagrees with the proposed level of skill” but asserts that “under any level of skill a [person of ordinary skill in the art] would not understand the asserted Grounds to raise any unpatentability issues.” Prelim. Resp. 8. Thus, Patent Owner does not present evidence or arguments in its Preliminary Response related to the level of ordinary skill in the art. competence reflected in the ’336 patent Specification and the asserted prior art references, based on our review of the limited record.” slip op. at 11

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “standard as would be used by a district court to construe a claim in a civil action involving the validity or infringement of a patent. 37 C.F.R. § 42.100(b). Under that standard, claim terms are given their ordinary and customary meaning, as would have been understood by a person of ordinary skill in the art at the time of the invention, in light of the language of the claims, the specification, and the prosecution history of record. Id.; see also Phillips v. AWH Corp., 415 F.3d 1303, 1312–19 (Fed. Cir. 2005) (en banc); Thorner v. Sony Comput. Entm’t Am. LLC, 669 F.3d 1362, 1365–66 (Fed. Cir. 2012). “The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’” Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (alteration in original) (quoting Vivid Techs., Inc. v. Am. Sci. Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)). Petitioner argues that it is not necessary for us to provide an express construction for any claim term because the Petition “establishes the prior art meets each claim limitation under any reasonable construction.” Pet. 14–15. Patent Owner similarly submits that we “need not construe any terms at this stage, because under any reasonable construction of the claim terms, the prior art fails to disclose or suggest the claimed features.” Prelim. Resp. 8. At this stage of the proceeding, we do not need to expressly construe any claim terms to determine whether Petitioner showed a reasonable likelihood of prevailing as to its challenge of at least one challenged claim.” slip op. at 12

    • Novelty / Anticipation (§102) › Priority / effective filing date / continuation supportPriority date awardedOther

      “an application filed September 20, 2010, that asserts the benefit of an application filed September 2, 2003. Ex. 1001, codes (22), (45), (54), (62). Petitioner asserts that the Challenged Claims of the ’336 patent “are entitled to an effective filing date of no earlier than September 2, 2003,” consistent with the date of the earliest application identified by the ’336 patent.9 See Pet. 7. For purposes of our analysis on the current record, in this Decision we apply September 2, 2003, as the priority date of the Challenged Claims. Walker was filed on May 1, 2003, and refers back to a provisional application filed on May 6, 2002, but Walker was not published until January 1, 2004. Ex. 1006, codes (22), (43), (60). Thus, Petitioner fails to show on the current record how, under pre–AIA 35 U.S.C. § 102(a), Walker discloses an invention that was described in a printed publication in this country before the invention thereof by the Patent Owner, because Walker was published after the applied priority date of the Challenged Claims of the’336 patent.” slip op. at 17

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 8,529,336
  • PTAB · Oct 10, 2025 · IPR2025-00653 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution on all claims because the Petition did not show a reasonable likelihood that any challenged claim was unpatentable over the asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “An inter partes review may be instituted only if “the information presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’504 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 12

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “Additionally, only terms that are in controversy need to be construed, and these need be construed only to the extent necessary to resolve the controversy. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’”) (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)). The parties assert that each claim term should be construed in accordance with its plain and ordinary meaning. Pet. 9; Prelim. Resp. 4 (citing Ex. 2009 ¶ 72); see Ex. 1002 ¶ 22 (opining the same). And, in the respective claim construction sections of their briefs, the parties do not propose any claim terms for express construction. We agree with the parties that no claim terms require express construction to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 13

    • Expert testimonyPetitioner expert discountedDecided for patent owner

      “Ex. 1002 ¶ 47. As reflected above, Dr. Wooley’s testimony as to element [1.2] does not even assert that Cardamone discloses a tank, let alone one or more sensors disposed at a tank as recited in element [1.2]. Thus, Dr. Wooley’s testimony does not support Petitioner’s argument on this issue.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,726,504
  • PTAB · Oct 10, 2025 · IPR2025-00652 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–23 and 25–30 were unpatentable over the asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’403 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 12

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “The parties assert that each claim term should be construed in accordance with its plain and ordinary meaning. Pet. 10; Prelim. Resp. 4 (citing Ex. 2009 ¶ 73); see Ex. 1002 ¶ 22 (opining the same). And, in the respective claim construction sections of their briefs, the parties do not propose any claim terms for express construction. We agree with the parties that no claim terms require express construction to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 13

