  • PTAB · Oct 10, 2025 · IPR2025-00652 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–23 and 25–30 were unpatentable over the asserted grounds.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’403 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 12

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededOther

      “The parties assert that each claim term should be construed in accordance with its plain and ordinary meaning. Pet. 10; Prelim. Resp. 4 (citing Ex. 2009 ¶ 73); see Ex. 1002 ¶ 22 (opining the same). And, in the respective claim construction sections of their briefs, the parties do not propose any claim terms for express construction. We agree with the parties that no claim terms require express construction to resolve the controversy before us. See Realtime Data, 912 F.3d at 1375.” slip op. at 13

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “We agree with Patent Owner that the Petition fails to demonstrate that Kahn discloses element [1.2] because the evidence cited does not disclose a “first computer system being configured to provide remote control of the first pump or first valve” (i.e., a fluid-handling device). Kahn is directed to providing access to fluid sensing data and analyzing and providing visual information on that data, but Petitioner has not identified any disclosure of the capability to remotely control fluid-handling devices. See, e.g., Ex. 1005, code (54), 1:27–36, 2:50–3:2. More specifically, Kahn’s disclosures that Petitioner relies on for allegedly teaching remote control are deficient. We discuss each. First, Petitioner points to the following, “[f]or instance, as illustrated in FIG. 1C, a fluid control device such as a valve 15A is located on the input side of a sen[s]or unit 110.” Ex. 1005, 8:19–21, cited in Pet. 13. This portion of Kahn, however, does not disclose remote control. Second, Petitioner cites to the following: Finally, or in addition to, the communication unit 112B can include on-site alerts such as optical (indicator lights), audible alerts (e.g., alarm sounds), tactile (e.g., vibration of the unit) or can be interfaced to an appropriate control valve for simply shutting off the supply of fluid upon the detection of emergency events, for instance. Pet. 13 (citing Ex. 1005, 10:62–67). We agree with Patent Owner that this portion of Kahn teaches on-site alerts and local control of the fluid-handling device. See Prelim. Resp. 7. This portion of Kahn does not disclose remote control.” slip op. at 18

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,294,403
  • PTAB · Oct 10, 2025 · IPR2025-00651 · APJ Bart A Gerstenblith · IPR · Institution

    The Board denied institution because Petitioner did not show a reasonable likelihood that claims 1–3, 6, 7, and 9–20 were unpatentable over any asserted ground.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)Institution denied meritsDenied

      “presented in the petition . . . and any [preliminary] response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2024). For the reasons given below, on this record Petitioner has not established a reasonable likelihood that it would prevail in showing the unpatentability of any of the Challenged Claims. Accordingly, we do not institute an inter partes review.” slip op. at 2

    • Skill levelSkill level patent owner adoptedDecided for patent owner

      “The parties’ proposed levels of ordinary skill in the art are similar, although Patent Owner proposes two years of experience along with a bachelor’s degree whereas Petitioner proposes “significant” experience. Patent Owner also proposes an alternative with more extensive experience in lieu of a bachelor’s degree. Although we find Petitioner’s proposed qualifications acceptable, we adopt Patent Owner’s proposed qualifications for the purposes of this Decision because they offer a wider range of qualifications that nonetheless comport with the level of ordinary skill necessary to understand and implement the teachings of the ’680 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978). Our analysis and findings herein, however, do not turn on any differences in the parties’ proposed qualifications.” slip op. at 11

    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed patent owner constructionDecided for patent owner

      “target value” is part of a command that is sent from a computing device to a server and then to a controller. The controller then receives a measurement of the fluid by a sensor and determines whether the measurement satisfies the “target value.” If the measurement does not satisfy the “target value,” further operations are undertaken. The recited operation sequence makes clear that the plain and ordinary meaning of “target value” is not as Dr. Wooley opines because the particular operating condition that a device is in at a particular time is represented by the measurement taken by the sensor, 11 Some claim language less relevant to construing “target value” was omitted for ease of reference. which the controller then uses to determine whether the measurement satisfies the “target value.” Additionally, claim 1 recites that the “target value” is sent as part of a command to the controller. The “target value” is not sent to the controller from the sensor, as might be expected if the plain and ordinary meaning of “target value” were as Dr. Wooley opines. Petitioner and Dr. Wooley’s construction would also result in “target value” meaning effectively the same thing as the measurement of the fluid by the sensor, a concept that is separately recited in claim 1 and to which the “target value” is compared. The Specification of the ’680 patent does not support Petitioner’s understanding of the plain and ordinary meaning of “target value.” Although the Specification does not recite “target value,” it recites “target state,” and describes “target state” sufficiently to understand the plain and ordinary meaning of “target” as used in “target value” and “target state.” In particular, the ’680 patent explains that “[i]n some embodiments, the process 104 includes receiving, via a network interface, from a remote user device, (e.g., via a command-center server) a command to change a state of a fluid-handling device to a target state.” Ex. 1001, 11:48–51. This portion reflects that the command is seeking to change a state of a fluid-handling device to a target state. In other words, the “target value” or “target state” is not generally “the particular operating condition that a device is in at a particular time”; rather, it is a value or state that the fluid-handling device is desired to be in, as Patent Owner and Dr. Durham explain. Additionally, just as claim 1 recites a directional component for the “target value” to be sent to the controller in a command, so too does the Specification describe a “target state” as being sent in a command from a remote user device. Thus, the Specification clearly supports the plain and ordinary meaning proposed by Patent Owner and Dr. Durham and not the plain and ordinary meaning proposed by Petitioner and Dr. Wooley. slip op. at 14

