  • PTAB · Feb 11, 2026 · IPR2024-01221 · APJ Iftikhar Ahmed · IPR · Final written decision

    Petitioner failed to prove claims 1, 2, 4, 5, 7, 8, 12, 13, 17, 19–21, 23, 24, 26, 27, 29, 30, 34, 39–41, and 43 unpatentable because the cited grounds did not establish the required …

    RulingsFinal written decision
    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed patent owner constructionDecided for patent owner

      “image capture device” refers to an imaging-based barcode reader and not a laser-based barcode scanner because we are persuaded that claim language and Specification support that interpretation and also because Patent Owner persuasively shows that a person of ordinary skill in the art would have understood the term as such. Claim 1 recites an “image capture device configured to capture an image.” Ex. 1001, 16:24–25. The plain meaning of the claim term requires that the image be captured, not just scanned. The claim further requires “generating an output based on the information embedded in the image,” requiring that information is retrieved from the captured image. Id. at 16:32–33. A device that does not capture an image is not an “image capture device” under the plain language of the claim. A laser-based barcode scanner employs light reflected from a laser beam to “generate an electrical signal that corresponds to the bars and spaces in the barcode being scanned.” See Ex. 2029 ¶¶ 42–43 (explaining in detail how laser-based barcode self-emitting a laser light across a code to be scanned, with a sensor tuned to capture the reflected light from the laser.”). It simply does not capture an image. slip op. at 14

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Based on our review of the complete record, we determine that Petitioner’s stated level of ordinary skill in the art is reasonable because it is consistent with the evidence of record, including the asserted prior art. The field of the ’167 patent “relates generally to secure transactions, and more specifically, to methods and devices for providing secure identification, verification, and authorization using a portable secure device.” Ex. 1001, 1:8–11. The ’167 patent seeks “to provide methods and devices that are capable of providing secure transactions in a more efficient manner.” Id. at 3:11–13. Accordingly, we adopt Petitioner’s definition. We note, however, that our patentability analysis would be the same under Patent Owner’s definition.” slip op. at 11

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “We agree with Patent Owner that Wang fails to disclose limitation 1[a]. Wang discloses a portable electronic authorization device (PEAD) that can be used as a self-checkout terminal. Ex. 1004 ¶ 115. In this context, Wang discloses By entering the UPC code or barcode using keypad on the PEAD or scanning in the UPC code or barcode using the input device built into the PEAD such as a barcode scanner or OCR reader, the PEAD can generate the receipt with the list of item prices through the wireless network and Internet by querying the item price using the barcode as the index for price lookup table which is Stored in a Server System. Id. (emphasis added). As discussed above (Section III.C.1), we are persuaded by Patent Owner’s arguments that the claimed “image capture device” refers to an imaging-based device and not a laser-based barcode scanner. Petitioner does not contend that Wang’s disclosure of the barcode scanner necessarily refers to an imaging-based device, but argues that Wang’s disclosure is sufficient because “both imaging-based barcode scanners and laser-based barcode scanners constitute image capture devices.” Reply 11. In light of our claim construction above, we disagree.” slip op. at 27

    • Obviousness (§103) › Graham factors (scope of art, differences, level of skill)Not shown unpatentableNot shown unpatentable

      “Petitioner contends that claims 1, 4, 5, 7, 12, 17, 23, 26, 27, 29, 34, and 43 are unpatentable as obvious over the combination of Wang and Drummond. Pet. 30–43. 1. Drummond Drummond is a patent titled “Automated Banking Machine System and Method,” and “relates to an automated banking machine apparatus and system that are capable of use in a wide area network, and which provides a user with a remote electronic receipt or other record related to a transaction performed at the machine.” Ex. 1008, code (54), ¶ 2. Drummond discloses that its automated banking machine, may “initiate the sending of a non-paper transaction receipt to the customer,” “[t]he receipt may be sent using a wide area network, such as the Internet,” and “[t]he receipt may be an electronic receipt, for example a receipt in the form of an e-mail message.” Id. ¶ 247. 2. Claims 1, 4, 5, 7, 12, 17, 23, 26, 27, 29, 34, and 43 For this obviousness ground, Petitioner relies on the same arguments and evidence as its Ground 1a (anticipation by Wang), discussed above, for the majority of claim limitations. See Pet. 33–43. Importantly, Petitioner relies solely on Wang as teaching independent claim limitations [1a], [23a], and [43b] relating to an image capture device and embedded information. Pet. 36, 41, 43. Accordingly, for the reasons discussed above with respect to Ground 1a, Petitioner has not established by a preponderance of the evidence, that the subject matter of claims 1, 4, 5, 7, 12, 17, 23, 26, 27, 29, 34, and 43 would have been obvious to one of ordinary skill in the art over the combination of Wang and Drummond.” slip op. at 31

    Patent outcomesUS 7,314,167 not shown unpatentable
    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 7,314,167
  • PTAB · Dec 23, 2025 · IPR2024-01030 · APJ Richard H Marschall · IPR · Final written decision

    Claims 1–20, 22–31, and 33–37 are unpatentable; claims 21 and 32 were not shown unpatentable, principally because the proposed combinations failed to establish motivation to combine or the required airtight seal.

