  • PTAB · Oct 10, 2025 · IPR2025-00652 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–23 and 25–30 were unpatentable over the asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’403 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 12

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “The parties assert that each claim term should be construed in accordance with its plain and ordinary meaning. Pet. 10; Prelim. Resp. 4 (citing Ex. 2009 ¶ 73); see Ex. 1002 ¶ 22 (opining the same). And, in the respective claim construction sections of their briefs, the parties do not propose any claim terms for express construction. We agree with the parties that no claim terms require express construction to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 13

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “We agree with Patent Owner that the Petition fails to demonstrate that Kahn discloses element [1.2] because the evidence cited does not disclose a “first computer system being configured to provide remote control of the first pump or first valve” (i.e., a fluid-handling device). Kahn is directed to providing access to fluid sensing data and analyzing and providing visual information on that data, but Petitioner has not identified any disclosure of the capability to remotely control fluid-handling devices. See, e.g., Ex. 1005, code (54), 1:27–36, 2:50–3:2. More specifically, Kahn’s disclosures that Petitioner relies on for allegedly teaching remote control are deficient. We discuss each. First, Petitioner points to the following, “[f]or instance, as illustrated in FIG. 1C, a fluid control device such as a valve 15A is located on the input side of a sen[s]or unit 110.” Ex. 1005, 8:19–21, cited in Pet. 13. This portion of Kahn, however, does not disclose remote control. Second, Petitioner cites to the following: Finally, or in addition to, the communication unit 112B can include on-site alerts such as optical (indicator lights), audible alerts (e.g., alarm sounds), tactile (e.g., vibration of the unit) or can be interfaced to an appropriate control valve for simply shutting off the supply of fluid upon the detection of emergency events, for instance. Pet. 13 (citing Ex. 1005, 10:62–67). We agree with Patent Owner that this portion of Kahn teaches on-site alerts and local control of the fluid-handling device. See Prelim. Resp. 7. This portion of Kahn does not disclose remote control.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,294,403
  • PTAB · Oct 10, 2025 · IPR2025-00651 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–3, 6, 7, and 9–20 were unpatentable over any asserted ground.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’680 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 11

    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed patent owner constructionDecided for patent owner

      “target value” is part of a command that is sent from a computing device to a server and then to a controller. The controller then receives a measurement of the fluid by a sensor and determines whether the measurement satisfies the “target value.” If the measurement does not satisfy the “target value,” further operations are undertaken. The recited operation sequence makes clear that the plain and ordinary meaning of “target value” is not as Dr. Wooley opines because the particular operating condition that a device is in at a particular time is represented by the measurement taken by the sensor, 11 Some claim language less relevant to construing “target value” was omitted for ease of reference. which the controller then uses to determine whether the measurement satisfies the “target value.” Additionally, claim 1 recites that the “target value” is sent as part of a command to the controller. The “target value” is not sent to the controller from the sensor, as might be expected if the plain and ordinary meaning of “target value” were as Dr. Wooley opines. Petitioner and Dr. Wooley’s construction would also result in “target value” meaning effectively the same thing as the measurement of the fluid by the sensor, a concept that is separately recited in claim 1 and to which the “target value” is compared. The Specification of the ’680 patent does not support Petitioner’s understanding of the plain and ordinary meaning of “target value.” Although the Specification does not recite “target value,” it recites “target state,” and describes “target state” sufficiently to understand the plain and ordinary meaning of “target” as used in “target value” and “target state.” In particular, the ’680 patent explains that “[i]n some embodiments, the process 104 includes receiving, via a network interface, from a remote user device, (e.g., via a command-center server) a command to change a state of a fluid-handling device to a target state.” Ex. 1001, 11:48–51. This portion reflects that the command is seeking to change a state of a fluid-handling device to a target state. In other words, the “target value” or “target state” is not generally “the particular operating condition that a device is in at a particular time”; rather, it is a value or state that the fluid-handling device is desired to be in, as Patent Owner and Dr. Durham explain. Additionally, just as claim 1 recites a directional component for the “target value” to be sent to the controller in a command, so too does the Specification describe a “target state” as being sent in a command from a remote user device. Thus, the Specification clearly supports the plain and ordinary meaning proposed by Patent Owner and Dr. Durham and not the plain and ordinary meaning proposed by Petitioner and Dr. Wooley. slip op. at 14

