  • PTAB · Oct 31, 2024 · IPR2024-00858 · APJ Carl M Defranco · IPR · Institution

    The Board instituted review of claims 5–7 and 16–19, finding a reasonable likelihood that claims 5–7 and 16–19 are unpatentable over Samartgis and at least claims 5 and 19 over Leoncavallo.

    RulingsInstitution decision
    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “U.S.C. § 314(a) due to the advanced state of the parallel district court action, and, in doing so, relies heavily on the district court’s scheduled trial date of September 22, 2025. See Prelim. Resp. 51, 54. While the district court’s scheduled trial date may be earlier than the Board’s projected deadline for a final written decision here, CamelBak’s reliance on that date is misplaced. The Office takes the position that a district court’s scheduled trial dates are “unreliable and often change” and that a more reliable indicator is the district court’s “median time-to-trial for civil actions,” which, in this case, would place the district court’s trial date after the projected deadline of any final written decision here. See Director Memorandum, Interim Procedure for Discretionary Denials in AIA-Post Grant Proceedings With Parallel District Court Litigation, U.S. PATENT AND TRADEMARK OFFICE (June 21, 2022) (“Director’s Interim Procedure”), at 8–9. Thus, CamelBak’s reliance 5 US D586,184 S, issued Feb. 10, 2009 (Ex. 1006, “Miller”). on the district court’s scheduled trial date has no bearing on whether we should discretionarily deny institution. Of greater relevance is Trove’s express stipulation not to pursue the same grounds in the district court action as advanced in the petition or any ground that relies on the prior art references cited in the petition. See Pet. 100. Although not exactly a Sotera stipulation, the Office nonetheless recognizes that such stipulations further mitigate concerns of potentially conflicting decisions and duplicative efforts between us and the district court. See Director’s Interim Procedure, at 7–8. Thus, given Trove’s stipulation and the fact that the district court’s median time-to-trial is after the projected deadline of our final written decision here, we will not discretionarily deny institution under § 314(a).” slip op. at 6

    • PTAB / AIA Trials › Discretionary denial › §325(d) same art / argumentsDenied

      “We disagree that Samartgis is the substantially the same as the corresponding design patent cited during prosecution, mainly because the design patent fails to show the closure retention mechanism that is clearly shown and described in Samartgis and goes to the very heart of Trove’s showing of anticipation and obviousness. Compare Ex. 1004, Figs. 3–5 (showing lug members 15, 16 and ramp sections 23, 25, 27), with Ex. 2001, Figs. 1–8 (omitting any depiction of lug members or ramp sections). Thus, Samartgis clearly was not considered. And, although Leoncavallo and Miller may arguably have been considered during prosecution, “[w]hen instituting . . . review, the Board will authorize the review to proceed on all of the challenged claims and on all grounds of unpatentability asserted for each claim.” 42 C.F.R. § 42.108(a). As such, we will not discretionarily deny institution under § 325(d). B. Level of Ordinary Skill in the Art” slip op. at 8

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Trove proposes that one of ordinary skill in the art would have had: an undergraduate degree in mechanical engineering or equivalent coursework, and a year or more of experience in designing, prototyping, and/or manufacturing fluid containers or similar products . . . [and that] [m]ore work experience may substitute for a lower level of education, and vice versa. Pet. 17–18 (citing Ex. 1003 ¶¶ 25–30). CamelBak appears to agree. See Prelim. Resp. 16 (“Patent Owner assumes Petitioner has correctly stated the level of ordinary skill in the art and does not set forth its own definition.”). At this stage, we see no reason to depart from Trove’s proposed definition, as it appears reasonable and consistent with the asserted prior art and the ’252 patent.” slip op. at 8

    • Claim Construction › Functional claiming / §112(f) means-plus-function › Whether §112(f) applies (Williamson, nonce words)Not reached

      “At this stage, we do not see the need to resolve the § 112(f) issue in light of Trove’s express and unrebutted showing that the prior art teaches sufficiently analogous structure to that identified in the ’252 patent for performing the disputed functional limitations of the claimed “closure retention mechanism.” See Pet. 35 (asserting that “[Samartgis’s] lug members 15 and 16 also are at least equivalent to the structure identified in the specification (i.e., the two or more spaced-apart tabs on the handle)” because “[l]ike the opposed tabs of the ’252 patent, the lug members 15 and 16 are projections that extend from the inner surface of the handle to engage the closure.”). Indeed, at this stage, CamelBak chooses not to address Trove’s showing in this regard, instead arguing that “the construction of ‘closure retention mechanism’ is irrelevant because [Trove] fails to show lug members 15 and 16 are configured to meet other limitations of claims 5 and 19.” Prelim. Resp. 20 n.7. That said, to the extent either party believes it is necessary for final resolution of patentability, they should explore the § 112(f) issue further during the trial phase.” slip op. at 10

    Claim construction§ 102 anticipationDiscretionary denial
    Patents in suitUS 8,905,252
  • PTAB · Oct 2, 2024 · IPR2024-00706 · APJ Sheila F Mcshane · IPR · Institution

    The Board denied institution on all challenged claims and grounds because Petitioner did not show a reasonable likelihood of prevailing on at least one claim.