    • Novelty / Anticipation (§102) › Anticipation standard (single reference, every element)Not shown unpatentableNot shown unpatentable

      “time-stamped process data, report exception therein to the remote host, and extract and transmit time-stamped process data to the remote host.” Ex. 1005, Abst. (emphases added). Almadi explains that its remote field systems must include a plurality of controller units “to issue commands to, and gather and process data from a plurality of field devices, including remote systems and instruments, . . . [and] a database server for the storage of process data retrieved from the remote subsystems and instruments.” Id. at 2:22–30 (emphases added). Based on these disclosures, we agree with Patent Owner that Petitioner has not established that Almadi discloses element [1.4]. Specifically, the teachings from Almadi identified by Petitioner refer to process data, which is data retrieved from the remote subsystems/field devices. Thus, we understand that Almadi’s teaching—of using an Ethernet switch to transmit “process data”—describes transmitting data from the remote subsystems/field devices. See Ex. 1005, 3:13–17, cited in Pet. 15. But claim 1 and particularly element [1.4], recites “sending, with the server, the target value to the network address [which identifies a controller of the fluid-handling device13] via the network,” which is different than sending process data from the field devices to the remote host or database server for storage.” slip op. at 19

    Claim construction§ 102 anticipation§ 103 obviousnesscites Phillips · KSR · Graham
    Patents in suitUS 11,175,680
  • PTAB · Mar 18, 2025 · IPR2023-01383 · APJ Kimberly Mcgraw · IPR · Final written decision

    Claims 1–5 were not shown unpatentable because Petitioner did not sufficiently establish a reason to modify the asserted prior art.

    RulingsFinal written decision
    • Expert testimonyPatent owner expert creditedDecided for patent owner

      “We disagree with Petitioner’s argument because it fails to address Dr. Schubert’s academic and other experience with GaN transistors. Dr. Schubert is currently a tenured full professor in the Department of Electrical Computer, and Systems Engineering at Rensselaer Polytechnic Institute and was previously a tenured full professor in the Department of Electrical and Computer Engineering at Boston University. Ex. 2001, 129. Additionally, Dr. Schubert was the director of Boston University’s Semiconductor Devices Research Laboratory. Ex. 2001, 129. Dr. Schubert persuasively explains that his general expertise is in the field of electrical engineering and applied physics, including semiconductors, processing, and devices and his specific expertise is in the field of semiconductor materials (such as GaN), semiconductor devices, semiconductor integrated circuits, ohmic contacts, Schottky contacts, HEMTs, and optoelectronic devices such as light-emitting diodes (LEDs). Ex. 2001 ¶ 11, App’x A pp.129–137. His experience includes “the design, growth, fabrication, and testing of semiconductor devices as well as the employment of these devices in a variety of applications” and he is “familiar with both the design of such transistors [HEMTs] and the manufacturing processes used for FETs. Ex. 2001 ¶ 11, App’x A, pp. 129–137. He is an author or co-author of numerous text books and articles, and co-inventor of numerous patents, including those dealing with HEMT transistors and GaN devices. Ex. 2001 ¶ 13, App’x A, pp. 129–137. Petitioner fails to present any persuasive argument or evidence that Dr. Schubert’s extensive education and experience regarding GaN transistors is insufficient or lacking such that his testimony should be given little weight. Finally, we disagree with Petitioner’s additional argument that that its expert’s testimony (Dr. Shealy) should be given more weight than Patent Owner’s expert’s testimony (Dr. Schubert) because “[u]nlike Dr. Schubert, Dr. Shealy is one of the pioneer scientists in the field of GaN transistors.” Reply 34 (stating that Dr. Shealy’s research lab built the first GaN HEMT device on silicon in 1999 and citing Ex. 2002, 87:19–238). Obviousness is determined through the lens of a “person of ordinary skill in the art,” not through the lens of a person with extraordinary skill or a pioneer in the field. Given Dr. Schubert’s extensive relevant education and experience, Petitioner does not persuasively explain why Dr. Shealy’s testimony on any specific topic, or his testimony in general, should be given more weight than Dr. Schubert’s.” slip op. at 16

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “understanding of a person of ordinary skill in the art (sometimes abbreviated herein as “POSITA”). Graham, , 383 U.S. at 17–18. Petitioner argued that a person of ordinary skill in the art would have had a “at least a four-year degree in electrical engineering, chemical engineering, physics, or material science or a closely related field and at least two years of experience in semiconductor device design or fabrication, including the processing of semiconductor materials, analysis of device operation, or the development of new device topologies. Additional education could substitute for professional experience and vice versa.” Pet. 11 (citing Ex 1003 ¶ 69). Patent Owner did not dispute this proposed definition prior to institution. See generally Prelim. Resp. In our Decision on Institution, we adopted Petitioner’s proposal. After institution, Patent Owner asserted a slightly different definition of a POSITA, namely someone who “would have possessed at least a four-year degree in electrical engineering, physics, material science, or a closely related field, and three years of professional work experience in the epitaxial growth, design, and fabrication of semiconductor electronic devices, including those of GaN.” Resp. 17. Relevant graduate education could substitute for the professional work experience. Id. Upon review of the full record, we see no reason to modify, and we thus maintain, the definition of a POSITA applied in our Decision on Institution. We also determine that our decision would be the same under either of the parties’ proposed definitions.” slip op. at 14

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)Not reached

      “During the proceeding, the parties also dispute the proper construction of “etching away the doped GaN layer, except a portion of the doped GaN layer beneath the gate contact” as recited in step [1e4] and provided briefing on this issue. Papers 35, 36, 37, 38. Because, as explained below, our determination rests upon Petitioner’s failure to show a sufficient reason to modify the asserted art, which is not dependent upon any particular claim construction, we need not, and do not, address these claim construction issues. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (citing Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)) (holding that only claim terms in controversy need to be construed, and only to the extent necessary to resolve the controversy).” slip op. at 13