    RulingsFinal written decision
    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “We find that the proposals from the parties substantially overlap, such that it remains unclear whether any substantive difference exists. Notably, neither party argues that the minor differences in the proposals lead to a different outcome on any issues in this proceeding. Based on our review of the proposals, we apply Patent Owner’s proposal because it is consistent with the problems and solutions disclosed in the ’483 patent and prior art of record. See, e.g., GPAC, 57 F.3d at 1579 (approving the determination of the level of ordinary skill in the art by appeal to the references of record). The outcome of the issues addressed in this Decision would not change if we applied Petitioner’s proposal.” slip op. at 9

    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed patent owner constructionDecided for patent owner

      “hermetically sealed” module does not encompass waterproof modules that are not airtight. First, as Petitioner admits, as a general matter, “[s]omething that is hermetically sealed is sealed so as to be airtight.” Pet. 28 (citing Ex. 1002 ¶ 103; Ex. 1010, 269); PO Sur-reply 16. Petitioner later tries to argue that the specification puts a different spin on this meaning, but still acknowledges that “[o]utside the context of the ’483 patent, a hermetic seal is sometimes equated with an airtight seal.” See Pet. Post-hearing 2–3 (citing Ex. 1002 ¶ 103; Ex. 1010, 269). Based on our review of the record, the “ordinary meaning” of “hermetically sealed” means “airtight,” and, as noted above, “airtight” is not the same thing as “waterproof.” Second, the claims support Patent Owner’s position by including dependent claims that separately claim a “hermetically sealed” module (claims 13 and 32) and a “waterproof” module (claims 15 and 34), strongly suggesting that the terms have a different scope to avoid rendering some claims redundant. See Ex. 1001, 11: 65–66, 12:3–4, 12:52–53, 12:55–56. Petitioner argues in its Post-hearing brief that claims requiring waterproof modules are “a narrower species” of hermetic seal, but fails to explain how hermetic, airtight, and waterproof seals would not fall within the scope of both claims using its approach. Pet. Post-hearing Reply 2. Petitioner’s earlier argument in its Reply also seems to cut against this position by asserting that the specification “treats hermitically sealing as conventional and equivalent to waterproofing,” with different dependent claims directed to two allegedly “equivalent” terms making little sense. Pet. Reply 14 (emphasis added). The most natural reading of the claim language suggests that “hermetically sealed” means airtight, and does not encompass modules that are waterproof but not airtight. Third, while the specification does not define “hermetically sealed” and uses “waterproof” and “hermetically sealed” in similar contexts, it does not suggest that “hermetically sealed” does not require an airtight seal consistent with its ordinary meaning. See Pet. Reply 14–15 (citing Ex. 1001, 6:47–53, 9:15–18, 10:47–50). Instead, the specification states that hermetic seals prevent water from contacting electronics, which remains consistent with Patent Owner’s position because airtight hermetic seals are also waterproof. See Ex. 1001, 6:47–53, 9:15–18. The specification also states that “[t]he module preferably houses any of the aforementioned electrical components in a substantially water-proof and wear resistant/moisture resistant environment and is preferably hermetically sealed.” Id. at 10:47–50 (emphasis added). This passage supports Patent Owner’s position by suggesting that the preferable “hermetically sealed” module goes beyond mere water resistance. See PO Sur-reply 16–17. slip op. at 16

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)UnpatentableUnpatentable

      “2. Petitioner’s Anticipation Arguments and Evidence Petitioner argues that Howell-596 discloses every limitation of claims 1, 9, 10, 14, 15, and 18, and points to specific portions of Howell-596 and expert testimony to support its arguments. See Pet. 10–20 (citing Ex. 1002; Ex. 1003). We have reviewed the evidence and arguments of record and find that Petitioner has shown, by a preponderance of the evidence, that the limitations in claims 1, 9, 10, 14, 15, and 18 are disclosed by Howell-596 for the reasons set forth in the Petition, which we adopt as our own. See id.11 Accordingly, we find that Petitioner has established, by a preponderance of the evidence, that Howell-596 anticipates claims 1, 9, 10, 14, 15, and 18.” slip op. at 12

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation not foundNot shown unpatentableNot shown unpatentable