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “time-stamped process data, report exception therein to the remote host, and extract and transmit time-stamped process data to the remote host.” Ex. 1005, Abst. (emphases added). Almadi explains that its remote field systems must include a plurality of controller units “to issue commands to, and gather and process data from a plurality of field devices, including remote systems and instruments, . . . [and] a database server for the storage of process data retrieved from the remote subsystems and instruments.” Id. at 2:22–30 (emphases added). Based on these disclosures, we agree with Patent Owner that Petitioner has not established that Almadi discloses element [1.4]. Specifically, the teachings from Almadi identified by Petitioner refer to process data, which is data retrieved from the remote subsystems/field devices. Thus, we understand that Almadi’s teaching—of using an Ethernet switch to transmit “process data”—describes transmitting data from the remote subsystems/field devices. See Ex. 1005, 3:13–17, cited in Pet. 15. But claim 1 and particularly element [1.4], recites “sending, with the server, the target value to the network address [which identifies a controller of the fluid-handling device13] via the network,” which is different than sending process data from the field devices to the remote host or database server for storage.” slip op. at 19

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,175,680
  • Tanklogix, LLC v. SiteproInstitution denied
    PTAB · Oct 10, 2025 · IPR2025-00650 · APJ Sheila F Mcshane · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 18–32 and 34 were unpatentable over Kahn or Kahn and Gutierrez.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “information presented in the petition . . . and any response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). Upon consideration of the Petition, the Preliminary Response, and the evidence of record, we determine that Petitioner has not established a reasonable likelihood of prevailing with respect to the unpatentability of at least one claim of the ’871 patent. Accordingly, for the reasons that follow, we decline to institute an inter partes review of claims 18–32 and 34 of the ’871 patent.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The respective proposed levels of qualifications for a person of ordinary skill in the art are similar, with Patent Owner proposing two years of experience compared to Petitioner proposing significant experience with remotely controlling fluid-handling devices, like SCADA systems. Patent Owner also proposes more extensive experience in lieu of educational experience. While we find Petitioner’s proposed qualifications to be acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of skill necessary to understand and implement the teachings of the ’871 patent and the asserted prior art. Our analysis and findings herein, however, do not turn on any differences in the qualifications adopted.” slip op. at 8

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “We determine that we need not expressly construe any claim terms to resolve the parties’ disputes on the current record. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“[W]e need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))).” slip op. at 10

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “actuators and the remote control of fluid handling devices, including the receipt with the user-interface module of “a user command to actuate an actuator via a presented control interface” (limitation [18.7]) and “account authorized to send commands to remotely control fluid handling devices” (limitation [18.11]). We agree with Patent Owner that the Petition fails to demonstrate that Kahn discloses or teaches these limitations because the evidence does not provide support that there is remote control of fluid handling devices or the use of a user command on a control interface to send a command to a fluid handling device, for instance. Kahn is directed to providing access to fluid sensing data and analyzing and providing visual information on that data, but we do not discern that it teaches or discloses the capability to remotely control fluid handling devices. See, e.g., Ex. 1005, code (54), 1:27–36, 2:50–3:2. More specifically, the Kahn disclosures that Petitioner repeatedly relies upon for allegedly teaching this control are deficient. See Ex. 1005, 10:62–67, 14:35– 15:2, 15:62–16:32; see also Pet. 12–14, 16–18. Kahn discloses that “the communication unit 112B can include on-site alerts such as optical (indicator lights), audible alerts (e.g., alarm sounds), tactile (e.g., vibration of the unit) or can be interfaced to an appropriate control valve for simply shutting off the supply of fluid upon the detection of emergency events, for instance.” Ex. 1005, 10:62–67. Communication unit 112B is part of the local “sensor unit,” wherein the detection conditions determined by the sensor are communicated to remote devices by communication unit 112B. See id. at 3:31–33, 5:62–6:2, 6:27–35, 7:33–37, 13:7–12, Figs. 1A–1C. Kahn discloses that the sensor units, which include communication units 112B, can be located near shut-off valves and can communicate with distant locations. See id. at 11:1–13. There are no disclosures, however, in the above passages that there is remote control of fluid handling devices, that there is a user command on a control interface that actuates an actuator, or that there is a command sent to the facility actuators via a network connection, as required in limitations [18.5]–[18.7] and [18.9]–[18.12], respectively. Rather, the disclosure indicates that the communication unit 112B includes on-site alerts and that the local (non-remote) communication unit 112B can be interfaced with the control valve.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 10,488,871
  • PTAB · Jul 14, 2025 · IPR2024-00465 · APJ Bart A Gerstenblith · IPR · Final written decision

    Claims 1–24 are unpatentable: claims 1–10 and 12–24 as obvious over Szrek and Llach, and claim 11 as obvious over Szrek, Llach, and Gilmore.