    RulingsInstitution decision
    • Parallel petitionsDecided for petitioner

      “The Board has indicated that “one petition should be sufficient to challenge the claims of a patent in most situations.” Consolidated Trial Practice Guide 59 (Nov. 2019) (“CTPG”).6 But “the Board recognizes that there may be circumstances in which more than one petition may be necessary.” Id. Here, although there is overlap in the prior art asserted, there are clear differences in the limitations in the respective claim sets in each case, which requires different analysis. The issues related to a potentially different priority date for claims in the -715 case also support the need for two petitions. Additionally, under these circumstances, it is not apparent there has been a substantial benefit afforded to Petitioner by filing two petitions. Thus, we determine that Petitioner’s filing of two parallel petitions does not weigh in favor of exercising our discretion to deny institution in this particular case.” slip op. at 9

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “partes review. See 35 U.S.C. § 314; 37 C.F.R. § 42.4(a). Under 35 U.S.C. § 314(a), we may not authorize an inter partes review unless the information in the petition and the preliminary response “shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” For the reasons stated below, we determine that Petitioner has not established a reasonable likelihood that it would prevail with respect to at least one claim. We therefore do not institute inter partes review.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Patent Owner does not challenge Petitioner’s definition of a person of ordinary skill in the art and its definition appears to be similar to that of Petitioner’s definition. Prelim. Resp. 10. For the purposes of this Decision, we adopt the assessment offered by Petitioner as it is consistent with the ’534 patent and the prior art before us. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001).” slip op. at 10

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “Petitioner argues that “[t]he invalidity issues raised in this Petition may be resolved without any formal claim construction.” Pet. 3. Patent Owner offers no claim construction. Prelim. Resp. 9–10. We determine that we need not expressly construe any claim terms to resolve the parties’ disputes on the current record. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“[W]e need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))).” slip op. at 10

    Claim construction§ 102 anticipation§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 10,877,534
  • PTAB · Oct 2, 2024 · IPR2024-00715 · APJ Sheila F Mcshane · IPR · Institution

    The Board denied institution because Vicor had not shown a reasonable likelihood of prevailing on any challenged claim over the asserted grounds.

    RulingsInstitution decision
    • Parallel petitionsDecided for petitioner

      “The Board has indicated that “one petition should be sufficient to challenge the claims of a patent in most situations.” Consolidated Trial Practice Guide 59 (Nov. 2019) (“CTPG”).7 But “the Board recognizes that there may be circumstances in which more than one petition may be necessary.” Id. Here, although there is overlap in the prior art asserted, there are clear differences in the limitations in the respective claim sets in each case, which requires different analysis. The issues related to a potentially different priority date for claims in this case also support the need for two petitions.8 Additionally, under these circumstances, it is not apparent there has been a substantial benefit afforded to Petitioner by filing two petitions. Thus, we determine that Petitioner’s filing of two parallel petitions does not weigh in favor of exercising our discretion to deny institution in this particular case.” slip op. at 9

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “have had (1) at least a bachelor’s degree in electrical engineering or a related field, and (2) at least two years of industry experience in power engineering” as of the date of the invention and that “[a]dditional graduate education could substitute for professional experience, and vice versa.” Pet. 3–4 (citing Ex. 1003 ¶¶ 47–48). 7 Available at https://www.uspto.gov/TrialPracticeGuideConsolidated. 8 We address the merits of the priority issue below. Patent Owner does not challenge Petitioner’s definition of a person of ordinary skill in the art and its definition appears to be similar to that of Petitioner’s definition. Prelim. Resp. 9. For the purposes of this Decision, we adopt the assessment offered by Petitioner as it is consistent with the ’534 patent and the prior art before us. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001).” slip op. at 9

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “Petitioner argues that “[t]he invalidity issues raised in this Petition may be resolved without any formal claim construction.” Pet. 3. Patent Owner offers no claim construction. Prelim. Resp. 9. We determine that we need not expressly construe any claim terms to resolve the parties’ disputes on the current record. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“[W]e need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))).” slip op. at 10

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “partes review. See 35 U.S.C. § 314; 37 C.F.R. § 42.4(a). Under 35 U.S.C. § 314(a), we may not authorize an inter partes review unless the information in the petition and the preliminary response “shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” For the reasons stated below, we determine that Petitioner has not established a reasonable likelihood that it would prevail with respect to at least one claim. We therefore do not institute inter partes review.” slip op. at 2

    Claim construction§ 102 anticipation§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 10,877,534
  • PTAB · Oct 1, 2024 · IPR2024-00705 · APJ Thu A Dang · IPR · Institution