      “Based on these undisputed points and the parties’ arguments, we agree with Patent Owner that Petitioner fails to establish that a POSITA would have been motivated to locate Howell-596’s module housing 1700, which contains its UV detection system 1500, behind a user’s ear. Petitioner never squarely addresses the fact that placing Howell-596’s UV detection system behind a user’s ear would negatively impact its performance. Pet. 31–33; Pet. Reply 17–22. As a result, even if we accept Petitioner’s arguments and evidence as to the various advantages when placing electronics behind a user’s ear, it fails to establish a motivation to combine that requires placing Howell-596’s module housing 1700, and therefore its UV detection system, behind a user’s ear. Petitioner never acknowledges the readily apparent disadvantages of placing a UV detection system behind the ear, where it may not work at all. See Pet. 31–33. Nor does Petitioner argue that, in its combination, adjustments would be made to ensure accurate operation of Howell-596’s UV detection system. See id. Similarly, Petitioner notes that both Howell-596 and Howell-833 disclose UV sensors behind the ear of a user, but those teachings do not establish that placing Howell-596’s module behind the ear would ensure proper operation of its UV detection system housed within that module. See Pet. Reply 17–22. Instead, even though Howell-596 discloses a sensor behind the ear of a user, it maintains the UV detection system in a module toward the front of the temple, away from the ear. See id. at 18–19; PO Surreply 21–22; Ex. 1003 ¶ 205 (describing UV detection system 2102), Fig. 21 (showing UV detection system 2102 toward the front of the temple). Moreover, Petitioner’s reliance on the sensor placed behind the ear of the user in Howell-596 lacks weight because that sensor merely indicates that the device “is being worn by a user,” which serves a very different purpose than Howell-596’s UV detection system, which seeks to monitor a user’s exposure to UV radiation, a central purpose of Howell-596’s eyewear. See Ex. 1003 ¶ 205, code (57). Howell-833 also employs a UV sensor behind the ear, but Petitioner does not establish that it operates any differently than the “being worn” sensor in Howell-596, and therefore does not establish that Howell-596’s UV detection system would still work for its intended purposes in Petitioner’s proposed combination. See Pet. Reply 19–20.” slip op. at 29

    Patent outcomesUS 8,708,483 mixed
    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR
    Patents in suitUS 8,708,483
  • PTAB · Nov 14, 2025 · IPR2025-00907 · APJ Justin T Arbes · IPR · Institution

    The Board instituted IPR on claims 1–20 and all asserted grounds after finding a reasonable likelihood that claim 1 is unpatentable over the three 3GPP references.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “inter partes review unless the information in the petition and preliminary response “shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” See 37 C.F.R. § 42.4(a) (“The Board institutes the trial on behalf of the Director.”). For the reasons that follow, we institute an inter partes review as to claims 1–20 of the ’944 patent on all grounds of unpatentability asserted in the Petition.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “B. Level of Ordinary Skill in the Art Petitioner argues that at the time of the ’944 patent (November 2019),2 a person of ordinary skill in the art would have had “a bachelor’s degree in electrical engineering, computer engineering, computer science, or a similar field, along with two years of experience designing or developing wireless networks, including long-term evolution LTE/4G or 5G new radio (NR) cellular technology,” where “[a]dditional years of experience could substitute for an advanced-level degree (and vice versa).” Pet. 10 (citing Ex. 1003 ¶¶ 39–44). Patent Owner “utilizes Petitioner’s proposed level of skill in the art” for its Preliminary Response. Prelim. Resp. 8. Based on the record presented, including our review of the ’944 patent and the types of problems and solutions described in the ’944 patent and cited prior art, we agree with Petitioner’s proposed definition of the level of ordinary skill in the art and apply it for purposes of this Decision.” slip op. at 10

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “C. Claim Interpretation We interpret each challenged claim using the same claim construction standard that would be used to construe the claim in a civil action under 35 U.S.C. 282(b), including construing the claim in accordance with the ordinary and customary meaning of such claim as understood by one of ordinary skill in the art and the prosecution history pertaining to the patent. 37 C.F.R. § 42.100(b). Petitioner argues that “no claim terms need be construed.” Pet. 8. Patent Owner does not propose interpretations of any claim terms in its Preliminary Response. We conclude that no express interpretation of any claim term is necessary to determine whether to institute an inter partes review in this proceeding, but encourage the parties to address various claim interpretation issues identified below during trial. See infra Section II.D.5; Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“Because we need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy,’ we need not construe [a particular claim limitation] where the construction is not ‘material to the . . . dispute.’” (emphasis added) (citation omitted)).” slip op. at 11

    • Novelty / Anticipation (§102) › Prior-art status of a reference › Printed publication / public accessibilityPrinted publication establishedInstituted