    RulingsFinal written decision
    • Skill levelSkill level board ownDecided for petitioner

      “B. Level of Ordinary Skill in the Art Petitioner proposes that the level of ordinary skill in the art is an artisan with a working knowledge of POS activation systems and lottery systems that was gained through a mixture of training and work experience in the relevant field such as (i) having a Bachelor’s degree in computer science, computer communications, electrical engineering, or equivalent degree, coupled with at least three years of work experience; (ii) having a Master’s degree in computer science, computer communications, or electrical engineering, but having less work experience; or (iii) having no formal degree, but having experience in the relevant field of at least six years of work experience. Pet. 2–3 (citing Ex. 1003 ¶¶ 13–14).9 Patent Owner states that, “[f]or the purpose of this proceeding, Patent Owner adopts the Petition’s proposed definition of the level of ordinary skill in the art.” PO Resp. 19 (citing Pet. 2–3). We find that the parties’ agreed-upon level of ordinary skill in the art is consistent with the level of ordinary skill in the art reflected by the ’451 patent and the prior art of record. See Inst. Dec. 14; see Okajima v. 9 Petitioner proposes the same level of ordinary skill in the art that the Board adopted in PGR2020-00084 (Pet. 2–3 (citing Ex. 1008, 11)), and IPR2023- 01235 (see IPR2023-01235, Paper 34 at 12–13). Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Therefore, we adopt the parties’ agreed-upon level of ordinary skill in the art, as articulated above, in our consideration of the issues presently before us.” slip op. at 13

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededNot reached

      “We need not construe “transaction processor” expressly because its meaning is not in dispute and its construction is not necessary to resolve the controversy before us.” slip op. at 16

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundReasonable expectation foundDecided for petitioner

      “On balance, we find that even with the alleged disadvantages identified by Patent Owner, one of ordinary skill in the art would have been motivated to modify Szrek with Llach’s third-party transaction processor because the advantage of having a “centralized intermediary” allows Szrek’s system to support different game providers, such as different lottery companies, which would reduce some implementation costs and allow the system to be more easily and cheaply extended. Pet. 47 (citing Ex. 1003 ¶ 181); see Medichem, S.A. v. Rolabo, S.L., 437 F.3d 1157, 1165 (Fed. Cir. 2006) (“a given course of action often has simultaneous advantages and disadvantages, and this does not necessarily obviate motivation to combine”) (citing Winner Int’l Royalty Corp. v. Wang, 202 F.3d 1340, 1349 n.8 (Fed. Cir. 2000)); see also Intel Corp. v. Qualcomm Inc., 21 F.4th 784, 795 (Fed. Cir. 2021) (stating the same). We acknowledge that the combination comes with some disadvantages, including “add[ed] delay, reduce[d] efficiency, and . . . implementation complexities by converting a simple, direct communication exchange into an exchange that traverses multiple systems.” PO Resp. 52 (citing Ex. 2052 ¶ 163). But, “[t]he fact that the motivating benefit comes at the expense of another benefit, however, should not nullify its use as a basis to modify the disclosure of one reference with the teachings of another. Instead, the benefits, both lost and gained, should be weighed against one another.” Winner, 202 F.3d at 1349 n.8. Here, Szrek expressly teaches indirect communication as a possible implementation of its system and Petitioner’s combination—employing Llach’s third-party transaction processor as part of the indirect communication channel—offers the attractive benefit of allowing Szrek’s system to support different game providers, which would reduce some implementation costs even if it might increase other costs, e.g., by having to program certain components (e.g., the cash registers) differently. Specifically, we find that the ability to expand Szrek’s system to support different game providers provides advantages that outweigh the disadvantages discussed above in the circumstance where one desires a more robust and comprehensive system. See Pet. Reply 23 (noting three advantages of the combination— (1) “allow[ing] Szrek’s system to use ‘a centralized system for activating lottery tickets from different retailers and different locations,’” (2) “allow[ing] support for different game providers, such as different lottery companies,” “reduc[ing] implementation costs,” and (3) “allow[ing] Szrek’s system to ‘communicate with individual card” slip op. at 37