    The Board instituted IPR on claims 1–6 under all five grounds, finding a reasonable likelihood of unpatentability based on Zeng-014 and Vinciarelli-218.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “whether to institute an inter partes review. Applying the standard set forth in 35 U.S.C. § 314(a), which requires demonstration of a reasonable likelihood that Petitioner would prevail with respect to at least one challenged claim, we grant Petitioner’s request and institute an inter partes review of all challenged claims.” slip op. at 2

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “the first electronic component’ for the first connection part is a structural feature or relationship.” Prelim. Resp. 8 (citing Ex. 2001 ¶¶ 52–54). Here, claim 1 requires a structure in which the first connection part comprises a first terminal at one end coupled to a surface of a carrier such as a circuit board, and a second terminal at the other end attached to a surface of the first component, such that the first connection part has mechanical support of the first electronic component. See Ex. 1001, 15:31–37. We are persuaded by Patent Owner’s contention that “this claim language connotes sufficient structural characteristics that preclude a product-by-process.” Prelim. Resp. 9.” slip op. at 10

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “B. Principles of Law To establish anticipation, each and every element in a claim, arranged as recited in the claim, must be found in a single prior art reference. Net MoneyIN, Inc. v. VeriSign, Inc., 545 F.3d 1359, 1371 (Fed. Cir. 2008). There is no requirement that the prior art must use the same words to describe a claim element in order to teach or disclose that claim element. Identity of terminology is not required for a claim element to be anticipated by the prior art without resorting to obviousness. See In re Gleave, 560 F.3d 1331, 1334 (Fed. Cir. 2009); In re Bond, 910 F.2d 831, 832 (Fed. Cir. 1990).” slip op. at 11

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation not foundNot shown unpatentable

      “The Federal Circuit has repeatedly warned that there has to be evidence of “glue” to make this specific combination, and not just the use of the claim as the roadmap for making the combination of prior art. See, e.g., InTouch Technologies, Inc. v. VGO Communications, Inc., 751 F.3d 1327, 1348–49 (Fed. Cir. 2014) (“Dr. Yanco’s testimony was nothing more than impermissible hindsight; she opined that all of the elements of the claims disparately existed in the prior art, but failed to provide the glue to combine these references.”). Here, Petitioner’s alleged motivations to modify the modules Vinciarelli-218 to use the “connection part by curving a piece of metal against an electronic component” of Zeng-014 (Pet. 69) reflect impermissible hindsight bias.” slip op. at 25

    Claim construction§ 102 anticipation§ 103 obviousnesscites KSR · Graham
    Patents in suitUS 9,819,263
  • PTAB · Sep 18, 2024 · IPR2024-00702 · APJ Sharon Fenick · IPR · Institution

    The Board instituted review of claims 1–6 and 8–16 on all asserted grounds, finding a reasonable likelihood that the Nair and Forsberg combination renders at least claim 1 obvious.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “The Board has authority to determine whether to institute an inter partes review. See 35 U.S.C. § 314(b) (2018); 37 C.F.R. § 42.4(a). Under 35 U.S.C. § 314(a), an inter partes review may not be authorized unless the information in the Petition and any preliminary response “shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” For the reasons that follow, we institute an inter partes review as to the challenged claims of the ’817 patent on all grounds of unpatentability presented.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “B. Level of Ordinary Skill in the Art Petitioner, citing Dr. Bims’s declaration, asserts that, “[a] person of ordinary skill in the art (“POSITA”) in the subject matter of the ’817 patent would have had a master’s degree in electrical engineering, computer engineering, or computer science, or equivalent and at least three years of experience in the field of telecommunications or wireless systems,” and that “[a]dditional education might compensate for less experience, and vice-versa.” Pet. 10–11 (citing Ex. 1002 ¶ 22). Patent Owner asserts that one of ordinary skill would have had “a bachelor’s degree in electrical engineering, computer engineering, or computer science with (1) at least three years of experience in the field of telecommunications or wireless systems; and/or (2) an advanced degree in field of telecommunications or wireless systems.” Prelim. Resp. 16. We do not discern a meaningful difference between the two parties proposals. Petitioner’s proposal appears consistent with the problems and solutions in the ’817 patent and prior art of record and is supported by expert testimony. We note, however, that the open-ended language “at least” expands the range of experience indefinitely with no upper bound. Upon this preliminary record and for the purposes of institution, we adopt Petitioner’s definition of the level of skill with the exception that we delete the words “at least.”” slip op. at 9

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “C. Claim Construction Neither party makes a claim construction proposal or indicates that any claim requires construction. Pet. 11; see generally Prelim. Resp. We note that an argument was raised that presents an implicit construction question regarding whether a flag which “only identifies if encryption [is] ‘on’ or ‘off’” (Prelim. Resp. 24) teaches or suggests “an encryption scheme identifier that identifies an encryption scheme used by the UE to encrypt the subscription identifier in the SUCI” (as recited in limitation 1d of claim 1 and identically in claims 9, 10, and 15). We address that argument below, in Sections II.D.3.c.ii and iii of this Decision. With that exception, we do not discern that any claim terms require construction at this point in the proceeding for the purpose of institution. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (only those terms that are in controversy need be construed, and only to the extent necessary to resolve the controversy) (citing Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)).” slip op. at 10