    • ExcludeDenied

      “III. PETITIONER’S MOTION TO EXCLUDE EXHIBIT 2008 Petitioner filed a Motion to Exclude (Paper 25, “Mot.”) Exhibit 2008, which is a hearing transcript from the parallel ITC investigation. Mot. 1. Because we do not rely upon Exhibit 2008 in our Decision, we dismiss Petitioner’s motion as moot.” slip op. at 47

    Patent outcomesUS 8,404,508 not shown unpatentable
    Claim construction§ 103 obviousnesscites Phillips · KSR
    Patents in suitUS 8,404,508
  • PTAB · Jan 31, 2025 · IPR2024-00979 · APJ Lisa A Murray · IPR · Institution

    The Board instituted inter partes review of claims 1–18 on all four asserted obviousness grounds, finding a reasonable likelihood that Dolan renders at least one challenged claim unpatentable.

    RulingsInstitution decision
    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “As set forth in the Director’s Memorandum, Interim Procedure for Discretionary Denials in AIA Post-Grant Proceedings with Parallel District Court Litigation (dated June 21, 2022), at 7, available at https://www.uspto. gov/sites/default/files/documents/interim_proc_discretionary_denials_aia_ parallel_district_court_litigation_memo_20220621_.pdf, the PTAB will not discretionarily deny institution of an IPR . . . in view of parallel district court litigation where a petitioner stipulates not to pursue in a parallel district court proceeding the same grounds as in the petition or any grounds that could have reasonably been raised in the petition. Petitioner’s stipulation (Ex. 1018) satisfies the language from the Director’s Memorandum quoted above. Therefore, we need not analyze each Fintiv factor to reach the determination that we will not exercise our discretion to deny institution in view of the parallel Eastern District of Texas Litigation.” slip op. at 7

    • PTAB / AIA Trials › Real party in interest / privityNot reached

      “Electronics, America, Inc.; and Google LLC as real parties in interest. Pet. 57. Petitioner explains that “Google LLC is a subsidiary of XXVI Holdings Inc., which is a subsidiary of Alphabet Inc.” Id. at 57 n.10. Petitioner asserts that “XXVI Holdings Inc. and Alphabet Inc. are not real parties-in-interest to this proceeding.” Id. Patent Owner identifies Cerence Operating Co., a subsidiary of Cerence, Inc., as a real party in interest. Paper 5, 1. Patent Owner disagrees with Petitioner, contending that Alphabet Inc. is also a real party in interest. Id. At this stage of the proceeding, we need not determine whether Alphabet Inc. is a real party in interest to Petitioner since neither Petitioner nor Patent Owner has identified any effect that determination would have on the outcome of this proceeding. To the extent Patent Owner seeks to maintain this contention, it should raise the issue in its Patent Owner response.” slip op. at 3

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Patent Owner does not currently take a position on the relevant level of ordinary skill in the art and believes that “the Board could assume Petitioner’s proposed level of ordinary skill for the purposes of deciding whether to institute.” Prelim. Resp. 3. At this stage of the proceeding and on the present record, we adopt Petitioner’s uncontested, proposed level of ordinary skill in the art, which we find consistent with the level of ordinary skill in the art reflected by the ’993 patent and the prior art of record. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978).” slip op. at 10

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)Plain and ordinary meaningOther

      “Additionally, only terms that are in controversy need to be construed, and these need to be construed only to the extent necessary to resolve the controversy. See Realtime Data, LLC v. Iancu, 912 F.3d 1368, 1375 (Fed. Cir. 2019) (“The Board is required to construe ‘only those terms . . . that are in controversy, and only to the extent necessary to resolve the controversy.’”) (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999)). At this time, neither party proposes a specific construction of any given claim term, instead requesting that the claims be given their plain and ordinary meaning. Pet. 10–11; Prelim. Resp. 5.” slip op. at 11

    Claim construction§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 8,081,993
  • PTAB · Dec 16, 2024 · IPR2024-01005 · APJ Julia Heaney · IPR · Institution

    The Board instituted IPR on claims 1–23 and all asserted grounds, finding a reasonable likelihood that at least one challenged claim would have been shown unpatentable.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “Institution of an inter partes review is authorized by statute when “the information presented in the petition . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a) (2018). Upon consideration of the Petition, the Preliminary Response, and the evidence of record, we determine that Petitioner has established a reasonable likelihood that it would prevail in showing the unpatentability of at least one claim challenged in the Petition. We also determine that the arguments and evidence of record do not support discretionary denial under 35 U.S.C. § 314(a). Accordingly, we institute an inter partes review of all claims and all grounds asserted in the Petition.1” slip op. at 2

    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “under the sixth Fintiv factor only after a determination that the first five Fintiv factors favor discretionary denial. CommScope, 4–5. Here, we do not find the first five factors cumulatively weigh in favor of discretionary denial. Therefore, we determine that the circumstances here do not warrant an analysis of whether the Petition presents compelling merits, and the considerations of the sixth Fintiv factor weigh against exercising discretionary denial. F. Conclusion Having considered the parties’ arguments in view of the Fintiv factors, and taking into account Petitioner’s stipulation, we determine that the circumstances here do not warrant exercising discretion under § 314(a) to deny institution. IV.” slip op. at 35