    • Obviousness (§103) › Motivation to combine / reasonable expectation of success › HindsightMotivation foundDecided for petitioner

      “On balance, we find that even with the alleged disadvantages identified by Patent Owner, one of ordinary skill in the art would have been motivated to modify Szrek with Llach’s third-party transaction processor because the advantage of having a “centralized intermediary” allows Szrek’s system to support different game providers, such as different lottery companies, which would reduce some implementation costs and allow the system to be more easily and cheaply extended. Pet. 47 (citing Ex. 1003 ¶ 181); see Medichem, S.A. v. Rolabo, S.L., 437 F.3d 1157, 1165 (Fed. Cir. 2006) (“a given course of action often has simultaneous advantages and disadvantages, and this does not necessarily obviate motivation to combine”) (citing Winner Int’l Royalty Corp. v. Wang, 202 F.3d 1340, 1349 n.8 (Fed. Cir. 2000)); see also Intel Corp. v. Qualcomm Inc., 21 F.4th 784, 795 (Fed. Cir. 2021) (stating the same). We acknowledge that the combination comes with some disadvantages, including “add[ed] delay, reduce[d] efficiency, and . . . implementation complexities by converting a simple, direct communication exchange into an exchange that traverses multiple systems.” PO Resp. 52 (citing Ex. 2052 ¶ 163). But, “[t]he fact that the motivating benefit comes at the expense of another benefit, however, should not nullify its use as a basis to modify the disclosure of one reference with the teachings of another. Instead, the benefits, both lost and gained, should be weighed against one another.” Winner, 202 F.3d at 1349 n.8. Here, Szrek expressly teaches indirect communication as a possible implementation of its system and Petitioner’s combination—employing Llach’s third-party transaction processor as part of the indirect communication channel—offers the attractive benefit of allowing Szrek’s system to support different game providers, which would reduce some implementation costs even if it might increase other costs, e.g., by having to program certain components (e.g., the cash registers) differently. Specifically, we find that the ability to expand Szrek’s system to support different game providers provides advantages that outweigh the disadvantages discussed above in the circumstance where one desires a more robust and comprehensive system. See Pet. Reply 23 (noting three advantages of the combination— (1) “allow[ing] Szrek’s system to use ‘a centralized system for activating lottery tickets from different retailers and different locations,’” (2) “allow[ing] support for different game providers, such as different lottery companies,” “reduc[ing] implementation costs,” and (3) “allow[ing] Szrek’s system to ‘communicate with individual card” slip op. at 37

    Patent outcomesUS 11,488,451 unpatentable
    Claim construction§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,488,451
  • PTAB · May 28, 2025 · IPR2025-00301 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution of review for claims 1–11, 16, and 21 under § 314(a), finding the Fintiv factors favored discretionary denial, and denied joinder.

    RulingsInstitution decision
    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Institution denied fintivInstitution denied

      “2026. This date is nearly five months prior to the date on which the final written decision would be due if trial were instituted in this proceeding. And, even if we assume Petitioner’s alleged February–March 2026 trial date, this date too is several months prior to the projected final written decision deadline. As such, it is unlikely that a final written decision in this proceeding would issue before trial in the district court, unless the trial was delayed or rescheduled for a later time. Thus, we find this factor weighs in favor of exercising our discretion to deny institution. See ARM Ltd. v. Daedalus Prime LLC, IPR2025-00207, Paper 10 at 2 (May 16, 2025) (Before the Office of the Under Secretary of Commerce for Intellectual Property and Director of the United States Patent and Trademark Office) (exercising discretion to deny institution with the same relative timing between district court trial and final written decision deadline).” slip op. at 13

    • PTAB / AIA Trials › Motions to amend / substitute claimsNot reached
    • PTAB / AIA Trials › Joinder §315(c) / SAS all-or-nothingJoinder, deniedDenied
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied discretionary otherInstitution denied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). Institution of inter partes review, however, is discretionary. See Harmonic Inc. v. Avid Tech., Inc., 815 F.3d 1356, 1367 (Fed. Cir. 2016) (“[T]he PTO is permitted, but never compelled, to institute an IPR proceeding.”). For the reasons discussed below, we exercise discretion pursuant to 35 U.S.C. § 314(a) not to institute inter partes review. Additionally, for the same reasons and because institution was denied in IPR2024-01248, we deny Petitioner’s Motion for Joinder. See 35 U.S.C. § 315(c) (“[T]he Director . . . may join as a party . . . any person who properly files a petition under section 311 that the Director . . . determines warrants the institution of an inter partes review under section 314.”).” slip op. at 3