    • Novelty / Anticipation (§102) › Priority / effective filing date / continuation supportReference is prior artDecided for petitioner

      “i. Nair Provisional’s Support for a Claim in Nair Patent Owner argues that the Petition is deficient because it does not show that the disclosure in the Nair Provisional supports at least one claim in Nair, even though Nair is subject to the AIA and Patent Owner concedes that the Board’s precedential opinion in Penumbra concludes we do not need to make such a determination regarding support for at least one claim to reach a prior art determination under the AIA. Prelim. Resp. 23–24 n.6; Penumbra, 2023) (precedential). Following that precedent, we decline to require a showing of support in the Nair Provisional for at least one claim in Nair and instead only require that the ministerial requirements for claiming priority were met. See Penumbra, Paper 34 at 32–33. Petitioner argues that the “ministerial requirements” described in Penumbra have been met. Pet. 4–5 (noting that Nair contains a priority claim to the Nair Provisional, was filed within 12 months of the Nair Provisional, and includes a common inventor). Patent Owner does not contest that these requirements have been met, and upon our examination, we agree that they appear to have been met. Ex. 1004, codes (22), (60), (72); Ex. 1008, 1, 4, 38. Thus, on the present record and for the purposes of institution, the disclosures of Nair are prior art, to the extent that the relied-upon disclosures are included in the Nair Provisional. ii. Nair Provisional’s Date for Cited Portions of Nair Patent Owner also argues that the Petition relies on material in Nair that was added after the filing of the Nair Provisional, and that this material cannot be properly relied on as prior art. Prelim. Resp. 19–23. We address these specific arguments regarding material Petitioner references from Nair (and the Nair Provisional) below, in our analysis with respect to the respective limitations of claim 1 these citations relate to.” slip op. at 15

    Claim construction§ 102 anticipation§ 103 obviousnesscites KSR · Graham
    Patents in suitUS 10,425,817
  • PTAB · Apr 25, 2024 · IPR2024-00024 · APJ Nathan A Engels · IPR · Institution

    The Board instituted IPR on claims 1–4, finding a reasonable likelihood that claim 1 would be unpatentable over Harada and Gutberlet.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “Institution of an inter partes review is authorized by statute when “the information presented in the petition . . . and any response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a); see 37 C.F.R. § 42.108. Upon consideration of the evidence currently of record, we conclude that the information presented shows that there is a reasonable likelihood that Petitioner would prevail in establishing the unpatentability of at least one challenged claim of the ’167 patent.” slip op. at 2

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundInstituted

      “Reasons to Combine Petitioner argues a person of ordinary skill would have been motivated to combine the teachings of Harada and Gutberlet for several reasons, in addition to the reasons discussed above with the claim limitations. Pet. 24–29. Among other things, Petitioner contends Harada and Gutberlet share a similar purpose and architecture, “both teach behavioral synthesis of C code to RTL; both simulate RTL; and both report latency metrics for each behavioral block.” Pet. 24 (citing Ex. 1004 ¶¶ 1–2, 72–73, 98, Figs. 16, 17; Ex. 1005, 1:10–27, 2:11–19, 7:3–6, 34:13–20, Table 38). Further, Petitioner contends combining the references’ teachings would have amounted to combining prior art elements according to known methods to yield predictable results, with Harada teaching “a process including steps for synthesizing behavioral code into RTL; performing RTL logic simulation; and analyzing the results, along with a table showing correspondence between RTL and behavioral code, to calculate latency for each behavioral block,” and Gutberlet teaching “using logic simulation to calculate latency for each behavioral block, measured in clock cycles/ns, and reported in a table.” Pet. 24–25 (citing Ex. 1004 ¶¶ 98, 117, 118, 132–134; Ex. 1005, 2:11–19, Table 38). Patent Owner argues a person of ordinary skill in the art would not have combined Harada and Gutberlet as suggested in the Petition because, according to Patent Owner, among other things, “Harada does not disclose using RTL in the context of its disclosure” and “Gutberlet discloses loop handling techniques on behavioral code, and any performance assessment occurs prior to generating RTL.” Prelim. Resp. 40. Further, Patent Owner argues Gutberlet explicitly teaches away from generating RTL code, analyzing the latency, and re-editing the source code if there is a latency issue and “[t]herefore, a [person of ordinary skill in the art] would not combine Gutberlet with any reference to satisfy the latency analysis elements of the ’167 claims. Prelim. Resp. 41 (citing Ex. 1005, 2:11–19). We again note that Patent Owner’s arguments are not currently supported by declaration testimony and amount to attorney argument at this stage in the proceeding. Petitioner’s arguments, on the other hand, are supported by the testimony of Dr. Lin in addition to the cited portions of the references, and we thus preliminarily find Petitioner has adequately articulated reasons for combining the references for the purposes of institution.” slip op. at 15