      “Patent Owner responds that Petitioner fails to show that the 3GPP-38.213-CR “document sent to [the] 3GPP email list on November 3 was available to non-3GPP members by November 5, 2019” (the alleged critical date for the ’944 patent). Prelim. Resp. 3 (emphasis omitted); see Pet. 10. According to Patent Owner, the listserv archive of emails cited by Mr. Rodermund “only shows that the November 3, 2019 email is available now—not that it was uploaded within a day of when the original email was sent”—and Mr. Rodermund provides only his uncorroborated opinion that uploads were “automatic” and “immediate.” Prelim. Resp. 5–6 (citing Ex. 1008 ¶¶ 43–63, 72–80). Patent Owner also contends that the November 2, 2019, metadata only relates to creation of 3GPP-38.213-CR and does not support Petitioner’s contention that the email was immediately uploaded. Id. at 6. Finally, Patent Owner argues that whether the subject matter of 3GPP-38.213-CR was discussed at the 3GPP meeting in October 2019 is “irrelevant,” given the date of the metadata, and has no bearing on whether the document itself was later publicly accessible. Id. at 6–7. Assessing the evidence of record collectively, however, we are persuaded that Petitioner has shown a reasonable likelihood that 3GPP-38.213-CR was publicly accessible from the ETSI email archive before November 5, 2019. Given his many years of experience with ETSI, in particular his responsibilities pertaining to management of documents like change requests, and as the “list owner” “responsible for managing and administrating” several email exploder lists, Mr. Rodermund appears to be well-qualified to testify to the matters in his declaration. See Ex. 1008 ¶¶ 7, 10–15, 47. He explains in detail how, based on his experience, emails sent” slip op. at 20

    Claim construction§ 102 anticipation§ 103 obviousnesscites KSR · Graham
    Patents in suitUS 11,139,944
  • PTAB · Oct 10, 2025 · IPR2025-00653 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution on all claims because the Petition did not show a reasonable likelihood that any challenged claim was unpatentable over the asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “An inter partes review may be instituted only if “the information presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’504 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 12

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “Additionally, only terms that are in controversy need to be construed, and these need be construed only to the extent necessary to resolve the controversy. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’”) (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)). The parties assert that each claim term should be construed in accordance with its plain and ordinary meaning. Pet. 9; Prelim. Resp. 4 (citing Ex. 2009 ¶ 72); see Ex. 1002 ¶ 22 (opining the same). And, in the respective claim construction sections of their briefs, the parties do not propose any claim terms for express construction. We agree with the parties that no claim terms require express construction to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 13

    • Expert testimonyPetitioner expert discountedDecided for patent owner

      “Ex. 1002 ¶ 47. As reflected above, Dr. Wooley’s testimony as to element [1.2] does not even assert that Cardamone discloses a tank, let alone one or more sensors disposed at a tank as recited in element [1.2]. Thus, Dr. Wooley’s testimony does not support Petitioner’s argument on this issue.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,726,504
  • PTAB · Oct 10, 2025 · IPR2025-00652 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–23 and 25–30 were unpatentable over the asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’403 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 12

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “The parties assert that each claim term should be construed in accordance with its plain and ordinary meaning. Pet. 10; Prelim. Resp. 4 (citing Ex. 2009 ¶ 73); see Ex. 1002 ¶ 22 (opining the same). And, in the respective claim construction sections of their briefs, the parties do not propose any claim terms for express construction. We agree with the parties that no claim terms require express construction to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 13

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “We agree with Patent Owner that the Petition fails to demonstrate that Kahn discloses element [1.2] because the evidence cited does not disclose a “first computer system being configured to provide remote control of the first pump or first valve” (i.e., a fluid-handling device). Kahn is directed to providing access to fluid sensing data and analyzing and providing visual information on that data, but Petitioner has not identified any disclosure of the capability to remotely control fluid-handling devices. See, e.g., Ex. 1005, code (54), 1:27–36, 2:50–3:2. More specifically, Kahn’s disclosures that Petitioner relies on for allegedly teaching remote control are deficient. We discuss each. First, Petitioner points to the following, “[f]or instance, as illustrated in FIG. 1C, a fluid control device such as a valve 15A is located on the input side of a sen[s]or unit 110.” Ex. 1005, 8:19–21, cited in Pet. 13. This portion of Kahn, however, does not disclose remote control. Second, Petitioner cites to the following: Finally, or in addition to, the communication unit 112B can include on-site alerts such as optical (indicator lights), audible alerts (e.g., alarm sounds), tactile (e.g., vibration of the unit) or can be interfaced to an appropriate control valve for simply shutting off the supply of fluid upon the detection of emergency events, for instance. Pet. 13 (citing Ex. 1005, 10:62–67). We agree with Patent Owner that this portion of Kahn teaches on-site alerts and local control of the fluid-handling device. See Prelim. Resp. 7. This portion of Kahn does not disclose remote control.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,294,403
  • PTAB · Oct 10, 2025 · IPR2025-00651 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–3, 6, 7, and 9–20 were unpatentable over any asserted ground.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’680 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 11

    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed patent owner constructionDecided for patent owner