    Discretionary denial
    Patents in suitUS 9,814,071
  • PTAB · Mar 21, 2025 · IPR2024-01250 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood of proving claims 1–5, 7, 9–16, or 20 unpatentable over the asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “An inter partes review may be instituted only if “the information presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2018). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “B. Level of Ordinary Skill in the Art Petitioner, supported by Dr. Min’s testimony, proposes that a person of ordinary skill in the art at the time of the invention would have had “at least a bachelor’s [degree] in [electrical engineering, computer engineering, or computer science], physics, or equivalent, and two years of experience with cellular telecommunications, radio-access network architectures, protocols and signal propagation in wireless networks.” Pet. 3 (citing Ex. 1003 ¶ 59). Dr. Min testifies that “[a]dditional education could substitute for professional experience and vice versa.” Ex. 1003 ¶ 59. Additionally, Petitioner contends that Dr. Min “exceeded this level of experience by the priority date.” Pet. 3 (citing Ex. 1010 (curriculum vitae of Dr. Min)). In its Preliminary Response, Patent Owner does not take a position on the relevant level of ordinary skill in the art. See generally Prelim. Resp. At this stage of the proceeding and on the present record, we adopt Petitioner’s uncontested proposed level of ordinary skill in the art, which we find consistent with the level of ordinary skill in the art reflected by the ’946 patent and the prior art of record. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978).” slip op. at 10

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededNot reached

      “Neither party contends that any claim terms require an express construction to resolve the present controversy. Pet. 8 (“For purposes of this Petition only, Petitioner does not believe any terms require a formal construction.”); see generally Prelim. Resp. Nonetheless, Petitioner explains that the Petition is structured such that “Ground 1 is based on Patent Owner’s infringement contentions in the district court litigation, where the claimed ‘MUD module’ is generally mapped to multiple-input multiple-output (MIMO) receivers in a wireless network.” Pet. 2. Petitioner contends that “[u]nder this broad interpretation of a ‘MUD module,’ Walton’s MIMO receiver renders every challenged claim obvious.” Id. In contrast to Ground 1, the Petition states that “Ground 2 is based on the plain meaning of ‘MUD module,’ which is a component that detects, separates, and decodes signals from multiple users transmitting simultaneously over the same frequency band.” Id. Petitioner contends that, “[a]pplying the correct meaning of the term, Walton’s MIMO receiver does not necessarily comprise a MUD module.” Id. Therefore, Petitioner explains that “Ground 2 combines Walton with Learned, which expressly discloses [a] multi-user detector, and thus renders every challenged claim obvious in combination with Walton.” Id. at 2–3.7 In other words, the Petition presents Ground 1 and Grounds 2/3 as alternatives depending on the meaning of 7 Although not specifically relevant to claim construction, Petitioner explains that “Ground 3 further combines Walton and Learned with Quigley, to the extent Patent Owner argues Walton does not disclose providing a burst control input.” Pet. 3. “MUD module,” where Ground 1 is based on Petitioner’s understanding of Patent Owner’s interpretation of the term and Grounds 2 and 3 are based on Petitioner’s interpretation of the term as having its plain meaning. Petitioner further contends that “[e]very other claim term carries its ‘ordinary and customary meaning’ . . . .” Id. at 8. Although Petitioner presents a potential dispute regarding the meaning of “MUD module,” we need not construe this term expressly because the determination we reach herein does not depend on which meaning MUD module is applied. Accordingly, we do not construe any claim terms expressly because express constructions are not necessary to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 12

    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Not reached

      “IV. DISCRETIONARY DENIAL Patent Owners contends that the factors set forth in Apple Inc. v. Fintiv, Inc., IPR2020-00019, Paper 11 at 9 (PTAB Mar. 20, 2020) (precedential), weigh heavily in favor of discretionary denial. Prelim. Resp. 40–46; Paper 10. Petitioner disagrees. Pet. 74–77; Paper 9. In light of the conclusion reached above, we need not address the parties’ arguments regarding discretionary denial.” slip op. at 25