    • Novelty / Anticipation (§102) › Prior-art status of a reference › Printed publication / public accessibilityOther

      “Shin’s Status as Prior Art The parties dispute whether Shin qualifies as a publicly accessible publication. According to Petitioner, prior to the critical date, Shin was published on the Internet by professors at the University of California at Irvine on both the University’s website and on the professors’ webpages. Pet. 17; Prelim. Reply 1–3. According to Petitioner, the authors were prominent and well-known in the industry, Shin was the very first publication listed on the relevant page of the University’s website in 2003, and Shin was one of only 44 papers on that page. Prelim. Reply 1–3. Patent Owner argues that Shin was not indexed or searchable in a meaningful way and that there is insufficient evidence that an interested person of ordinary skill exercising reasonable diligence would have located Shin. Prelim. Resp. 17–18, 21; Prelim. Sur-Reply 1–3. Patent Owner further argues the facts of Shin’s alleged availability are similar to the facts of Acceleration Bay, LLC v. Activision Blizzard Inc., 908 F.3d 765, 772-74 (Fed. Cir. 2018). Prelim. Resp. 19–21; Prelim. Sur-Reply 1–3. At this preliminary stage, we question whether Petitioner has sufficiently shown that Shin qualifies as a publicly available publication.” slip op. at 17

    • Skill levelSkill level petitioner adoptedOther

      “Level of Ordinary Skill in the Art Petitioner asserts that a person of ordinary skill in the art “would have had a bachelor’s degree in electrical engineering or a similar field with at least two years of experience in the field; or a master’s degree with specialization in the field,” and “[a] person with less education but more relevant practical experience may also meet this standard.” Pet. 21 (citing Ex. 1003 ¶¶ 63–64). Petitioner also states that the relevant field is “IC design and manufacturing, including EDA tools and behavioral synthesis.” Pet. 21 (citing Ex. 1001, 1:17–2:37; Ex. 1003 ¶ 62). At this stage, Patent Owner does not address the level of ordinary skill. For the purposes of this Decision, we apply Petitioner’s articulation of the level of ordinary skill, which is supported by the testimony of Dr. Lin and is consistent with the level reflected by the ’167 patent and the asserted prior art.” slip op. at 6

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 7,971,167
  • PTAB · Feb 21, 2024 · IPR2023-01287 · APJ Michael R Zecher · IPR · Institution

    The Board instituted IPR on claims 1–30 and all asserted grounds, finding a reasonable likelihood of success on at least one claim based on the obviousness challenges.

    RulingsInstitution decision
    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed board ownDecided for petitioner

      “restriction region” should not be limited to an “exclusionary zone” or “an area where the vehicle is excluded from entry,” as asserted by SZ DJI. See Prelim. Resp. 9; Prelim. Sur-reply 2. Upon reviewing the specification of the ’121 patent, it states the following: “[i]n some embodiments, a flight response measure may include allowing the UAV to remain in the flight restriction region, but imposing certain restrictions on the operation of the UAV within the flight restriction region. The UAV may be forced to remain within the flight restriction region.” Ex. 1001, 17:44–49. Construing the claim term “restriction region” in accordance with SZ DJI’s proposed construction as an “exclusionary zone” would exclude these embodiments, which allow the UAV to remain in the flight restriction region, or force the UAV to remain within the flight restriction region. See, e.g., Vitronics Corp. v. Conceptronic, Inc., 90 F.3d 1576, 1583 (Fed. Cir. 1996) (Although a preferred embodiment should not be read into claims as limitations, construction of a claim term that excludes a preferred embodiment “is rarely, if ever, correct and would require highly persuasive evidentiary support.”). In light of these embodiments, which do not comport with SZ DJI’s proposed construction, and lacking persuasive evidentiary support from the specification to support its narrow construction, the proper construction of the claim term “restricted region” is broader than SZ DJI would allow. At this stage of the proceeding, lacking a clear construction for the claim term “restriction region” in the Petition itself, we decline to adopt Textron’s implied construction for this claim term presented for the first time in the Preliminary Reply. See Prelim. Reply 1. Instead, for the purposes of institution, we preliminary construe the claim term “restricted region” in accordance with its plain and ordinary meaning as “any region in which it is possible to limit or affect operation of a ground vehicle.”3 Our preliminary construction finds support in various embodiments disclosed the specification, which include both confinement and exclusion. See, e.g., Ex. 1001, 17:48–49 (“The UAV may be forced to remain within the flight restriction region.”), 22:46–48 (“For instance, if the user is approaching a flight restriction region, the user may be alerted and may change course of the UAV to exit the flight restriction region.”). During trial, if the construction of the claim term “restriction region” remains in dispute, we invite the parties to provide arguments and evidence regarding the plain and ordinary meaning of this claim term. slip op. at 11