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededNot reached

      “Thus, although both parties indicate that no claim construction is necessary at this stage of the proceeding, it is apparent that they disagree as to the meaning of “discrete carbon nanotubes.” While Petitioner appears to construe “discrete carbon nanotubes” as “nanotubes that are generally individually distinct” (Pet. 13), Patent Owner argues a more restricted construction requiring that “discrete carbon nanotubes” not be reacted with other components. Prelim. Resp. 3. The evidence relating to claim 10 In quotations from the Preliminary Response throughout this Decision, we have retained bolding and underlining added to the text by Patent Owner. construction that Patent Owner offers on the current record, however, does not address its proposed restriction. See id. at 9, n. 4, citing Ex. 1001, 3:9, 5:39–40 (“The ’649 Patent describes the ‘discrete carbon nanotubes’ as, for example, ‘individually dispersed’, ‘individualized carbon nanotubes’, ‘dispersed as individual nanotubes’, and ‘essentially discrete individual fibers, not entangled as a mass.’”). As discussed in Section II.D.2 below, we determine based on the record at this stage of the proceeding that Petitioner demonstrates sufficiently for purposes of institution that Sun discloses or suggests “discrete carbon nanotubes.” Therefore, we do not explicitly construe any claim terms in this Decision. See Nidec Motor Corp. v. Zhongshan Broad Ocean Motor Co., 868 F.3d 1013, 1017 (Fed. Cir. 2017) (“we need only construe terms ‘that are in controversy, and only to the extent necessary to resolve the controversy’” (quoting Vivid Techs., Inc. v. Am. Sci. & Eng’g, Inc., 200 F.3d 795, 803 (Fed. Cir. 1999))). If either party intends to argue a claim construction at trial, however, including what is the ordinary meaning of a term, they should do so in a clearly designated section of their briefing. See Patent Trial and Appeal Board Consolidated Trial Practice Guide (Nov. 21, 2019) (“CTPG”), 46, 49 (available at https://www.uspto.gov/TrialPracticeGuideConsolidated); O2 Micro Int’l Ltd. v. Beyond Innovation Tech. Co., 521 F.3d 1351, 1361 (Fed. Cir. 2008) (“A determination that a claim term ‘needs no construction’ or has the ‘plain and ordinary meaning’ may be inadequate when a term has more than one ‘ordinary’ meaning or when reliance on a term’s ‘ordinary’ meaning does not resolve the parties’ dispute.”). Claim construction arguments should not be relegated to patentability arguments on the facts.” slip op. at 7

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “Petitioner argues a person of ordinary skill in the art at the time of the invention “would have had at least [a] Master’s degree in materials science, chemistry, chemical engineering, a field relevant to polymer science and engineering, or the equivalent, and at least three years of experience in nanomaterials, electrochemistry, batteries, or polymer related activities.” Pet. 5 (citing Ex. 1003 ¶ 19). Petitioner further argues that “[a]dditional work experience can compensate for less formal education, and vice versa.” Id. Patent Owner does not dispute the level of ordinary skill in the art. Prelim. Resp. 4. For purposes of this decision, we adopt Petitioner’s definition of the level of ordinary skill in the art because it is consistent with the ’649 patent and the asserted prior art.” slip op. at 9

    Claim construction§ 103 obviousnessDiscretionary denialcites KSR · Graham
    Patents in suitUS 9,636,649
  • PTAB · Nov 26, 2024 · IPR2024-00936 · APJ Bart A Gerstenblith · IPR · Institution

    The Board instituted IPR on all challenged claims and grounds, finding a reasonable likelihood that claims 1, 5, 8, 9, 11–19, 23, 26, 27, and 29–36 are obvious over Tayloe, TI Datasheet, and Macnally.

    RulingsInstitution decision
    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “https://www.uspto.gov/sites/default/files/documents/interim_proc_discretion ary_denials_aia_parallel_district_court_litigation_memo_20220621_.pdf, the PTAB will not discretionarily deny institution of an IPR . . . in view of parallel district court litigation where a petitioner stipulates not to pursue in a parallel district court proceeding the same grounds as in the petition or any grounds that could have reasonably been raised in the petition. Petitioner’s stipulation (Ex. 1041) satisfies the language from the Director’s Memorandum quoted above. Therefore, we need not analyze each Fintiv factor to reach the determination that we will not exercise our discretion to deny institution in view of the parallel Western District of Texas Litigation.” slip op. at 11

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “Accordingly, on the present record at this stage of the proceeding and for the reasons discussed above, we find that Petitioner has shown a reasonable likelihood of establishing that one of ordinary skill in the art would have been motivated to combine the teachings of Tayloe, TI Datasheet, and Macnally with a reasonable expectation of success. Patent Owner is invited to elaborate further on its positions in future briefing with potential expert support.” slip op. at 35

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “person of ordinary skill in the art at the time of the invention would have had “at least a bachelor’s degree in electrical engineering or a related subject and two or more years of experience in the field of EM circuit design.” Pet. 6 (citing Ex. 1003 ¶¶ 68–71). Petitioner further proposes that “[l]ess work experience may be compensated by a higher level of education, such as a master’s degree.” Id. Patent Owner does not take a position, in the Preliminary Response, on the level of ordinary skill in the art. See generally Prelim. Resp. On the present record at this stage of the proceeding, we adopt Petitioner’s uncontested, proposed level of ordinary skill in the art, which we find consistent with the level of ordinary skill in the art reflected by the ’528 patent and the prior art of record. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d 1573, 1579 (Fed. Cir. 1995); In re Oelrich, 579 F.2d 86, 91 (CCPA 1978).” slip op. at 12

    • Prior constructionPrior construction adoptedTerm construed petitioner constructionDecided for petitioner