    Claim construction§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 8,089,946
  • PTAB · Mar 21, 2025 · IPR2024-01248 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because the Petition did not show a reasonable likelihood of proving claims 1–11, 16, and 21 unpatentable over the asserted obviousness grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsInstitution denied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2018). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “At this stage of the proceeding and on the present record, we adopt Petitioner’s uncontested proposed level of ordinary skill in the art, which we find consistent with the level of ordinary skill in the art reflected by the ’071 patent and the prior art of record. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978).” slip op. at 12

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “Neither party proposes a specific construction of any claim term, although Petitioner contends each term should be construed according to its plain and ordinary meaning. Pet. 16; see generally Prelim. Resp. Accordingly, we need not construe any claim terms expressly because the meaning of the terms is not in dispute and an express construction is not necessary to resolve the controversy before us.” slip op. at 13

    • BurdenNot shown unpatentable

      “We find the Petition lacking in particularity because it does not clearly identify what aspect of Jin is alleged to teach the unique signal parameters (or unique estimated signal parameters) recited in claim 1. See, e.g., 35 U.S.C. § 312(a)(3) (“A petition filed under section 311 may be considered only if — (3) the petition identifies, in writing and with particularity, . . . the evidence that supports the ground for the challenge to each claim . . . .”). First, as reflected above, the Petition asserts that something called a “unique pilot parameter” teaches the recited unique estimated signal parameters. But “unique pilot parameter” is not a term or phrase recited in Jin. See Prelim. Resp. 19 (arguing the same). So, when Petitioner states “Jin discloses that the base station uses the unique pilot parameter (i.e., ‘unique estimated signal parameters’) to ‘identify which user (i.e., mobile terminal) has transmitted the received data,’” it is not clear what element in Jin Petitioner intends to identify by the term “unique pilot parameter.” Dr. Min’s testimony does not help resolve the ambiguity in the Petition. In particular, Dr. Min also refers to a “unique pilot parameter (i.e., ‘unique signal parameter’) for each user.” Ex. 1003 ¶ 89. But, as noted above, Jin does not disclose an element referred to as a “pilot parameter” and it is not clear what element Dr. Min intended to identify in Jin.8” slip op. at 18

    Claim construction§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 9,814,071
  • PTAB · Feb 19, 2025 · IPR2023-01363 · APJ Jon B Tornquist · IPR · Final written decision

    Claims 1, 2, and 10–13 are unpatentable as obvious over the stated combinations of Holmberg, Battey, Blankenship, and Cowen.

    RulingsFinal written decision
    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Petitioner contends a person of ordinary skill in the art “would have had at least a bachelor’s degree in electrical engineering, computer engineering, or a related field, and at least 1 year of experience related to communication networks or the equivalent.” Pet. 7. Petitioner further contends that “[a]dditional education could substitute for professional experience or significant experience in the field could substitute for formal education.” Id. at 7–8 (citing Ex. 1003 ¶¶ 29–31). Dr. Eldering agrees that one of ordinary skill in the art “would have had at least a bachelor’s degree in electrical engineering, computer engineering, or a related field, and at least one year of experience related to communication networks or the equivalent.” Ex. 2001 ¶ 24. According to Dr. Eldering, “[a] person with less relevant practical experience but with additional experience would also qualify.” Id. Patent Owner contends that” slip op. at 9

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededNot reached

      “Although Patent Owner disagrees with Petitioner’s construction, it contends “the Board need not resolve this claim construction dispute because Petitioner’s proposed grounds 1-5 are all insufficient under either construction.” PO Resp. 19. Upon review of the parties’ arguments and the prior art of record, we determine that no claim terms require express construction for purposes of this decision. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)). For example, we discuss below in Section III.G why we do not reach the claim construction issue presented by Petitioner.” slip op. at 11