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “III. CONCLUSION We conclude that the information presented in the Petition demonstrates that there is a reasonable likelihood that Textron would prevail in challenging at least one of claims 1–30 of the ’121 patent as unpatentable. Accordingly, we institute an IPR as to all challenged claims and all the grounds raised in the Petition. See 37 C.F.R. § 42.108(a). At this stage of the proceeding, we have not made a final determination with respect to the patentability of the challenged claims or the construction of any claim term. IV. ORDER Accordingly, it is ORDERED that, pursuant to 35 U.S.C. § 314 and 37 C.F.R. § 42.4(a), an IPR is hereby instituted as to all of the challenged claims and all of the grounds raised in the Petition; and” slip op. at 54

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “Based on our initial review of Humphries, we are persuaded by SZ DJI’s argument that the reference does not disclose, either expressly or inherently, “private property,” such as residential and commercial buildings. See Ex. 1004. It is well settled that a prior art reference may anticipate when the claim limitations not expressly found in that reference are nonetheless inherent in it, for example, if the prior art necessarily functions in accordance with, or includes, the claimed limitations. In re Cruciferous Sprout Litig., 301 F.3d 1343, 1349 (Fed. Cir. 2002). However, the fact that a certain thing may result from a given set of circumstances is not sufficient for inherent anticipation. In re Robertson, 169 F.3d 743, 745 (Fed. Cir. 1999). Figure 2 of Humphries does not meet the exacting standard of anticipation because there is nothing within the four corners of this reference indicating that the geofence objects 220 actually encompass the city of Clinton, Mississippi, much less that such a location would be associated with private property, such as residential or commercial buildings. Notwithstanding, we believe that Humphries, together with the general background knowledge of a person of ordinary skill in the art, teaches that the geofence annotated in Textron’s version of Figure 2 would encompass a real-world location, such as the city of Clinton, Mississippi, which at the very least includes “a location associated with a private property.” We address this below when addressing the asserted ground based on obviousness over Humphries. See infra Section II.C.2.” slip op. at 25

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundReasonable expectation foundInstituted

      “Based on the preliminary record, the purported deficiencies identified by SZ DJI do not undermine Textron’s asserted obviousness ground based on the combined teachings of Humphries and Marcus. For example, it is not dispositive that both Humphries and Marcus relate to systems applicable to airborne vehicles, whereas the challenged claims require a ground vehicle, because Humphries explicitly contemplates that its system also is applicable to a ground vehicle. Ex. 1004, 4:26–31 (disclosing that tracked device 120 may be “associated with a vehicle such an automobile, truck or the like”), 5:44–46 (“The object being tracked as described in the present invention is a vehicle (e.g., cars, boats, trucks, trains).”). Moreover, as we explain in our preliminary claim construction analysis above, we decline to adopt SZ DJI’s narrow view of the claim term “restriction region” as limited to exclusion. Instead, we preliminary construe the claim term “restricted region” in accordance with its plain and ordinary meaning as “any region in which it is possible to limit or affect operation of a ground vehicle.” See supra Section II.A. Lastly, even if the user and roles in Humphries and Marcus are different or there are certain disclosures in Marcus that might create tension with its proposed combination with Humphries, this would not undermine Textron’s rationale to combine the teaching of these two reference. Textron does not seek to bodily incorporate all of Marcus into Humphries, but instead only relies on Marcus to teach specifying a location associated with private property. See Pet. 47–48 (citing Ex. 1005 ¶¶ 14, 17). In summary, Textron has shown a reasonable likelihood that it would” slip op. at 38

    Claim construction§ 102 anticipation§ 103 obviousnesscites KSR · Graham
    Patents in suitUS 11,482,121
  • PTAB · Jan 23, 2024 · IPR2023-01198 · APJ John R Kenny · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–17 were unpatentable over the asserted Takashi, Onishi, and Kim grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “information presented in the Petition shows “there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2018). For the reasons set forth below, upon considering the Petition, the Preliminary Response, and the evidence of record, we determine the information presented in the Petition does not establish a reasonable likelihood that Petitioner would prevail with respect to at least one of the challenged claims. Accordingly, we do not institute inter partes review. A. Related Matters The parties identify the following related district court litigation” slip op. at 2

    • Skill levelSkill level petitioner adoptedOther

      “degree in electrical engineering, computer engineering, or equivalent training or job experience, along with 1–2 years of experience in any of the fields of power electronics, motor control systems, and battery systems for electric motor applications. Pet. 8. Further, Petitioner asserts that additional education could compensate for less practical experience and vice versa. Id. Patent Owner has not challenged Petitioner’s definition for an ordinarily skilled artisan. See generally Prelim. Resp. At this stage, Petitioner’s 2 JP 1994253415 A (Ex. 1005). Certified Translation of which is Ex. 1004. All cites to Takashi are to its certified translation (Ex. 1004) unless otherwise noted. 3 JP201193653A (Ex. 1007). Certified Translation of which is Ex. 1006. All cites to Onishi are to its certified translation (Ex. 1006) unless otherwise noted. 4 US 8,330,419 B2 (Ex. 1008). definition appears consistent with the level of skill reflected in the Specification and in the asserted prior art references. Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001). Thus, for purposes of this Decision, we adopt Petitioner’s definition.” slip op. at 6