      “target value” is part of a command that is sent from a computing device to a server and then to a controller. The controller then receives a measurement of the fluid by a sensor and determines whether the measurement satisfies the “target value.” If the measurement does not satisfy the “target value,” further operations are undertaken. The recited operation sequence makes clear that the plain and ordinary meaning of “target value” is not as Dr. Wooley opines because the particular operating condition that a device is in at a particular time is represented by the measurement taken by the sensor, 11 Some claim language less relevant to construing “target value” was omitted for ease of reference. which the controller then uses to determine whether the measurement satisfies the “target value.” Additionally, claim 1 recites that the “target value” is sent as part of a command to the controller. The “target value” is not sent to the controller from the sensor, as might be expected if the plain and ordinary meaning of “target value” were as Dr. Wooley opines. Petitioner and Dr. Wooley’s construction would also result in “target value” meaning effectively the same thing as the measurement of the fluid by the sensor, a concept that is separately recited in claim 1 and to which the “target value” is compared. The Specification of the ’680 patent does not support Petitioner’s understanding of the plain and ordinary meaning of “target value.” Although the Specification does not recite “target value,” it recites “target state,” and describes “target state” sufficiently to understand the plain and ordinary meaning of “target” as used in “target value” and “target state.” In particular, the ’680 patent explains that “[i]n some embodiments, the process 104 includes receiving, via a network interface, from a remote user device, (e.g., via a command-center server) a command to change a state of a fluid-handling device to a target state.” Ex. 1001, 11:48–51. This portion reflects that the command is seeking to change a state of a fluid-handling device to a target state. In other words, the “target value” or “target state” is not generally “the particular operating condition that a device is in at a particular time”; rather, it is a value or state that the fluid-handling device is desired to be in, as Patent Owner and Dr. Durham explain. Additionally, just as claim 1 recites a directional component for the “target value” to be sent to the controller in a command, so too does the Specification describe a “target state” as being sent in a command from a remote user device. Thus, the Specification clearly supports the plain and ordinary meaning proposed by Patent Owner and Dr. Durham and not the plain and ordinary meaning proposed by Petitioner and Dr. Wooley. slip op. at 14

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “time-stamped process data, report exception therein to the remote host, and extract and transmit time-stamped process data to the remote host.” Ex. 1005, Abst. (emphases added). Almadi explains that its remote field systems must include a plurality of controller units “to issue commands to, and gather and process data from a plurality of field devices, including remote systems and instruments, . . . [and] a database server for the storage of process data retrieved from the remote subsystems and instruments.” Id. at 2:22–30 (emphases added). Based on these disclosures, we agree with Patent Owner that Petitioner has not established that Almadi discloses element [1.4]. Specifically, the teachings from Almadi identified by Petitioner refer to process data, which is data retrieved from the remote subsystems/field devices. Thus, we understand that Almadi’s teaching—of using an Ethernet switch to transmit “process data”—describes transmitting data from the remote subsystems/field devices. See Ex. 1005, 3:13–17, cited in Pet. 15. But claim 1 and particularly element [1.4], recites “sending, with the server, the target value to the network address [which identifies a controller of the fluid-handling device13] via the network,” which is different than sending process data from the field devices to the remote host or database server for storage.” slip op. at 19

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,175,680
  • Tanklogix, LLC v. SiteproInstitution denied
    PTAB · Oct 10, 2025 · IPR2025-00650 · APJ Sheila F Mcshane · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 18–32 and 34 were unpatentable over Kahn or Kahn and Gutierrez.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “information presented in the petition . . . and any response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). Upon consideration of the Petition, the Preliminary Response, and the evidence of record, we determine that Petitioner has not established a reasonable likelihood of prevailing with respect to the unpatentability of at least one claim of the ’871 patent. Accordingly, for the reasons that follow, we decline to institute an inter partes review of claims 18–32 and 34 of the ’871 patent.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The respective proposed levels of qualifications for a person of ordinary skill in the art are similar, with Patent Owner proposing two years of experience compared to Petitioner proposing significant experience with remotely controlling fluid-handling devices, like SCADA systems. Patent Owner also proposes more extensive experience in lieu of educational experience. While we find Petitioner’s proposed qualifications to be acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of skill necessary to understand and implement the teachings of the ’871 patent and the asserted prior art. Our analysis and findings herein, however, do not turn on any differences in the qualifications adopted.” slip op. at 8

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “We determine that we need not expressly construe any claim terms to resolve the parties’ disputes on the current record. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“[W]e need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))).” slip op. at 10