    • Expert testimonyPetitioner expert creditedDecided for petitioner

      “We find that Holmberg expressly contemplates using its wall box within multi-dwelling units, notes that multi-dwelling wall boxes in the prior art were “typically provided” on every floor, and discloses that the multi-dwelling wall boxes would contain optical couplings for each resident on a given floor. Ex. 1004 ¶¶ 7, 34; Pet. Reply 8–10. In view of these disclosures, we credit the testimony of Dr. Kiaei that one of ordinary skill in the art would have sought to use Holmberg’s wall box in multi-dwelling units and would have seen a need to access the area behind spice tray 230 to connect and disconnect subscribers. Ex. 1003 ¶ 92; Ex. 1033 ¶¶ 7–8. Moreover, even if Holmberg were limited to mid-span locations and distributing drop cables, as opposed to distribution cables for individual subscribers, as asserted by Patent Owner, Patent Owner does not dispute that a technician would still need periodic access to the area behind splice tray 230 in these mid-span devices. Tr. 38:3–39:1 (counsel agreeing that one would need to access the area behind splice tray 230 in Holmberg, albeit in “rare occasions”); Ex. 1003 ¶¶ 90–92; Ex. 1033 ¶¶ 7–8. Thus, whether used in the manner contemplated by Petitioner or Patent Owner, Petitioner persuasively demonstrates that access to the space behind splice tray 230 in Holmberg would be necessary. With access behind splice tray 230 required, Petitioner persuasively demonstrates that one of ordinary skill in the art would have seen a benefit to replacing Holmberg’s fasteners or screws with a hinged connection, such as that disclosed in Battey, to allow easier access to the area behind the splice tray. Pet. 41 (citing Ex. 1005 ¶ 39 (disclosing that a rotatable splice tray or shelf would “provide[] full and convenient access to the splice tray”)). First, Petitioner and Dr. Kiaei persuasively demonstrate that once the fibers of Holmberg are routed from behind splice tray 230 and the distribution cables spooled on this tray, a technician could not reasonably access fiber optic cables stored behind splice tray 230 without releasing or opening splice tray 230. Pet. Reply 14–15 (citing Ex. 1023, 60:20–61:15); Ex. 1033 ¶¶ 31–32. Second, Petitioner persuasively demonstrates that without a hinged connection, the technician would have to either hold the splice tray of Holmberg with one hand while performing the necessary routing and splicing steps, two screws would need to remain in place (essentially replicating a hinge), or the tray would have to be left to dangle, supported only by the routed and spliced fibers. Pet. Reply 19–20.” slip op. at 22

    • Strike new argumentNew argument consideredDecided for petitioner

      “Allegedly New Arguments on Reply Patent Owner contends that Petitioner’s arguments regarding the benefits of a hinged connection when performing the splicing and routing steps should be dismissed or ignored because they were improperly raised for the first time on reply. Sur-reply 19–20. We disagree. The Petition asserts that one of ordinary skill in the art would have sought to add a hinged connection, such as that disclosed in Battey, in Holmberg and would have seen a benefit to so doing. Pet. 40–44. Petitioner did not change its proposed combination or its stated rationale in its Reply. Rather, in response to Patent Owner’s counter-arguments, Petitioner expands upon the benefits of its proposed combination, i.e., the substitution of a hinged connection in place of fasteners. Pet. Reply 15–21. This is permissible, as a reply may properly expand on or extend previously raised arguments relating to the motivation to make the proposed changes to the prior art. See Rembrandt Diagnostics, LP v. Alere, Inc., 76 F.4th 1376, 1385 (Fed. Cir. 2023) (explaining that the reply arguments properly relied on the same legal ground, the same prior art references, and same legal argument—the motivation to make the proposed changes to the prior art reference).” slip op. at 25

    Patent outcomesUS 9,008,483 unpatentable
    Claim construction§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 9,008,483
  • PTAB · Feb 13, 2025 · IPR2024-00978 · APJ Bart A Gerstenblith · IPR · Institution

    The Board instituted IPR on claims 1–17 on all petition grounds, finding a reasonable likelihood that Dolan renders at least one challenged claim obvious.

    RulingsInstitution decision
    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “letter stipulating that if the Board institutes this IPR petition on the grounds presented therein, then Samsung will not pursue in the above-captioned litigation any grounds that were raised or reasonably could have been raised in the IPR. For the sake of clarity, this stipulation does not extend to co-petitioner Google, which is not a party to the above-referenced litigation.” slip op. at 7

    • PTAB / AIA Trials › Real party in interest / privityNot reached

      “Electronics, America, Inc.; and Google LLC as real parties in interest. Pet. 61. Petitioner explains that “Google LLC is a subsidiary of XXVI Holdings Inc., which is a subsidiary of Alphabet Inc.” Id. at 61 n.10. Petitioner asserts that “XXVI Holdings Inc. and Alphabet Inc. are not real parties-in-interest to this proceeding.” Id. Patent Owner identifies Cerence Operating Co. and Cerence, Inc. as real parties in interest. Paper 5, 1. Patent Owner disagrees with Petitioner, contending Alphabet Inc. is also a real party in interest. Id. At this stage of the proceeding, we need not determine whether Alphabet Inc. is a real party in interest to Petitioner since neither Petitioner nor Patent Owner has identified any effect that determination would have on the outcome of this proceeding. To the extent Patent Owner seeks to maintain this contention, it should raise the issue in its Patent Owner response.” slip op. at 3