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “B. Claim Construction The Petition and the Preliminary Response do not request that we expressly construe any claim term. Pet. 15; Prelim. Resp. 5–6. Further, on this record, we determine that no claim term requires an express construction for the purpose of determining whether to institute inter partes review. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“[W]e need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng'g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))).” slip op. at 7

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “As mentioned, Petitioner argues that Takashi’s use of duty setting means to read pre-calculated command duties stored in memory discloses “calculating a compensation amount.” Pet. 19. Petitioner, however, does not explain why reading pre-calculated command duties stored in memory constitutes calculating command duties based on a present electrical parameter. Id. at 19–21. Dr. Zane similarly does not provide such an explanation. Ex. 1004 ¶¶ 64–69. The term “pre-calculated,” given its ordinary usage, indicates that the duty cycles have been calculated before they have been read from memory, which means they are not calculated based on a present electrical parameter. Thus, Petitioner has not sufficiently shown that reading pre-calculated command duties stored in memory constitutes calculating command duties based on a present electrical parameter.” slip op. at 10

    Claim construction§ 102 anticipation§ 103 obviousness
    Patents in suitUS 10,640,224
  • PTAB · Jan 23, 2024 · IPR2023-01217 · APJ John R Kenny · IPR · Institution

    The Board instituted IPR on all asserted grounds challenging claims 1–23, finding a reasonable likelihood of proving at least one challenged claim unpatentable.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “The Petition, to justify institution of review, must demonstrate a reasonable likelihood that Petitioner would prevail with respect to at least one challenged claim. See 35 U.S.C. § 314(a). After considering the Petition, the Preliminary Response, the Preliminary Reply, the Preliminary Sur-reply, and the evidence of record, we determine that the Petition has met this standard and institute inter partes review.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “degree in electrical engineering, computer engineering, or equivalent training or job experience, along with 1–2 years of experience in the field of GPS, location-based-services, and/or geofencing. Pet. 11. Further, Petitioner asserts that additional education could compensate for less practical experience and vice versa. Id. Patent Owner has not challenged Petitioner’s definition for an ordinarily skilled artisan. See generally Prelim. Resp. At this stage, Petitioner’s definition appears consistent with the level of skill reflected in the Specification and in the asserted prior art references. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001). Thus, for purposes of this Decision, we adopt Petitioner’s definition.” slip op. at 7

    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed board ownDecided for petitioner

      “On this preliminary record, we determine that the term “vehicle restriction region” is not limited to regions that have an area where a vehicle is excluded from entry or warned upon transgression. The dispute between the parties regarding “vehicle restriction region” specifically concerns the meaning of the word “restriction,” in particular whether “restriction” requires the exclusion of vehicles from entry or a warning upon transgression. Pet. 18–37; Prelim. Resp. 5–24. The parties are not disputing whether the asserted prior art discloses vehicles or regions. Pet. 18–37; Prelim. Resp. 5– 24. The Specification teaches that the term “restriction” is not so limited. For example, the Specification discloses that the term “flight restriction zone” “may refer to any region in which it is possible to limit or affect operation of an aerial vehicle.” Ex. 1001, 4:8–11 (emphasis added). This disclosure does not require the exclusion of entry of an aerial vehicle or a warning upon transgression. Further, the Specification teaches that flight restriction strip 2104 in region 2100 in Figure 21 may permit flight of the UAV while other flight restriction strips may prevent flight of the UAV. Id. at 29:20–22. This disclosure further does not require the exclusion of entry of a vehicle or a warning upon transgression. To the contrary, the Specification describes the latter (an alert) as an optional addition, and, as described above, flight restriction strip 2104 can expressly permit flights. Id. at 29:26–31. In light of the Specification’s definition of a “flight restriction zone” as “any region in which it is possible to limit or affect operation of an aerial vehicle,” it would appear that the proper construction of “vehicle restriction zone” is “any region in which it is possible to limit or affect operation of a vehicle.” Ex. 1001, 4:8–11.” slip op. at 8

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Instituted

      “We determine that Petitioner has made a sufficient showing for the preamble of claim 1. First, on this preliminary record, we agree with Petitioner that Humphries’s geofenced area constitutes a vehicle restriction region because it is a region in which it is possible to limit or affect operation of a vehicle. Pet. 19. Humphries describes the geofenced regions as areas in which tracked objects are to be confined. Ex. 1004, 1:44–50.” slip op. at 11

    Claim construction§ 102 anticipation§ 103 obviousness
    Patents in suitUS 11,462,116
  • PTAB · Oct 26, 2023 · IPR2022-00730 · APJ Iftikhar Ahmed · IPR · Final written decision

    Claims 22, 23, 30, 32, and 33 were not shown unpatentable because Pakzad did not disclose the claimed combined macro and femto timing information, and the obviousness grounds did not address that limitation.