      “their plain and ordinary meaning, with one exception. Pet. 3. Specifically, Petitioner asserts “storage element” or “energy storage element” are recited “interchangeably” in the claims and should each be construed to mean “an element of a system that stores non-negligible amounts of energy from an input EM signal,” which Petitioner notes was “determined by the Board and affirmed by the [U.S. Court of Appeals for the] Federal Circuit.” Id. (citing ParkerVision, Inc. v. Vidal, 88 F.4th 969, 976 (Fed. Cir. 2023) (holding “ParkerVision acted as its own lexicographer to define the term ‘storage element’” and “the Board’s construction of ‘storage element’ [(quoted above)] correctly tracks the lexicography provided by [ParkerVision]”) (citing U.S. Patent No. 6,061,551 (“the ’551 patent”), 66:55–67)). Petitioner contends that, like U.S. Patent No. 7,110,444 that was at issue in ParkerVision v. Vidal, the ’528 patent also incorporates the ’551 patent by reference. Pet. 4 (citing Ex. 1001, 1:30–34). And Petitioner notes that the ’528 patent “includes an identical disclosure to that deemed dispositive from the incorporated by reference ’551 patent.” Id. (citing Ex. 1001, 73:9–22 (which Petitioner contends defines “storage module”)). Further, Petitioner asserts “[n]o intrinsic evidence demands a different construction” because, even though claim 1 recites “system,” “energy,” and “transfer,” it does so “in isolation” and “does not recite ‘energy transfer system,’ let alone restrict the claimed ‘storage element’ to any energy transfer system.” Id. at 5 (also contending the file history of the ’528 patent does not support a different construction). Petitioner also contends “the proposed combinations teach the claimed ‘storage element’ or ‘energy storage element,’ even including the alleged condition of ‘low impedance load’ that purportedly ‘goes to the heart of what makes an element, a “storage” element.’” Id. Patent Owner does not take a position on claim construction in the Preliminary Response. See generally Prelim. Resp. On the present record at this stage of the proceeding, we agree with Petitioner, for the reasons discussed above, that “storage element” and “energy storage element” are used interchangeably in the claims and should be construed consistently with our prior construction of “storage element,” which, as noted above, was affirmed by the Federal Circuit, to mean “an element of a system that stores non-negligible amounts of energy from an input EM signal.” We need not construe any other claim terms expressly because there is no present controversy as to the meaning of any other claim terms in this proceeding. Realtime Data, 912 F.3d at 1375.” slip op. at 14

    Claim construction§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 9,118,528
  • PTAB · Nov 26, 2024 · IPR2024-00796 · APJ Iftikhar Ahmed · IPR · Institution

    The Board instituted IPR on claims 1–20, finding a reasonable likelihood that claims 1 and 11 would be obvious over Nevo and Avitabile.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “review. See 35 U.S.C. § 314 (2018); 37 C.F.R. § 42.4(a) (2022). To institute an inter partes review, we must determine that the information presented in the Petition shows “a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a). Based on the information presented in the Petition and the supporting evidence, we are persuaded that there is a reasonable likelihood that Petitioner would prevail with respect to at least one of the challenged claims. Accordingly, we institute an inter partes review of the challenged claims on the grounds set forth in the Petition.” slip op. at 2

    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “Stipulate[s] and agree[s] that, if the PTAB institutes an inter partes review proceeding (“IPR”) for U.S. Patent No. 7,483,686 on the grounds presented in [the Petition], [Petitioner] will not pursue an invalidity defense in [the Western District of Texas Litigation] that the patent claims subject to the instituted IPR are invalid based on the same grounds as in the [P]etition or any grounds that could have reasonably been raised in the [P]etition. Ex. 1015 (letter from M. Bernstein to J. Charkow, dated May 21, 2024); see also Prelim. Reply 1 (“Patent Owner’s Preliminary Response (Paper 6) fails to acknowledge, much less address, Petitioner’s Sotera stipulation not to pursue in the related litigation the same grounds or any grounds of invalidity that could reasonably have been raised in this IPR.”); Sotera Wireless, Inc. v. Masimo Corp., IPR2020-01019, Paper 12 (Dec. 1, 2020) (Decision Granting Institution) (precedential as to § II.A).” slip op. at 8

    • Skill levelSkill level petitioner adoptedDecided for petitioner

      “would have had at least a bachelor’s degree in electrical engineering or a related subject and two or more years of experience in the field of [radio frequency (‘RF’)] circuit design, or at least five years of work experience and training in the design and development of RF circuits and/or systems,” and “[l]ess work experience may be compensated by a higher level of education, such as a master’s degree.” Pet. 14–15 (citing Ex. 1002 ¶ 38). Patent Owner does not address the level of ordinary skill in the art in its Preliminary Response. See generally Prelim. Resp. We determine, on the current record, that Petitioner’s proposed level of ordinary skill is consistent with the ’686 patent and the asserted prior art. See Okajima v. Bourdeau, 261 F.3d 1350, 1355 (Fed. Cir. 2001); In re GPAC Inc., 57 F.3d at 1579. We adopt that level of ordinary skill in the level of ordinary skill in the art based on the full trial record. slip op. at 10

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)No construction neededNot reached

      “Petitioner contends that all claim terms should be given their plain and ordinary meaning. Pet. 15 (citing Ex. 1002 ¶ 74). Petitioner, however, notes that several claim terms in the ’686 patent, or closely related claim terms for patents related to the ’686 patent, have been construed during prior litigation involving Patent Owner. Id. Petitioner discusses five claim terms and various constructions proposed or adopted in prior litigation. Id. at 15–20.” slip op. at 11

    Claim construction§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 7,483,686
  • PTAB · Nov 13, 2024 · IPR2023-00900 · APJ Jon B Tornquist · IPR · Final written decision

    Claims 13–17 were not shown unpatentable: Lee-based grounds fail on the stackable add-on layer limitation, and Watanabe-based grounds fail on nonvolatile memory, enablement, or motivation to combine.