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “actuators and the remote control of fluid handling devices, including the receipt with the user-interface module of “a user command to actuate an actuator via a presented control interface” (limitation [18.7]) and “account authorized to send commands to remotely control fluid handling devices” (limitation [18.11]). We agree with Patent Owner that the Petition fails to demonstrate that Kahn discloses or teaches these limitations because the evidence does not provide support that there is remote control of fluid handling devices or the use of a user command on a control interface to send a command to a fluid handling device, for instance. Kahn is directed to providing access to fluid sensing data and analyzing and providing visual information on that data, but we do not discern that it teaches or discloses the capability to remotely control fluid handling devices. See, e.g., Ex. 1005, code (54), 1:27–36, 2:50–3:2. More specifically, the Kahn disclosures that Petitioner repeatedly relies upon for allegedly teaching this control are deficient. See Ex. 1005, 10:62–67, 14:35– 15:2, 15:62–16:32; see also Pet. 12–14, 16–18. Kahn discloses that “the communication unit 112B can include on-site alerts such as optical (indicator lights), audible alerts (e.g., alarm sounds), tactile (e.g., vibration of the unit) or can be interfaced to an appropriate control valve for simply shutting off the supply of fluid upon the detection of emergency events, for instance.” Ex. 1005, 10:62–67. Communication unit 112B is part of the local “sensor unit,” wherein the detection conditions determined by the sensor are communicated to remote devices by communication unit 112B. See id. at 3:31–33, 5:62–6:2, 6:27–35, 7:33–37, 13:7–12, Figs. 1A–1C. Kahn discloses that the sensor units, which include communication units 112B, can be located near shut-off valves and can communicate with distant locations. See id. at 11:1–13. There are no disclosures, however, in the above passages that there is remote control of fluid handling devices, that there is a user command on a control interface that actuates an actuator, or that there is a command sent to the facility actuators via a network connection, as required in limitations [18.5]–[18.7] and [18.9]–[18.12], respectively. Rather, the disclosure indicates that the communication unit 112B includes on-site alerts and that the local (non-remote) communication unit 112B can be interfaced with the control valve.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 10,488,871
  • PTAB · Apr 30, 2025 · IPR2024-01494 · APJ Justin T Arbes · IPR · Institution

    The Board instituted review of claims 5, 6, and 9–20 on all asserted grounds after finding a reasonable likelihood that claim 5 would have been obvious over Bowen and Soukup.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “Pursuant to 35 U.S.C. § 314(a), the Director may not authorize an inter partes review unless the information in the petition and preliminary response “shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” See 37 C.F.R. § 42.4(a) (“The Board institutes the trial on behalf of the Director.”). For the reasons that follow, we institute an inter partes review as to claims 5, 6, and 9–20 of the ’909 patent on all grounds of unpatentability asserted with respect to those claims in the Petition.” slip op. at 2

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundReasonable expectation foundDecided for petitioner

      “We disagree with Patent Owner’s arguments based on the current record. Dr. Bokor testifies that “as is evident from the TMR equation, . . . lowering the resistance (barrier height) for parallel spin electrons [(i.e., Rp)] compared to antiparallel [(i.e., Rap)] improved TMRs.” Ex. 1024 ¶ 169 (citing Ex. 1035, 3273) (emphasis added). Dr. Bokor’s testimony is consistent with the TMR equation above, which has Rp as the only term in the denominator, and reflects that Rp would be lowered disproportionally, or otherwise the TMR would not have “improved.” Id. It also appears to be supported by other evidence of record. See Ex. 1035, 3273 (noting the” slip op. at 17

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element) › Inherent disclosureInherency not foundNot shown unpatentable

      “Finally, we note that, although Petitioner has made a sufficient showing with respect to obviousness, we are not persuaded by Petitioner’s inherency argument. See Pet. 36. Specifically, Petitioner has not established that a barrier height of 0.1–0.85 eV is necessarily present in, or the natural result of, a tunnel barrier layer having some amount of oxygen vacancy defects. See Hospira, Inc. v. Fresenius Kabi USA, LLC, 946 F.3d 1322, 1329 (Fed. Cir. 2020) (“When the prior art does not expressly disclose a claim limitation, ‘inherency may supply a missing claim limitation in an obviousness analysis.’ . . . Inherency is established in the context of obviousness when ‘the limitation at issue necessarily must be present, or the natural result of the combination of elements explicitly disclosed by the prior art.’”). Petitioner points to the ’909 patent’s statement that “[w]hen there are oxygen vacancy defects, the potential barrier height of the MgO tunnel barrier is thought to decrease (such as in the range of 0.10 to 0.85 eV; more specifically, 0.2 to 0.5 eV), which is thought to result in an increase in the tunneling current.” Ex. 1017, col. 7, ll. 19–23; see Pet. 36. Bowen, however, has “oxygen vacancy defects” in its MgO layer and “[o]xygen vacancies are naturally present in every oxide” according to Petitioner, but Bowen discloses a barrier height of 0.9 eV, which is outside the claimed range (albeit only slightly). Pet. 13, 23–24. Thus, Bowen contradicts Petitioner’s assertion that a barrier height within the claimed range of 0.1–0.85 eV is inherent when there are oxygen vacancy defects.” slip op. at 23