    RulingsFinal written decision
    • Expert testimonyPatent owner expert creditedPetitioner expert discountedDecided for patent owner

      “information from all three types of sources together or at the same time. Patent Owner argues that “a [person of ordinary skill in the art] would understand that this passage in Pakzad ‘any one of several sources’ confirms that Pakzad only uses a single signal source at a time.” PO Resp. 34 (citing Ex. 2002 ¶ 69). Dr. Chrissan testifies that he understands this disclosure to mean that “Pakzad teaches a single signal source at a time, not more than one.” Ex. 2002 ¶ 70 (emphasis added). We find Patent Owner’s interpretation, supported by Dr. Chrissan’s testimony, to be a reasonable reading of Pakzad’s disclosure. Dr. Chrissan further testifies that “Pakzad’s invention is about using both a course [sic] routing graph and fine routing graph to make computation of a motion model (e.g., a particle filter) more efficient,” and “Pakzad was not directed to leveraging a heterogenous network by incorporating both macro and femto cells concurrently.” Id. ¶ 68. We agree with Dr. Chrissan’s explanation for the lack of clear disclosure in Pakzad about which measurements Pakzad uses with its particle filter.” slip op. at 25

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “understanding of a person of ordinary skill in the art at the time of the invention. Graham, 383 U.S. at 17. Petitioner contends that a person of ordinary skill in the art “would have been someone with at least (1) a bachelor’s degree in electrical engineering, computer engineering/science, or a related scientific field, and (2) either (a) a master’s degree in electrical engineering, computer engineering/science, or a related filed, or (b) two or more years of work or research experience in wireless networking and/or computing.” Pet. 21 (citing Ex. 1009 ¶ 23). Patent Owner does not dispute Petitioner’s definition for a person of ordinary skill in the art, but adds that the person of ordinary skill in the art “may alternatively have additional years of practical and relevant work or research experience as substitution for less or different technical education, and vice versa.” See PO Resp. 17. We determine that the level of ordinary skill proposed by Petitioner is consistent with the ’819 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). We adopt Petitioner’s proposed level in deciding the patentability of the challenged claims.” slip op. at 9

    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed patent owner constructionDecided for patent owner

      “claim 30 should be construed “to refer to the previously recited ‘femto base station timing information,’ ‘macro base station timing information,’ and ‘femto base station position information.’” PO Resp. 18. Patent Owner argues that its proposed construction is “based on at least three aspects of the intrinsic record: (1) the claim language itself; (2) guidance from the specification defining the disputed term; and (3) illustrative embodiments confirming the meaning of the disputed term.” Id. (citing Ex. 2002 ¶ 47). Specifically, Patent Owner contends that “the specification describes two embodiments that further confirm to a [person of ordinary skill in the art] that ‘the base station information’ consists of the [three types of information previously] recited.” Id. at 19–23 (citing Ex. 1001, 19:29–33, 20:50–54, Figs. 8, 9; Ex. 2002 ¶¶ 47–55).” slip op. at 10

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “More importantly, anticipation requires that the four corners of a single, prior art document describe every element of the claimed invention, and we are not persuaded that Pakzad describes the combinational use of the two different types of timing information as claimed. See Xerox Corp. v. 3Com Corp., 458 F.3d 1310, 1322 (Fed. Cir. 2006) (citing Advanced Display Sys., Inc. v. Kent State Univ., 212 F.3d 1272, 1282 (Fed. Cir. 2000)). The Federal Circuit has made it clear that “it is not enough that the prior art reference discloses part of the claimed invention, which an ordinary artisan might supplement to make the whole, or that it includes multiple, distinct teachings that the artisan might somehow combine to achieve the claimed invention.” Net MoneyIN, 545 F.3d at 1371 (citation omitted) (emphasis added). In Net MoneyIN, although a prior art reference described two protocols, which when taken together, disclosed “all five links arranged or combined in the same way as claimed,” the Federal Circuit determined that the reference did not anticipate the claim. See id. Rather, the Federal” slip op. at 28

    Patent outcomesUS 8,958,819 not shown unpatentable
    Claim construction§ 102 anticipation§ 103 obviousnesscites Enfish · Phillips · KSR · Graham
    Patents in suitUS 8,958,819
Page 1 of 4
← Previous1234Next →

Holdings, summaries, rulings, issues, outcomes, winners and claim constructions shown for a decision were generated by a large language model reading the opinion. They are a guide to the decision, not the decision. Confirm every one against the court's own text before relying on it. Outcomes read from the patent owner’s side. Party names are extracted from the decision and are missing on about 900 short Director denials and scans, which carry the trial number instead.