    RulingsFinal written decision
    • Claim Construction › Intrinsic evidence (Phillips canons) › Plain and ordinary meaning to a POSITATerm construed board ownDecided for petitioner

      “meaning in the art. See Irdeto Access, Inc. v. Echostar Satellite Corp., 383 F.3d 1295, 1300 (Fed. Cir. 2004) (stating that, absent an accepted meaning in the art, “we construe a claim term only as broadly as provided for by the patent itself”). Thus, we must attempt to discern the meaning of this term from the claim language itself and from the remainder of the intrinsic record. See Vitronics Corp. v. Conceptronic, Inc., 90 F.3d 1576, 1582 (Fed. Cir. 1996) (“It is well-settled that, in interpreting an asserted claim, the court should look first to the intrinsic evidence of record, i.e., the patent itself, including the claims, the specification and, if in evidence, the prosecution history.”). Upon review of the parties’ arguments and the intrinsic record, we agree with Petitioner that the ’702 patent does not support a construction of “stackable add-on layer” that encompasses memory cells formed by sequential deposition on a substrate without being formed and then added to a separately formed substrate.” slip op. at 10

    • Obviousness (§103) › Graham factors (scope of art, differences, level of skill)Not shown unpatentableNot shown unpatentable

      “As discussed above, we construe “stackable add-on layer” to not include memory cells that are formed by sequential deposition on or above a substrate without being added to a separately formed substrate. It is undisputed, and indeed it is Petitioner’s assertion, that Lee’s memory devices are formed by sequential deposition. See Pet. 52 (asserting that in Lee “the layers of the array are directly deposited on the layers of each underlying level, and the array is deposited on the interlayer insulating layer formed over a substrate”); see also id. at 70 (“Lee discloses forming vertical memory devices through layer-by-layer sequential deposition on the substrate . . . .”). Therefore, Petitioner does not show that Lee discloses every limitation of independent claim 13 under our claim construction. Thus, Petitioner does not demonstrate by a preponderance of the evidence that claim 13 would have been obvious in view of Lee. 3. Claims 14 and 15 Claims 14 and 15 depend from claim 13. Ex. 1001, 12:35–42. Petitioner’s arguments for these claims do not remedy the deficiencies noted above with respect to independent claim 13. Pet. 54–59. Accordingly, Petitioner does not demonstrate by a preponderance of the evidence that claims 14 and 15 would have been obvious in view of Lee alone. E. Claims 16 and 17 over Lee and Endoh Petitioner contends the subject matter of claims 16 and 17 would have been obvious over the combined disclosures of Lee and Endoh. Pet. 59–69. Petitioner’s arguments with respect to these claims, however, do not remedy the deficiencies noted above with respect to Lee and its monolithic, sequentially deposited memory array. Accordingly, Petitioner does not demonstrate by a preponderance of the evidence that claims 16 and 17 would have been obvious over Lee and Endoh.” slip op. at 18

    • Obviousness (§103) › Motivation to combine / reasonable expectation of successMotivation not foundNot shown unpatentableNot shown unpatentable

      “combined Lee and Watanabe to achieve improved integration density. Pet. 71. Petitioner concedes, however, that the benefits of Lee’s design related to 3-D integration and improved integration density would be obtained if Lee’s memory structures are formed using either Lee’s monolithic construction method or Watanabe’s alternative stacking method. Pet. Reply 13–14 (citing Ex. 1041 ¶ 34). Thus, we are not persuaded that improved integration density provides a sufficient rationale for Petitioner’s combination of Lee’s memory device and Watanabe’s stacking method. Petitioner argues that Watanabe’s stacking method “improves the accuracy of the wiring” because the wiring is made “for each planar member.” Pet. 72 (citing Ex. 1005, 6:1–3). Watanabe also states that its disclosed methods provide “a low interconnection wire resistance.” Ex. 1005, 6:20–23. Petitioner does not, however, explain sufficiently how Watanabe’s stacking method would improve Lee’s device. For example, Petitioner does not address whether the alleged wiring benefit already existed in Lee’s monolithic array or explain how this benefit would also apply to Lee’s particular memory array, which differs in construction and elements from Watanabe’s device. This diminishes Petitioner’s benefits-based motivation to combine arguments. In general, a petitioner need not demonstrate that a particular alternate method would improve a prior art device in order to show a motivation to combine. Intel Corp. v. PACT XPP Schweiz AG, 61 F.4th 1373, 1380–81 (Fed. Cir. 2023); see Pet. Reply 20 (citing Intel). But here, Petitioner affirmatively invokes improvement of Lee’s device as a reason for the combination, and we must evaluate Petitioner’s contention. Moreover, any relative lack of improvement or benefits must be weighed against any problems the alternative method would introduce. See Intel Corp. v. Qualcomm Inc., 21 F.4th 784, 795–96 (Fed. Cir. 2021) (noting that simultaneous advantages and disadvantages to a proposed combination must be analyzed to determine whether the disadvantages “outweighed any reason to combine”). Here, as discussed above in more detail with respect to the ground based on Watanabe, the evidence shows that one of ordinary skill in the art would have expected Watanabe’s bonding temperature of 900– 1000° C to damage the electronic devices in an underlying substrate. Ex. 2029 ¶¶ 75–76; Ex. 2028, 123:13–124:7; Ex. 2027, 715. The expected damage to Lee’s device, when balanced against the limited evidence of a benefit to the combination,7 outweighs the reason to combine Lee and Watanabe set forth in the Petition. Accordingly, Petitioner does not demonstrate by a preponderance of the evidence that claim 13 would have been obvious over Lee and Watanabe. 2. Analysis – Claims 14 and 15 Claims 14 and 15 both depend directly from independent claim 13. Ex. 1001, 12:35–42. Petitioner’s arguments with respect to claims 14 and 15 do not remedy the deficiencies noted above with respect to independent claim 13. Pet. 73. Accordingly, Petitioner does not demonstrate by a preponderance of the evidence that these claims would have been obvious over Lee and Watanabe.” slip op. at 40