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Patent Owner does not currently take a position on the relevant level of ordinary skill in the art, but believes that “the Board could assume Petitioner’s proposed level of ordinary skill for purposes of deciding whether to institute.” Prelim. Resp. 3. At this stage of the proceeding and on the present record, we adopt Petitioner’s uncontested, proposed level of ordinary skill in the art, which we find consistent with the level of ordinary skill in the art reflected by the ’078 patent and the prior art of record. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978).” slip op. at 10

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “An inter partes review may be instituted only if “the information presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). For the reasons given below, on this record, Petitioner has established a reasonable likelihood that it would prevail in showing the unpatentability of at least one of the Challenged Claims. Accordingly, we institute an inter partes review of the Challenged Claims on all grounds raised in the Petition.” slip op. at 2

    § 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 7,395,078
  • PTAB · Jan 31, 2025 · IPR2024-01267 · APJ Lisa A Murray · IPR · Institution

    The Board instituted IPR on claims 1–3, 7–9, 12, and 13 on all petitioned grounds, finding a reasonable likelihood that claim 1 is obvious over Arai and Fenwick.

    RulingsInstitution decision
    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “the PTAB will not discretionarily deny institution of an IPR . . . in view of parallel district court litigation where a petitioner stipulates not to pursue in a parallel district court proceeding the same grounds as in the petition or any grounds that could have reasonably been raised in the petition. Petitioner’s stipulation in Exhibit 1020 satisfies the language from the Director’s Memorandum quoted above. Therefore, we need not analyze each Fintiv factor before determining that we will not exercise our discretion to deny institution in view of the parallel Eastern District of Texas Litigation. In light of Petitioner’s stipulation, Patent Owner’s request is denied.” slip op. at 6

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “any evidence of objective indicia of nonobviousness. We conclude that on balance, considering the record presently before us, Petitioner has established a reasonable likelihood of showing that the differences between the subject matter of claim 1 and the teachings of Arai and Fenwick are such that the subject matter, as a whole, would have been obvious at the time of the invention to a person having ordinary skill in the art. e. Summary as to Claim 1 For the reasons discussed above, on the present record we find that Petitioner has established a reasonable likelihood that it would prevail in showing that the combination of Arai and Fenwick teaches or suggests each element of claim 1 of the ’428 patent. See 35 U.S.C. § 314(a).” slip op. at 27

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “At this stage of the proceeding and on the present record, we adopt Petitioner’s uncontested, proposed level of ordinary skill in the art, which we find consistent with the level of ordinary skill in the art reflected by the ’428 patent and the prior art of record. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978).” slip op. at 9

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation foundInstituted

      “Relying on the Declaration of Jean Renard Ward, Petitioner contends that “[a] POSITA would have been motivated to incorporate[] Fenwick’s teachings regarding automatically sending recognized words to an application into Arai because this would have furthered Arai’s purpose of having a natural, uninterrupted flow in entering characters without having to press extra keys.” Pet. 31–32 (citing Ex. 1002 ¶ 139). Petitioner concludes that the combination would have been obvious in that it would apply Fenwick’s known technique for recognizing words without additional user confirmation to Arai’s known method of performing handwriting recognition, ready for improvement, to yield the predictable result of the Arai/Fenwick combination: “recognition results are sent to an application without further user confirmation—e.g., pressing the Enter Key—and handwritten character recognition results are removed from the temporary memory such as RAM when the recognition results are sent to the application.” Id. at 32 (citing Ex. 1002 ¶ 140).” slip op. at 18

    § 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 9,026,428
Page 1 of 15
← Previous12345…Next →

Holdings, summaries, rulings, issues, outcomes, winners and claim constructions shown for a decision were generated by a large language model reading the opinion. They are a guide to the decision, not the decision. Confirm every one against the court's own text before relying on it. Outcomes read from the patent owner’s side. Party names are extracted from the decision and are missing on about 900 short Director denials and scans, which carry the trial number instead.