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “B. Level of Ordinary Skill in the Art Petitioner argues that at the time of the ’909 patent (2004), a person of ordinary skill in the art would have had “a Ph.D. in electrical engineering, physics, materials science, or a related field, and at least one year of experience in the research, design, and/or development of magnetic/spintronic devices, or the equivalent,” or “a Master’s degree in electrical engineering, physics, materials science, or a related field, and four years of experience in the research, design, and/or development of magnetic/spintronic devices, or the equivalent,” where “[l]ess work experience may be compensated by a higher level of relevant education, and vice versa.” Pet. 18–19 (citing Ex. 1024 ¶ 25). Patent Owner applies Petitioner’s definition of the level of ordinary skill in the art for purposes of its Preliminary Response. Prelim. Resp. 17. Based on the record presented, including our review of the ’909 patent and the types of problems and solutions described in the ’909 patent and cited prior art, we agree with Petitioner’s proposed definition of the level of ordinary skill in the art and apply it for purposes of this Decision.” slip op. at 9

    Claim construction§ 102 anticipation§ 103 obviousnesscites KSR · Graham
    Patents in suitUS 11,968,909
  • PTAB · Mar 14, 2025 · IPR2024-01449 · APJ Justin T Arbes · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1 and 2 were unpatentable under any of the four asserted obviousness grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “inter partes review unless the information in the petition and preliminary response “shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” See 37 C.F.R. § 42.4(a) (“The Board institutes the trial on behalf of the Director.”). For the reasons that follow, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “ordinary skill in the art would have had “a Ph.D. in electrical engineering, physics, materials science, or a related field, and at least one year of experience in the research, design, and/or development of magnetic/spintronic devices, or the equivalent,” or “a Master’s degree in electrical engineering, physics, materials science, or a related field, and four years of experience in the research, design, and/or development of magnetic/spintronic devices, or the equivalent,” where “[l]ess work experience may be compensated by a higher level of relevant education, and vice versa.” Pet. 29 (citing Ex. 1024 ¶ 25). Patent Owner applies Petitioner’s definition of the level of ordinary skill in the art for purposes of its Preliminary Response. Prelim. Resp. 17. Based on the record presented, including our review of the ’463 patent and the types of problems and solutions described in the ’463 patent and cited prior art, we agree with Petitioner’s proposed definition of the level of ordinary skill in the art and apply it for purposes of this Decision.” slip op. at 8

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededDecided for patent owner

      “C. Claim Interpretation We interpret each challenged claim using the same claim construction standard that would be used to construe the claim in a civil action under 35 U.S.C. 282(b), including construing the claim in accordance with the ordinary and customary meaning of such claim as understood by one of ordinary skill in the art and the prosecution history pertaining to the patent. 37 C.F.R. § 42.100(b). Petitioner argues that “the claim terms should be given their plain and ordinary meaning and no claim construction is necessary.” Pet. 25–26. Patent Owner does not propose interpretations of any claim terms in its Preliminary Response. We conclude that no express interpretation of any claim term is necessary to determine whether to institute an inter partes review in this proceeding. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“Because we need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy,’ we need not construe [a particular claim limitation] where the construction is not ‘material to the . . . dispute.’” (citation omitted) (emphasis added)).” slip op. at 9

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation not foundNot shown unpatentable

      “Further, because Bowen’s disclosed barrier height is outside the claimed range, Petitioner relies on Soukup’s purported teaching of a barrier height of “about 0.33 eV” and contends that a person of ordinary skill in the art would have been motivated to “achieve” that barrier height for the MgO barrier of Bowen’s device. Id. at 34–36. The data that Petitioner relies on from Soukup for the “about 0.33 eV” barrier height, though, was determined using the slope of an Arrhenius plot, not Simmons’ formula. Ex. 1028, 3229 (Abstract), 3231–33, Table I. In Soukup, apparent barrier heights for the samples were determined using (1) the slope of an Arrhenius plot, and (2) the zero-field intercept of the straight line logI versus V1/2 plot. Id. at 3229 (Abstract), 3230–32, Fig. 3, Table I. Reproduced below is Table I of Soukup, as annotated by Patent Owner (Prelim. Resp. 39): Annotated Table I of Soukup includes the results of analyses of sample test data, with the column highlighted in yellow showing the barrier heights obtained by a zero-field intercept method and the column highlighted in blue showing barrier heights obtained from the slope of an Arrhenius plot. See Ex. 1028, 3233; Prelim. Resp. 38–39. Dr. Bokor testifies that “Soukup disclosed that Simmons’ formula was used to approximate tunnel barrier height” and “[o]ne of skill would have understood the ‘height and the bias dependence of the insulator potential-energy barrier’ [referenced in Soukup] included the tunnel barrier height.” Ex. 1024 ¶¶ 145–147 (quoting Ex. 1028, 3229; citing Ex. 1024 ¶¶ 45–49). We do not find this testimony persuasive. Although Soukup refers to “Simmons’ model” and the Simmons 1963 paper in its “Introduction,” it does not teach any calculation using Simmons’ formula to obtain a barrier height within the claimed range. See Ex. 1028, 3229, 3236 n.1; Prelim. Resp. 63. Soukup plainly recognizes that there are methods of calculating barrier height other than Simmons’ formula, and discusses at length its calculations using two such methods: the Arrhenius plot method and the zero-field intercept method. See, e.g., Ex. 1028, 3229 (Abstract) (“These results . . . indicate a potential barrier height of about 0.72 eV when determined from the zero-field intercept of the straight line logI vs V1/2 plot and about 0.33 eV when obtained from an Arrhenius plot.”), 3232–33. Petitioner does not address whether the 0.33 eV barrier height it relies on from Soukup (determined using the Arrhenius plot method) would still be within the claimed range if calculated using Simmons’ formula. See Prelim. Resp. 63. Nor does Petitioner rely on any values from Soukup’s disclosure that would be used as the variables in Simmons’ formula—Petitioner relies solely on Bowen. See Pet. 39–42. Thus, Petitioner’s argument that Bowen and Soukup teach a barrier height within the claimed range, obtained using equation (1), is not persuasive. See id. at 34–42.” slip op. at 17