    • Expert testimonyPatent owner expert creditedOther

      “We credit the testimony of Dr. Przybylski that one of ordinary skill in the art would have understood that Watanabe’s stacked structure would be severely impacted if bonded at a temperature above 900° C, as disclosed in Watanabe. Ex. 2029 ¶¶ 76–77. Dr. Przybylski’s opinion is supported by Dr. Lee’s testimony (Ex. 2028, 123:13–124:7, 125:6–126:7), as well as Watanabe (Ex. 1005, 6:6–14) and Batude (Ex. 2027, 715). As further discussed below, we find that Petitioner has not rebutted Patent Owner’s showing of nonenablement, and Patent Owner has carried its burden to demonstrate that Watanabe was not enabled for bonding temperatures of 900–1000° C, as of the 2004 filing date of the ’702 patent.” slip op. at 32

    Patent outcomesUS 7,378,702 not shown unpatentable
    Claim construction§ 103 obviousnesscites KSR · Graham
    Patents in suitUS 7,378,702
  • PTAB · Jul 24, 2024 · IPR2024-00465 · APJ Bart A Gerstenblith · IPR · Institution

    The Board instituted IPR on claims 1–24 on all petition grounds, finding a reasonable likelihood that Irwin renders at least one challenged claim obvious.

    RulingsInstitution decision
    • Other 314aInstitution denied discretionary otherDenied

      “Even assuming Linq3 is a real party in interest to Petitioner and assuming we may exercise our discretion to deny institution based on unclean hands (see Kavo Dental Techs, LLC v. Osseo Imaging, Inc., IPR2020-00659, Paper 10 at 19 (PTAB June 10, 2020)), Patent Owner essentially asks us to resolve multiple factual issues related to its contract dispute with Linq3 to justify denial of institution. See, e.g., Prelim. Resp. 1– 26. Many, if not all, of these issues appear to be involved in the contract dispute, which will be resolved by the Arizona state court. We are not in a good position to make determinations about these particular issues at this stage of the proceeding, on the limited record before us. Rather, we find that the state court is better suited to address the conduct of Linq3 of which Patent Owner complains. Accordingly, we leave these matters for the state court. To the extent Patent Owner seeks to pursue its argument that Linq3 is a real party in interest to Petitioner, even though no time bar under 35 U.S.C. § 315(b) has been asserted, Patent Owner may raise the issue of real party in interest again in its Patent Owner Response, and the parties may brief and argue the issue during trial.” slip op. at 10

    • PTAB / AIA Trials › Discretionary denial › General Plastic (serial petitions)Institution denied general plasticDenied

      “We disagree. First, we agree with Patent Owner that the fact pattern presented here is not the typical situation in which the factors from General Plastic are considered. In particular, this proceeding challenges claims of a different patent than the patents at issue in PGR2020-00084 and IPR2023- 01235. Challenging claims of different patents significantly distinguishes the facts here from those in General Plastic, and we decline Patent Owner’s invitation to extend General Plastic in this regard. Accordingly, we do not exercise our discretion to deny institution.” slip op. at 11

    • PTAB / AIA Trials › Real party in interest / privityNot reached

      “Even assuming Linq3 is a real party in interest to Petitioner and assuming we may exercise our discretion to deny institution based on unclean hands (see Kavo Dental Techs, LLC v. Osseo Imaging, Inc., IPR2020-00659, Paper 10 at 19 (PTAB June 10, 2020)), Patent Owner essentially asks us to resolve multiple factual issues related to its contract dispute with Linq3 to justify denial of institution. See, e.g., Prelim. Resp. 1– 26. Many, if not all, of these issues appear to be involved in the contract dispute, which will be resolved by the Arizona state court. We are not in a good position to make determinations about these particular issues at this stage of the proceeding, on the limited record before us. Rather, we find that the state court is better suited to address the conduct of Linq3 of which Patent Owner complains. Accordingly, we leave these matters for the state court. To the extent Patent Owner seeks to pursue its argument that Linq3 is a real party in interest to Petitioner, even though no time bar under 35 U.S.C. § 315(b) has been asserted, Patent Owner may raise the issue of real party in interest again in its Patent Owner Response, and the parties may brief and argue the issue during trial.” slip op. at 10

    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “5. Weighing the Graham Factors “Once all relevant facts are found, the ultimate legal determination [of obviousness] involves the weighing of the fact findings to conclude whether the claimed combination would have been obvious to an ordinary artisan.” Arctic Cat, 876 F.3d at 1361. On balance, considering the record presently before us, Petitioner has established a reasonable likelihood that it would prevail in showing that Irwin would have rendered the subject matter of claims 1–9 and 11–24 of the ’451 patent obvious to one of ordinary skill in the art at the time of the invention.” slip op. at 38

    Claim construction§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 11,488,451
  • PTAB · Jun 11, 2024 · IPR2024-00245 · APJ Nathan A Engels · IPR · Institution

    The Board instituted IPR on claims 1–4 on all asserted grounds, finding a reasonable likelihood that Samsung would show at least one claim unpatentable.