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “We agree with Patent Owner that the Petition fails to demonstrate that Kahn discloses element [1.2] because the evidence cited does not disclose a “first computer system being configured to provide remote control of the first pump or first valve” (i.e., a fluid-handling device). Kahn is directed to providing access to fluid sensing data and analyzing and providing visual information on that data, but Petitioner has not identified any disclosure of the capability to remotely control fluid-handling devices. See, e.g., Ex. 1005, code (54), 1:27–36, 2:50–3:2. More specifically, Kahn’s disclosures that Petitioner relies on for allegedly teaching remote control are deficient. We discuss each. First, Petitioner points to the following, “[f]or instance, as illustrated in FIG. 1C, a fluid control device such as a valve 15A is located on the input side of a sen[s]or unit 110.” Ex. 1005, 8:19–21, cited in Pet. 13. This portion of Kahn, however, does not disclose remote control. Second, Petitioner cites to the following: Finally, or in addition to, the communication unit 112B can include on-site alerts such as optical (indicator lights), audible alerts (e.g., alarm sounds), tactile (e.g., vibration of the unit) or can be interfaced to an appropriate control valve for simply shutting off the supply of fluid upon the detection of emergency events, for instance. Pet. 13 (citing Ex. 1005, 10:62–67). We agree with Patent Owner that this portion of Kahn teaches on-site alerts and local control of the fluid-handling device. See Prelim. Resp. 7. This portion of Kahn does not disclose remote control.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,294,403
  • PTAB · Oct 10, 2025 · IPR2025-00651 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–3, 6, 7, and 9–20 were unpatentable over any asserted ground.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’680 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 11

    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed patent owner constructionDecided for patent owner

      “target value” is part of a command that is sent from a computing device to a server and then to a controller. The controller then receives a measurement of the fluid by a sensor and determines whether the measurement satisfies the “target value.” If the measurement does not satisfy the “target value,” further operations are undertaken. The recited operation sequence makes clear that the plain and ordinary meaning of “target value” is not as Dr. Wooley opines because the particular operating condition that a device is in at a particular time is represented by the measurement taken by the sensor, 11 Some claim language less relevant to construing “target value” was omitted for ease of reference. which the controller then uses to determine whether the measurement satisfies the “target value.” Additionally, claim 1 recites that the “target value” is sent as part of a command to the controller. The “target value” is not sent to the controller from the sensor, as might be expected if the plain and ordinary meaning of “target value” were as Dr. Wooley opines. Petitioner and Dr. Wooley’s construction would also result in “target value” meaning effectively the same thing as the measurement of the fluid by the sensor, a concept that is separately recited in claim 1 and to which the “target value” is compared. The Specification of the ’680 patent does not support Petitioner’s understanding of the plain and ordinary meaning of “target value.” Although the Specification does not recite “target value,” it recites “target state,” and describes “target state” sufficiently to understand the plain and ordinary meaning of “target” as used in “target value” and “target state.” In particular, the ’680 patent explains that “[i]n some embodiments, the process 104 includes receiving, via a network interface, from a remote user device, (e.g., via a command-center server) a command to change a state of a fluid-handling device to a target state.” Ex. 1001, 11:48–51. This portion reflects that the command is seeking to change a state of a fluid-handling device to a target state. In other words, the “target value” or “target state” is not generally “the particular operating condition that a device is in at a particular time”; rather, it is a value or state that the fluid-handling device is desired to be in, as Patent Owner and Dr. Durham explain. Additionally, just as claim 1 recites a directional component for the “target value” to be sent to the controller in a command, so too does the Specification describe a “target state” as being sent in a command from a remote user device. Thus, the Specification clearly supports the plain and ordinary meaning proposed by Patent Owner and Dr. Durham and not the plain and ordinary meaning proposed by Petitioner and Dr. Wooley. slip op. at 14

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “time-stamped process data, report exception therein to the remote host, and extract and transmit time-stamped process data to the remote host.” Ex. 1005, Abst. (emphases added). Almadi explains that its remote field systems must include a plurality of controller units “to issue commands to, and gather and process data from a plurality of field devices, including remote systems and instruments, . . . [and] a database server for the storage of process data retrieved from the remote subsystems and instruments.” Id. at 2:22–30 (emphases added). Based on these disclosures, we agree with Patent Owner that Petitioner has not established that Almadi discloses element [1.4]. Specifically, the teachings from Almadi identified by Petitioner refer to process data, which is data retrieved from the remote subsystems/field devices. Thus, we understand that Almadi’s teaching—of using an Ethernet switch to transmit “process data”—describes transmitting data from the remote subsystems/field devices. See Ex. 1005, 3:13–17, cited in Pet. 15. But claim 1 and particularly element [1.4], recites “sending, with the server, the target value to the network address [which identifies a controller of the fluid-handling device13] via the network,” which is different than sending process data from the field devices to the remote host or database server for storage.” slip op. at 19

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,175,680
Page 1 of 15
← Previous12345…Next →

Holdings, summaries, rulings, issues, outcomes, winners and claim constructions shown for a decision were generated by a large language model reading the opinion. They are a guide to the decision, not the decision. Confirm every one against the court's own text before relying on it. Outcomes read from the patent owner’s side. Party names are extracted from the decision and are missing on about 900 short Director denials and scans, which carry the trial number instead.