    Claim construction§ 102 anticipation§ 103 obviousnesscites KSR · Graham
    Patents in suitUS 9,123,463
  • PTAB · Feb 14, 2025 · IPR2024-01221 · APJ Iftikhar Ahmed · IPR · Institution

    Instituted review of claims 1, 2, 4, 5, 7, 8, 12, 13, 17, 19–21, 23, 24, 26, 27, 29, 30, 34, 39–41, and 43 on all asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “We have authority to determine whether to institute an inter partes review. See 35 U.S.C. § 314 (2018); 37 C.F.R. § 42.4(a) (2022). To institute an inter partes review, we must determine that the information presented in the Petition shows “a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). Based on the information presented in the Petition and the supporting evidence, we are persuaded that there is a reasonable likelihood that Petitioner would prevail with respect to at least one of the challenged claims. Accordingly, we institute an inter partes review of the challenged claims on the grounds set forth in the Petition.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “have had “a relatively high level of skill, such as having at least a bachelor’s degree in the field of computer science and/or electrical engineering, together with 2–3 years in the financial technology sector.” Pet. 16. Petitioner adds that a person having ordinary skill in the art “would have knowledge of the commercial and scientific literature pertaining to securing transactions” and “would also have knowledge of processing devices.” Id. at 16–17 (citing Ex. 1002 ¶ 19). Patent Owner does not address the level of ordinary skill in the art in its Preliminary Response. See Prelim. Resp. Based on our review of the record before us, we determine that Petitioner’s stated level of ordinary skill in the art is reasonable because it appears consistent with the evidence of record, including the asserted prior art. Accordingly, for the purposes of this Decision, we adopt Petitioner’s definition.” slip op. at 11

    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITAPlain and ordinary meaningDecided for petitioner

      “At this stage of the proceeding, we are not persuaded that the term “embedded” should be narrowly construed in the manner proposed by Patent Owner. We find nothing in the claims that requires us to import a “hidden” or a “provide security” limitation into the claims. Claim 1, for example, merely recites “the image having information embedded therein, including information related to a transaction,” and “generat[ing] an output based on the information embedded in the image.” Ex. 1001, 16:24–33 (emphasis added). The claim language therefore does not require limiting embedded information in the proposed way.” slip op. at 13

    • Claim Construction › Intrinsic evidence (Phillips canons) › Specification disavowal / 'present invention' languageDisclaimer not foundDecided for petitioner

      “As discussed above, disclaiming or disavowing claim scope requires a “clear and unmistakable disclaimer.” Thorner, 669 F.3d at 1367. We are not persuaded that the cited portion can be read to clearly and unmistakably disavow claim scope. The cited portion of the Specification discusses various input parameters for decoding a captured image. Ex. 1001, 6:8–10. When viewed in context, “other information” refers to other predetermined information, including “the corresponding private key,” “stored in the memory 150,” which “may be used to decrypt or decode the captured image.” Id. at 6:13–22; see also id. at 5:18–20 (private keys are stored in memory). We therefore read the Specification as merely listing possible input parameters for decoding an image and not disclaiming “the corresponding private key” from the scope of “predetermined information.” After all, the very next sentence states that “predetermined information may include, for example, address information, personal profile information, and payment account information.” Id. at 6:17–22 (emphasis added). Given the various broad categories included in “predetermined information,” we are not persuaded, for purposes of institution, that “predetermined information” excludes a private key. We further determine that this preliminary construction is sufficient to resolve the Petitioner’s anticipation and obviousness contentions presented under Petitioner’s Ground 1, and no further construction of the term is necessary.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites KSR · Graham
    Patents in suitUS 7,314,167
Page 1 of 12
← Previous12345…Next →

Holdings, summaries, rulings, issues, outcomes, winners and claim constructions shown for a decision were generated by a large language model reading the opinion. They are a guide to the decision, not the decision. Confirm every one against the court's own text before relying on it. Outcomes read from the patent owner’s side. Party names are extracted from the decision and are missing on about 900 short Director denials and scans, which carry the trial number instead.