    RulingsInstitution decision
    • PTAB / AIA Trials › Institution threshold (reasonable likelihood / more likely than not)InstitutedInstituted

      “Institution of an inter partes review is authorized by statute when “the information presented in the petition . . . and any response . . . shows that there is a reasonable likelihood that the petitioner would prevail with respect to at least 1 of the claims challenged in the petition.” 35 U.S.C. § 314(a); see 37 C.F.R. § 42.108. Upon consideration of the evidence currently of record, we conclude that the information presented shows that there is a reasonable likelihood that Petitioner would prevail in establishing the unpatentability of at least one challenged claim of the ’150 Patent.” slip op. at 2

    • PTAB / AIA Trials › Discretionary denial › Fintiv (parallel litigation)Denied

      “DISCRETIONARY DENIAL Patent Owner argues that we should exercise our discretion to deny the Petition based on the parallel district court litigation. Prelim. Resp. 35 (citing Apple Inc. v. Fintiv, Inc., IPR2020-00019, Paper 11 at 6 (PTAB Mar. 20, 2020) (precedential)). Petitioner, however, presented a Sotera stipulation.7 Pet. 88 (citing Ex. 1023). Thus, we do not exercise our discretion to deny institution here. See Katherine K. Vidal, Interim Procedure for Discretionary Denials in AIA Post-Grant Proceedings with 7 See Sotera Wireless, Inc. v. Masimo Corp., IPR2020-01019, Paper 12 at 19 (PTAB Dec. 1, 2020) (precedential). Parallel District Court Litigation (June 21, 2022) (“Consistent with [Sotera], the PTAB will not discretionarily deny institution in view of parallel district court litigation where a petitioner presents a stipulation not to pursue in a parallel proceeding the same grounds or any grounds that could have reasonably been raised before the PTAB.”).8” slip op. at 14

    • Claim Construction › Threshold & procedure › Whether a term needs construction (O2 Micro)Term construed petitioner constructionOther

      “Petitioner states that (i) “coded multi-view video signal,” recited in each of the challenged claims, “encompasses a coded video signal for two or more viewpoints, including at least one base viewpoint and at least one nonbase viewpoint” (Pet. 7), and (ii) “picture signal,” also recited in each of the challenged claims, “refers to a signal that represents at least one picture from a viewpoint” (Pet. 9). Petitioner also identifies four elements of claim 1 that Petitioner contends are means-plus-function claim elements under 35 U.S.C. § 112 ¶ 6 (pre-AIA). Patent Owner states that for the purposes of its Preliminary Response, Patent Owner “does not dispute Petitioner’s proposed constructions . . . , including terms that it contends are subject to 35 U.S.C. § 112(6).” Prelim. Resp. 10. At this stage, we apply the parties’ agreed-upon constructions for the purposes of this Decision.” slip op. at 7

    • Obviousness (§103) › Graham factors (scope of art, differences, level of skill)Instituted

      “and DTS are provided in optional fields of packetized elementary stream packets. Ex. 1005, 7:19–25. Further, “[t]he video DTS . . . indicates the time when the picture needs to be decoded by the STD” (Ex. 1005, 7:47– 49), and on the current record, we understand Petitioner to cite the DTS parameters encoded in the transport stream for enhancement layer pictures as teaching the claimed coded information representing a desired delay time. Pet. 33. Among other examples, Petitioner (Pet. 34) and Dr. Reader (Ex. 1005 ¶ 201) cite Chen-736’s example of the formula DTSEi = DTSLi +1.5F, where F is a time interval based on the frame rate (Ex. 1005, 8:9–20), as indicating that DTSEi represents the start of decoding of the ith picture in the enhancement layer being delayed 1.5F relative to the start of decoding of the ith picture frame of the base layer. Pet. 36 (citing Ex. 1003 ¶ 201); see Pet. 35–40 (citing additional examples of serial and parallel decoding with similar DTS calculations). At this stage, we find Petitioner’s position that the claim’s recitation that the coded information must “represent” the desired delay time to be a reasonable reading of the plain language of the claim such that a DTS value can represent the desired delay time even if it requires calculation. Pet. 35 n.8. Even if Chen-736’s use of F-based offsets as time intervals “is different than the concept of a desired delay between decoding” and Chen-736 recognizes the distinction between PTS and DTS (Prelim. Resp. 14–15), on the current record, these arguments do not rebut Petitioner’s mapping of Chen-736 to the claim language. Similarly, Patent Owner’s argument that Chen-736 teaches a DTS for all picture signals, including the base viewpoints and non-base viewpoints (Prelim. Resp. 16), does not rebut Petitioner’s mapping of Chen-736’s enhancement-layer DTS to the claim language. At this stage, on the current record we determine Petitioner has sufficiently shown that Chen-736 teaches or reasonably suggests this claim element.” slip op. at 12

    Claim construction§ 103 obviousnessDiscretionary denialcites Phillips · KSR · Graham
    Patents in suitUS 8,139,150
Page 1 of 11
← Previous12345…Next →

Holdings, summaries, rulings, issues, outcomes, winners and claim constructions shown for a decision were generated by a large language model reading the opinion. They are a guide to the decision, not the decision. Confirm every one against the court's own text before relying on it. Outcomes read from the patent owner’s side. Party names are extracted from the decision and are missing on about 900 short Director denials and scans, which carry the trial number instead.